ML17292A592

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Oct 1996 for WNP-2.W/961011 Ltr
ML17292A592
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/31/1996
From: Kasko B, Galen Smith
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GO2-96-223, NUDOCS 9611190191
Download: ML17292A592 (9)


Text

CATEGORY 1 REGULAT( INFORMATION DISTRIBUTIONOCSTEM (RIDE)

ACCESSION NBR:9611190191 DOC.DATE: 96/10/31 NOTARIZED: NO DOCKET ¹ FACII;:5p-,.397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH.IAIAME AUTHOR AFFILIATION KASKO,B. Washington Public Power Supply System SMITH,G.O. Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly, operating rept for Oct 1996 for WNP-2 Operating License NPF-21.W/961011 ltr.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

E RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD4-2 PD 1 1 COLBURN,T 1 1 0

INTERNAL: 1 1 AEOD/SPD/RRAB 1 1 FILE CENTER 1 1 1 NRR/DRPM/PECB 1 1 R 08/DBA/PAD 1 1 RGN4 1 1 EXTERNAL LITCO BRYCE I J H 1 1 NOAC 1 1 NRC PDR 1 1 D

U NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 11 ENCL 11

~ ~

l

WASHINGTON PUBLIC POWER SUPPLY SYSTEM I'.O. Box 968 ~ 3000 George Washington Way ~ Richland, Washington 99352-0968 ~ (509) 372-5000 October 11, 1996 G02-96-223 Docket No. 50-397 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555 Gentlemen:

Subject:

WNP-2 OPERATING LICENSE NPF-21 MONTHLYOPERATING REPORT OCTOBER 1996 Transmitted herewith is the Monthly Operating Report for the month of October 1996 as required by Technical Specification 6.9.1.6.

Respectfully, G. O. Smith Plant General Manager Mail Drop 9270 cc: LJ Callan - NRC RIV TG Colburn - NRR KE Perkins, Jr. - NRC RIV, WCFO NRC Sr. Resident Inspector - 927N NS Reynolds - Winston & Strawn INPO ANI Library UtilityData Institute DL Williams - BPA / 399 9biii90i9i 9b103i PDR ADOCK 05000397, R PDR

IO 1

4 h I

~4 'J h;

OPERATING STATUS REPORT for WNP-2 Date: November 1, 1996 Docket: 50-397 2.'. Reporting Period: OCTOBER 1996 Outage + On-line Hours: 745.0 Utility

Contact:

Bernice Kasko (509) 377-4473

4. Licensed Thermal Power (MW, ): 3486 Nameplate Rating (Gross MW, ): 1199
6. Design Electrical Rating (Net MW,): 1153
7. Maximum Dependable Capacity - summer (Gross MW,): 1153
8. Maximum Dependable Capacity - summer (Net MW, ): 1107
9. Ifchanges occur above since last report, give reasons: none
10. Power to which restricted, if any (Net MW,): none
11. Reasons for restrictions, if any:

MONTH YEAR CUMULATIVE

12. Report Period Hours 745.0 7,320.0 104,168.2
13. Hours Reactor Critical 745.0 4,772.8 74,408.6
14. Rx Reserve Shutdown Hours 0.0 985.9 1,730.8
15. Hours Generator On-Line 745.0 4,535.6 71,786.1
16. Unit Reserve Shutdown Hours 0.0 997.4 1,956.2
17. Gross Thermal Energy (MWH) 2,432,864 12,400,967 212,858,517
18. Gross Electrical Energy (MWH) 822,140 4,103,520 71,681,000
19. Net Electrical Energy (MWH) 793,218 3,907,623 68,665,941
20. Unit Service Factor 100.0% 62.0% ,68.9%
21. Unit Availability Factor 100.0% 75.6% 70.8%
22. Unit Capacity Factor (MDC Net) 96.2% 48.3% 60.3%
23. Unit Capacity Factor (DER Net) 92.3% 46.3% 59.4%
24. Unit Forced Outage Rate 0.0% 2.6% 10.5%
25. Forced Outage Hours 0.0 123.3 8,443.0
26. Shutdowns scheduled over the next 6 months (type, date, duration): Refueling outage begins 4/12/97, duration is 42 days
27. Ifcurrently shutdown, estimated startup date; Note: Cumulative Unit Capacity Factors (MDC & DER) are calculated with weighted averages.

t AVERAGE DAILY UNIT POWER LEVEL t DOCKET NO.: 50-397 UNIT: WNP-2 DATE: November 1, 1996 COMPLETED BY: B Knsko TELEPHONE: (509) 377M73 REPORT PERIOD: OCTOBER 1996 AVERAGE DAILYPOWER LEVEL AVERAGE DAILYPOWER LEVEL DAY (Net MWe) DAY (Net MWe) 1140 16 1143 1143 17 1138 1139 18 1123 1131 19 1137 1112 20 1130 1137 21 1139 1134 22 1145 1133 23 1101 1060 24 1042 10 1006 25 1036 892 26 779 12 639 27 1024 13 890 28 1042 14 1136 29 1049 15 1142 30 1059 31 1087 INSTRUCTIONS On this form, list the average daily unit power level in MWe (net) for each day in the reporting month. Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of the unit, there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

4

~ I ~

fQ

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NOut 50-397 UNlT NAME.'NP-2 DATE: November 1, 1996 COMPLETED BY: B Kasko TELEPHONE: (509) 377M73 REPORT PERIOD: OCTOBER 1996 No. Date Type Hours Reason Method LER Number System Component Cause and Corrective Action To Prevent Recurrence 96-12 10/11/96 S Zero N/A N/A CH PUMPXX Reduced power to perform scram time testing, turbine valve testing and digital feedwater testing.

96-13 10/26/96 F Zero N/A N/A CB MOTORX Reduced power to perform maintenance on ASD channel 1A2.

SUMMARY

At the end of the month WNP-2 was operating at 100% power.

TYPE REASON METHOD SYSTEM & COMPONENT F - Forced A - Equipment Failure E - Operator Training & ~1- Menue G41 1 ttsF&,

S - Scheduled B - Maintenance or Test License Examination 2 - Manual Scram C - Refueling F - Administration 3 - Auto Scram D - Regulatory Restriction 6 -- Operational Error 4 - Continued H Other 5 - Reduced Load 9 - Other

I pI A

II'