ML17290A603

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Aug 1993 for WNP-2.W/930909 Ltr
ML17290A603
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 08/31/1993
From: Embree D, Parrish J
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GO2-93-229, NUDOCS 9309150207
Download: ML17290A603 (8)


Text

. ACCELERATE+ DOCUMENT DIST UTION SYSTEM 4

REGULA~ INFORMATION DISTRIBUTI YSTEM (RIDS)

ACCESSION NBR:9309150207 DOC.DATE: 93/08/31 NOTARIZED: NO DOCKET FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH. NAME AUTHOR AFFILIATION EMBREE,D.G. Washington Public Power Supply System PARRISH,J.V. Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating rept for Aug 1993 for WNP-2.W/930909 ltr.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR I ENCL r SIZE: 5 TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PDV LA 3 3 PDV PD 1 1 CLIFFORD,J 1 1 D

INTERNAL: ACRS 10 10 AEOD/DOA 1 1 AEOD/DSP/TPAB 1 1 RRQ~GR &/~OEAB 1 1 NRR/DRIL/RPEB 1 1

1 1

REG F~~ 01 1 1 D RGN5 EXTERNAL: EGGG BRYCEEJ.H 1 1 NRC PDR 1 1 NSIC 1 1 D

NOTE TO ALL "RIDS" RECIPIEN'I'S:

I'LEASE HELP US TO REDUCE WAS'I'I:! CONTACT 'fl IE DOCUMEN'I'ON'I'ROI. I)L'~l'.

ROOM I 1.37 (EXT. 504-2065) TO ELIMIi4ATE YOUR NAME FIKOM DIS'I'RIIIIPI'ION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24 Je

WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 96S ~ 3000 George Washington Way ~ Richland, Washington 99352 Docket No. 50-397 September 9, 1993 G02-93-229 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555

Dear Sir:

Subject:

NUCLEAR PLANT NO. 2 MONTHLYOPERATING REPORT August 1993 Transmitted herewith is the Monthly Operating Report for the month of August 1993 as required by our Technical Specifications 6.9.1.6, Very trul ours,

. V. Parrish (MD1023)

Assistant Managing Director of Opertions DE/ja CC: Mr. W. H. Lovelace, NRC, Washington, DC Mr. B. H. Faulkenberry, NRC Region V Mr. R. C. Barr, NRC Resident Inspector (901A)

Mr. J. T. Wheelock, INPO Mr. C. Bergesen, Utility Data Institute l5.034 Z(P 9'30'tti50207 930831 PDR ADQCK 05000397

~ ~

~q

'L

'(

H

4 WASIIINOTON PUBLIC PO\VBR SUPPLY SYSTBM r

WNP-2 MONTHLY GENERATION STATISTICS FOR AUGUST 1993 THERMAL GENERATION STATISTICS

  • ELECTRICAL Current Calendar Fiscal Commercial Month Year-to-Date Year-to-Date (Dec. 1984)

Gross Thermal (MWHth) 1,618,841 11,900,049 4,070,541 149,064,699 Gross Electrical (MWHe) 549,450 4,098,440 1,391,000 49,947,530 Net Electrical (MWHe) - BPA 527 698 )~I,;,"<<Ig~gs,:;,':.'","::.'::.'pc+

Off-Site Power Used On-Line 1 95

.,5. >0 i g.<<g"k~Piic;.;(,';@/ 8i .',",.."<< ~ S<<:< l,X ...

', ' ',',%,,'x>ig~t;>.,~:j g < t',. '4.) Ni.(M.t;.;:;.i<<j~j';;tg@p@<<.<<',:<h Off-Site Power Used Off-Line 3 388 <<,,,

Net Electrical (MWHe) - Actual 524,114 3,894,604 1,334,331 47,845,023 Critical Hours 559.0 4,032.5 1,303.0 Hours On-Line 524.5 3,830.3 1,268.5 Availability Factor 70.5% 65.7% 85.2% 67.4%

Capacity Factor 63.4% 60. 1% 80.6% 57.2%

REACTOR FUEL USAGE STATISTICS

  • Current Cycle 9 Since 8/01/93 Month Full Power Days Used: 20.30 56.87 20.30

,"'<<4<:?<):.<$ l:":pgx)IS);:.:.:.Ni<<>?,.;5'-:;.'ji::

Full Power Days Left in Core: 159.13 Full Power Days Loaded 216 FFTR or coastdown) 'without Equivalent Full Power Days Loaded 255 (with FFTR and coastdown)

Electrical and thermal generation statistics and the reactor fuel usage statistics were obtained from WNP-2 Control Room logs and BPA Historical Accounts data.

p:magen datahreportshsshstats.ss Performance Evaluations September 8, 1993 MD 1026

e E

OPERATING STATUS REPOR for WNP-2 Date: September 1, 1993 Docket: 50-397

2. Reporting Period: AUGUST 1993 Outage + On-Line Hours: 744.0
3. Utility

Contact:

David G. Embree (509) 377-8448 4, Licensed Thermal Power (MW, ): 3323

5. Nameplate Rating (Gross MW, ): 1200.9
6. Design Electrical Rating (Net MW,): 1120
7. Maximum Dependable Capacity (Gross MW,): 1165
8. Maximum Dependable Capacity (Net MW, ): 1112
9. If changes occur above since last report, give reasons: n/a
10. Power to which restricted, if any (Net MW,): n/a
11. Reasons for restrictions, if any: n/a MONTH YEAR CUMULATIVE
12. Report Period Hours 744.0 5,831.0 76,399.2 13, Hours Reactor Critical 559.0 4,032.5 53,181.2
14. Rx Reserve Shutdown Hours 0.0 0.0 340.4
15. Hours Generator On-Line 524.5 3,830.3 51,138.0
16. Unit Reserve Shutdown Hours 0.0 0.0 381.7
17. Gross Thermal Energy (MWH) 1,618,841 11,900,049 149,064,699
18. Gross Electrical Energy (MWH) 549,450 4,098,440 49,947,530
19. Net Electrical Energy (MWH) 524,179 3,894,669 47,845,088 20., Unit Service Factor 70.5% 65.7% 66.9%
21. Unit Availability Factor 70.5% 65.7% 67.4%
22. Unit Capacity Factor (MDC Net) 63.4% 60. 1% 57.2%
23. Unit Capacity Factor (DER Net) 62.9% 59.6% 56.9%
24. Unit Forced Outage Rate 29.5% 13.8% 13.4%
25. Forced Outage Hours 219.5 612.0 7,885.3
26. Shutdowns scheduled over the next 6 months (type, date, duration): None.
27. Ifcurrently shutdown estimated startup date:

Note: Cumualtive Unit Capacity Factors (MDC 8c DER) are calculated with weighted averages.

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 50-397 UNIT: WNP-2 DATE: September 1, 1993 COMPLETED BY: D. G. Embree TELEPHONE: (509) 377-8448 REPORT PERIOD: AUGUST 1993 AVERAGE DAILYPOWER LEVEL AVERAGE DAILYPOWER LEVEL DAY (Net MWe) DAY (Net MWe) 1097 16 1089 1092 17 1092 18 1089

-17 19 1089

-14 20 1065

-15 21 1087

-15 22 1094

-14 23 1090

-14 24 1105 10 -14 25 1104

-17 26 1105 12 82 27 1097 13 276 28 1098 792 29 1099 15 883 30 1096 31 1095 INSTRUCfIONS On this form, list the average daily unit power level in MWe (net) for each day in the reporting month. Compute to the nearest whole megawatt.

These figures willbe used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of the unit, there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-397 UNIT NAME: WNP-2 DATE: September 1; 1993 COMPLETED BY: D.G. Embree TELEPHONE: (509) 3774448 REPORT PERIOD: AUGUST 1993 No. Date Type Hours Reason Method LER Number System Component Cause and Corrective Action To Prevent Recurrence 93%7 8/03/93 F 219.5 93427 CD VALVEX During performance of a surveillance procedure to calibrate Main Steam Radiation Indicating Switch, the reactor unexpectedly scrammed &om 100%

power due to a full isolation of the MSIVs.

It was discovered that a MSIV pilot valve had been improperly rebuilt during the recent refueling outage.

It was correctly rebuilt and the plant vys eventually restarted. See LER 93M7 for other corrective actions taken and training evolutions planned.

SUMMARY

WNP-2 had one automatic scram during the month of August. Upon completion of required equipment repairs, the plant was restarted and ramped up to full power operation by month's end.

TYPE REASON METHOD SYSTEM & COMPONENT F - Forced A - Equipment Failure E - Operator Training & 1 - Manual NUREGA161 Exhibits F & H S - Scheduled B - Maintenance or Test License Examination 2 - Manual Scram C - Refueling F - Administration 3 - Auto Scram D - Regulatory Restriction G - Operational Error 4 - Continued H - Other 5 - Reduced Load 9 - Other