MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) IR 05000275/20243012023-08-24024 August 2023 Notification of NRC Initial Operator Licensing Examination 05000275/2024301; 05000323/2024301 IR 05000275/20230052023-08-22022 August 2023 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2023005 and 05000323/2023005) - Mid Cycle Letter IR 05000275/20230022023-08-14014 August 2023 Quarterly Integrated Inspection Report 05000275/2023002 and 05000323/2023002- August 7, 2023 IR 05000275/20213012023-08-0909 August 2023 Errata for Diablo Canyon Power Plant, Units 1 and 2 - NRC Examination Report 050002752021301 and 050003232021301 IR 05000275/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000275/2023402, and 05000323/2023402 IR 05000275/20233012023-07-25025 July 2023 NRC Initial Operator Licensing Examination Approval 05000275/2023301, 05000323/2023301 IR 05000275/20230102023-05-11011 May 2023 NRC Inspection Report 05000275 2023010 and 05000323 2023010 IR 05000275/20230012023-05-0909 May 2023 Integrated Inspection Report 05000275/2023001 and 05000323/2023001 IR 05000275/20234032023-03-10010 March 2023 NRC Security Baseline Inspection Report 05000275/2023403, 05000323/2023403 (Full Report) IR 05000275/20220062023-03-0101 March 2023 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2022006 and 05000323/2022006) IR 05000275/20220042023-02-0202 February 2023 Integrated Inspection Report 05000275/2022004 and 05000323/2022004 IR 05000275/20220102023-01-27027 January 2023 Biennial Problem Identification and Resolution Inspection Report 05000275/2022010 and 05000323/2022010 IR 05000275/20224022022-10-26026 October 2022 Security Baseline Inspection Report 05000275/2022402 and 05000323/ 2022402 IR 05000275/20220032022-10-24024 October 2022 Integrated Inspection Report 05000275/2022003 and 05000323/2022003 and Exercise of Enforcement Discretion IR 05000275/20220052022-08-23023 August 2022 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2022005 and 05000323/2022005) IR 05000275/20220022022-08-10010 August 2022 Integrated Inspection Report 05000275/2022002 and 05000323/2022002 IR 05000275/20220112022-08-0909 August 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000275/2022011 and 05000323/2022011 IR 05000275/20224012022-08-0303 August 2022 NRC Security Inspection Report 05000275/2022401, 05000323/2022401 ML22143A8812022-05-26026 May 2022 Revised Integrated Inspection Report 05000275/2022001 and 05000323/2022001 ML22118A9362022-05-0505 May 2022 Integrated Inspection Report 05000275/2022001 and 05000323/2022001 IR 05000275/20220012022-05-0505 May 2022 Integrated Inspection Report 05000275/2022001 and 05000323/2022001 IR 05000323/20214202022-03-31031 March 2022 Security Inspection Report 05000275 and 05000323/2021420 IR 05000275/20210062022-03-0202 March 2022 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2021006 and 05000323/2021006) IR 05000275/20210042022-02-0303 February 2022 Integrated Inspection Report 05000275/2021004 and 05000323/2021004 IR 05000275/20214042022-01-13013 January 2022 Public - Security Baseline Inspection Report 05000275/2021404 and 05000323/2021404 IR 05000275/20210032021-11-0303 November 2021 Integrated Inspection Report 05000275/2021003 and 05000323/2021003 IR 05000275/20210112021-09-10010 September 2021 Design Basis Assurance Inspection (Programs) Report 05000275/2021011 and 05000323/2021011 IR 05000275/20214052021-08-0505 August 2021 Security Baseline Inspection Report 05000275/2021405 and 05000323/2021405 IR 07200026/20214012021-08-0303 August 2021 Diablo Canon Nuclear Power Plant, Security Baseline Inspection Report 07200026/2021401 IR 05000275/20210022021-08-0202 August 2021 Integrated Inspection Report 05000275/2021002 and 05000323/2021002 IR 05000275/20210122021-07-28028 July 2021 Temporary Instruction 2515/194 Report 05000275/2021012 and 05000323/2021012 IR 05000275/20214012021-07-0101 July 2021 Security Baseline Inspection Report 05000275/2021401 and 05000323/2021401 IR 05000275/20210012021-05-0707 May 2021 DC IR 2021-001-drk, Diablo Canyon Power Plant Units 1 & 2 - Integrated Inspection Report 05000275/2021001, 05000323/2021001, & Independent Spent Fuel Storage Installation Inspection Report 07200026/2021001 DCL-21-036, One Hundred Eighty Day Steam Generator Report for Diablo Canyon Power Plant Unit 1 Twenty-Second Refueling Outage2021-04-22022 April 2021 One Hundred Eighty Day Steam Generator Report for Diablo Canyon Power Plant Unit 1 Twenty-Second Refueling Outage ML21102A0702021-04-12012 April 2021 Notification of NRC Design Bases Assurance Inspection (Programs) (05000275/2021011 and 05000323/2021011) and Initial Request for Information IR 05000275/20214032021-03-31031 March 2021 Cyber Security Inspection Report 05000275/2021403 and 05000323/2021403 IR 05000275/20210102021-03-11011 March 2021 Triennial Fire Protection Inspection Report 05000275/2021010 and 05000323/2021010 IR 05000275/20200062021-03-0303 March 2021 DC 2020 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 & 2 (Report 05000275/2020006 & 05000323/2020006) IR 05000275/20200042021-01-26026 January 2021 Integrated Inspection Report 05000275/2020004 and 05000323/2020004 IR 05000275/20204112020-12-22022 December 2020 Security Baseline Inspection Report 05000275/2020411 and 05000323/2020411 IR 05000275/20204102020-12-15015 December 2020 NRC Security Inspection Report 05000275/2020410 and 05000323/2020410 IR 05000275/20200102020-10-30030 October 2020 Biennial Problem Identification and Resolution Inspection Report 05000275/2020010 and 05000323/2020010 IR 05000275/20200032020-10-29029 October 2020 Integrated Inspection Report 05000275/2020003 and 05000323/2020003 IR 05000275/20200052020-09-0101 September 2020 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2020005 and 05000323/2020005) IR 05000275/20200022020-07-22022 July 2020 Integrated Inspection Report 05000275/2020002 and 05000323/2020002 IR 05000275/20200012020-04-16016 April 2020 Integrated Inspection Report 05000275/2020001 and 05000323/2020001 2024-02-09
[Table view] Category:Letter
MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] |
See also: IR 05000275/2016003
Text
May 27, 2016
Mr. Edward D. Halpin, Senior Vice President
and Chief Nuclear Officer
Pacific Gas and Electric Company
Diablo Canyon Power Plant
P.O. Box 56, Mail Code 104/6
Avila Beach, CA 93424
SUBJECT: DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NOTIFICATION OF NRC
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION (05000275/2016003
AND 05000323/2016003) AND REQUEST FOR INFORMATION
Dear Mr. Halpin:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff
will conduct a triennial heat sink performance inspection at your Diablo Canyon Power Plant,
Units 1 and 2, from August 1-5, 2016. The inspection will be comprised of one reactor inspector
from the NRCs Region IV office for one week. The inspection will be conducted in accordance
with NRC Inspection Procedure 71111.07, "Heat Sink Performance."
Experience has shown that this inspection is resource intensive, both for the NRC inspectors
and your staff. In order to minimize the impact to your on-site resources and to ensure a
productive inspection, we have enclosed a request for documents needed for this inspection.
Please note that the documents are requested to be provided by July 22, 2016. We request
that during the on-site inspection week, you ensure that copies of analyses, evaluations, or
documentation regarding the implementation and maintenance of your heat exchanger program
are available. Of specific interest are those documents that establish your heat exchanger
program satisfies the NRC regulatory requirements and conforms to applicable the NRC
guidance. Also, appropriate personnel knowledgeable of safety-related heat exchangers should
be available to support the inspector at the site during the inspection.
We have discussed the schedule for this inspection activity with your staff and understand that
our regulatory contact for this inspection will be David Madsen of your licensing organization. If
there are any questions about this inspection or the material requested, please contact the
inspector, Gerond George, at 817-200-1562 or by e-mail at Gerond.George@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, control
number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to
E. Halpin -2-
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of
this letter and its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRC's document
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Thomas R. Farnholtz, Chief
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-275 and 50-323
License Nos. DPR-80 and DPR-82
Enclosure:
Request for Information
cc: Electronic Distribution
Request for Information
Triennial Heat Sink Performance Inspection
Diablo Canyon Power Plant
Inspection Report: 05000275/2016003, 05000323/2016003
Inspection Dates: August 1-5, 2016
Inspection Procedure: IP 71111.07, Heat Sink Performance
Inspector: Gerond A. George, Senior Reactor Inspector
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office via electronic format
(Certrec IMS preferred), to the attention of Gerond George, by July 22, 2016. The inspector will
select specific items from the information requested below and then request from your staff
additional documents needed during the on-site inspection week. Also, we request that you
categorize the documents in your response with the numbered list below, and for Adobe
portable document files (.pdf) please make the text searchable. If requested documents are
large and only hard copy formats are available, please inform the inspector and provide subject
documentation during the first day of the on-site inspection. If you have any questions
regarding this information request, please call the lead inspector as soon as possible.
The following heat exchangers/heat sinks have been selected for inspection:
- Safety Injection Lube Oil Cooler (1-1, 1-1A/B)
For all Generic Letter 89-13 exchangers:
1. List of corrective action program documents (with a short description) associated with
Generic Letter 89-13 heat exchangers, heat sinks, silting, corrosion, fouling, heat
exchanger cavitation, or heat exchanger testing, in the previous three years
2. System health report(s) and maintenance rule system notebooks for all the Generic
Letter 89-13 heat exchangers
3. Copy of any self-assessments done on any Generic Letter 89-13 heat exchangers in the
previous three years
4. Copies of any procedures developed to implement the recommendations of Generic
Letter 89-13 (e.g., the Generic Letter 89-13 Heat Exchanger Program description)
5. Copies of any commitments to the Generic Letter 89-13 program
For the specific heat exchangers selected:
Testing Documents
6. Copies of the two most recent completed tests confirming thermal performance for those
heat exchangers which are performance-tested
7. Instrument uncertainties of the instruments used during testing
8. Copy of any operability determinations or other documentation of degradation
associated with the heat exchangers or the systems that support the operation for the
selected heat exchangers
9. Documents that show the as-found results are recorded, evaluated, and appropriately
dispositioned such that the as-left condition is acceptable
Cleaning Documents
10. The cleaning and inspection maintenance schedule for each heat exchanger for the next
five years
11. Copy of the document describing the inspection results for the last two cleaning and
inspection activities completed on each heat exchanger
12. Cleaning procedures with acceptance criteria for the selected heat exchangers
13. Copies of the documents that verify the structural integrity of the heat exchanger
(e.g., eddy current summary sheets, ultrasonic testing results, and visual inspection
results)
14. Copies of those documents that describe the methods taken to control water chemistry
in the heat exchangers
Design Documents
15. Copies of the design basis documents and updated final safety analysis report pages for
the selected heat exchangers
16. Copies of the system training manuals for the selected heat exchangers
17. Provide a list of calculations with a description which currently apply to each heat
exchanger
18. Copies of vendor data sheets and design basis data for the selected heat exchangers
19. Copy of the calculation which establishes the limiting (maximum) design basis heat load
which is required to be removed by each of these heat exchangers
20. Copy of the calculation which correlates surveillance testing results from these heat
exchangers with design basis heat removal capability (e.g., basis for surveillance test
acceptance criteria)
21. Copy of the calculations or documents which evaluate the potential for water hammer or
excessive tube vibration in the heat exchanger or associated piping
22. Copy of the document which identifies the current number of tubes in service for each
heat exchanger and the supporting calculation which establishes the maximum number
of tubes which can be plugged in each heat exchanger
23. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes
which are identified in each heat exchanger
For the ultimate heat sink or safety-related service water system:
24. Intake structure inspections that monitor the integrity of the ultimate heat sink
25. Copies of calculations and surveillances that determine the ultimate heat sink reservoir
capacity and heat transfer capability
26. Copies of any design changes performed on the ultimate heat sink or safety-related
service water system
27. Copies of procedures for a loss of ultimate heat sink or safety-related service water
system
28. Copies of inspections and/or maintenance related to macrofouling (silt, mussel shells,
debris, etc.) and aquatic life
29. Copies of inspections and/or maintenance related to preventing biotic fouling
30. Copies of procedures and/or test results to survey or monitor interface valves between
the safety-related section of the service water system and the non-safety-related section
31. Copy of the most recent service water flow balance test results, both as-found and as-
left
32. History of any through-wall pipe leaks on the safety-related service water system
Inspector Contact Information:
Gerond A. George
Senior Reactor Inspector
817-200-1562
Gerond.George@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Gerond A. George
1600 East Lamar Blvd.
Arlington, TX 76011-4511
ML16148A373
SUNSI Review ADAMS Publicly Available Non-Sensitive Keyword:
By: GAG Yes No Non-Publicly Available Sensitive NRC-002
OFFICE SRI/DRS C:EB1
NAME GGeorge TFarnholtz
SIGNATURE /RA/ /RA/
DATE 5/27/16 5/27/16
Letter to Edward D. Halpin from Thomas R. Farnholtz, dated May 27, 2016
SUBJECT: DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NOTIFICATION OF NRC
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION (05000275/2016003
AND 05000323/2016003) AND REQUEST FOR INFORMATION
Distribution by RIV:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Acting Senior Resident Inspector (John.Reynoso@nrc.gov)
Resident Inspector (Michael.Stafford@nrc.gov)
Administrative Assistant (Madeleine.Arel-Davis@nrc.gov)
Branch Chief, DRP/A (Jeremy.Groom@nrc.gov)
Senior Project Engineer, DRP/A (Ryan.Alexander@nrc.gov)
Project Engineer, DRP/A (Mathew.Kirk@nrc.gov)
Project Engineer, DRP/A (Thomas.Sullivan@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Project Manager (Balwant.Singal@nrc.gov)
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)