Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2015005 and 05000368/2015005)
ML15243A553
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 09/01/2015
From: Dapas M
Region 4 Administrator
To: Jeremy G. Browning
Entergy Operations
neil okeefe
References
IR 2015005
Download: ML15243A553 (8)


Text

September 1, 2015

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR ARKANSAS NUCLEAR ONE,

UNITS 1 AND 2 (REPORT 05000313/2015005 AND 05000368/2015005)

Dear Mr. Browning:

On August 13, 2015, the Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Arkansas Nuclear One, Units 1 and 2. The U.S. Nuclear Regulatory Commission reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015. This letter informs you of the U.S. Nuclear Regulatory Commissions assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at Arkansas Nuclear One, Units 1 and 2 during the most recent quarter was within the Multiple/Repetitive Degraded Cornerstone Column of the U.S.

Nuclear Regulatory Commissions Reactor Oversight Process (ROP) Action Matrix based on having one Yellow finding in the Initiating Events Cornerstone for Units 1 and 2, and one Yellow finding in the Mitigating Systems Cornerstone for Units 1 and 2. In addition, based on the results of a Frequently Asked Question (FAQ) review completed by the ROP Working Group on February 19, 2015, you have revised your reported Unplanned Scrams per 7,000 Critical Hours PI in the Initiating Events Cornerstone for Unit 2, and the revised PI result was White for the second and third quarters of 2014, and then returned to Green in the fourth quarter of 2014.

In a letter to you dated June 23, 2014 (ML14174A832), the U.S. Nuclear Regulatory Commission informed you of its final significance determination associated with an inspection finding in the Initiating Events Cornerstone for Units 1 and 2 that was identified in the first quarter of 2014. That finding, which the NRC concluded was of substantial safety significance (Yellow), involved your staffs failure to provide adequate oversight for the planned movement of the Unit 1 turbine stator in March 2013 using a temporary hoisting assembly.

In a letter to you dated January 22, 2015 (ML15023A076), the U.S. Nuclear Regulatory Commission informed you of its final significance determination associated with an inspection finding in the Mitigating Systems Cornerstone for Units 1 and 2 that was identified in the third quarter of 2014. That finding, which the NRC concluded was of substantial safety significance (Yellow), involved your staffs failure to design, construct, and maintain the Units 1 and 2 auxiliary building and emergency diesel fuel storage building flood barriers so that they would protect safety-related equipment from flooding. In addition to ROP baseline inspections, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95003, Supplemental Inspection for Repetitive Degrades Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs or One Red Input. The objectives of this inspection are: (1) to provide information to be used to determine whether continued operation of the facility is acceptable and whether additional regulatory actions are necessary to arrest declining plant performance; (2) to provide an independent assessment of the extent of risk significant issues to aid in the determination of whether an unacceptable margin of safety or security exists; (3) to independently assess the adequacy of the programs and processes used by the licensee to identify, evaluate, and correct performance issues; (4) to independently evaluate the adequacy of programs and processes in the strategic performance areas; (5) to provide insight into the overall root and contributing causes of the identified performance deficiencies; (6) to determine if the NRC oversight process provided sufficient warning to significant reductions in safety; and (7) to evaluate your licensees third-party safety culture assessment and conduct a graded assessment of your safety culture based on the results of the evaluation. You will receive separate notification when we schedule this inspection.

The U.S. Nuclear Regulatory Commission also plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, due to the Unplanned Scrams per 7000 Critical Hours PI transitioning to the White (low to moderate safety significance) range for the second and third quarters of 2014. The objectives of this inspection are: (1) to provide assurance that the root causes and contributing causes of risk-significant performance issues are understood; (2) to provide assurance that the extent of condition and extent of cause of risk-significant performance issues are identified; (3) to provide assurance that the corrective actions for risk-significant performance issues are sufficient to address the root and contributing causes and prevent recurrence. We will plan this inspection when you notify us in writing of your readiness for inspection.

The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The U.S. Nuclear Regulatory Commission provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The U.S. Nuclear Regulatory Commission will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In accordance with Inspection Manual Chapter 0305, Operating Reactor Assessment Program, the U.S. Nuclear Regulatory Commission is considering conducting an additional problem identification and resolution inspection during the second half of 2016. You will be notified separately when this inspection is scheduled.

In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The U.S. Nuclear Regulatory Commission is conducting audits of licensee efforts towards compliance with these Orders. The audit has been completed for Arkansas Nuclear One, and the information gathered will aid staff in development of the ultimate Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the U.S. Nuclear Regulatory Commission staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 2515/191, Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the U.S.

Nuclear Regulatory Commissions Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the U.S. Nuclear Regulatory Commission Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Neil OKeefe at (817) 200-1574 with any questions you have regarding this letter.

Sincerely,

/RA/

Marc L. Dapas Regional Administrator Region IV

Docket Nos. 50-313, 50-368 License Nos. DPR-51, NPF-6

Enclosure:

Arkansas Nuclear One Units 1 and 2 Inspection/Activity Plan

SUNSI Review By: NOKeefe ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive OFFICE RIV/BC/DRP RIV/D/DRS RIV/D/DRP RIV/RA NAME NOKeefe; RDR AVegel TPruett MLDapas SIGNATURE

/RA/

/RA/

/RA/

/RA/

DATE 8/26/15 8/26/15 8/27/15 8/27/15

Letter to Jeremy Browning from Neil OKeefe dated September 1, 2015

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR ARKANSAS NUCLEAR ONE,

UNITS 1 AND 2 (REPORT 05000313/2015005 AND 05000368/2015005)

DISTRIBUTION:

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

Senior Resident Inspector (Brian.Tindell@nrc.gov)

Resident Inspector (Margaret.Tobin@nrc.gov)

Resident Inspector (Andy.Barrett@nrc.gov)

Branch Chief, DRP/E (Neil.OKeefe@nrc.gov)

Senior Project Engineer, DRP/E (John.Dixon@nrc.gov)

Project Engineer, DRP/E (Brian.Correll@nrc.gov)

Project Engineer, DRP/E (Jackson.Choate@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

RIV State Liaison Officer (Bill.Maier@nrc.gov)

Project Manager (Andrea.George@nrc.gov)

Acting Team Lead DRS/TSS (Eric.Ruesch@nrc.gov)

Director, DIRS, NRR (Scott.Morris@nrc.gov)

Deputy Director, DIRS, NRR (Allen.Howe@nrc.gov)

Director, DORL, NRR (Anne.Boland@nrc.gov)

Deputy Director, DORL, NRR (George.Wilson@nrc.gov)

Director, NSIR/DPR (Rob.Lewis@nrc.gov)

Chief, PLB IV, DORL, NRR (Michael.Markley@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Cindy.Rosales-Cooper@nrc.gov)

ROPassessment Resource@nrc.gov ROPreports@nrc.gov

Distribution via Listserv for Arkansas Nuclear One

Page 1 of 3 08/26/2015 14:05:01 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Arkansas Nuclear One Inspection / Activity Plan 07/01/2015 - 06/30/2017 EXAM

- INITIAL OPERATOR EXAM

2 INITIAL EXAM ANO (8/2015)

X02545 07/27/2015 07/31/2015

INITIAL EXAM ANO (8/2015)

X02545 08/24/2015 08/29/2015 EB1-07

- ANO TRIENNIAL HEAT SINK PERFORMANCE

1, 2 IP Heat Sink Performance 7111107T 07/13/2015 07/17/2015 95003

- 95003 PREPARATION AND INSPECTION

2 IP Adverse Weather (System/Seasonal)

7111101-Seasonal 01/01/2016 02/29/2016 1, 2 IP Adverse Weather (System/Seasonal)

7111101-Seasonal 01/01/2016 02/29/2016 1, 2 IP Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inp 95003 01/01/2016 02/29/2016 71111.08

- INSERVICE INSPECTION 2R24

2 IP Inservice Inspection Activities - PWR 7111108P 09/21/2015 10/02/2015 EP-1

- BIENNIAL EP PROGRAM INSPECTION

1, 2 IP Alert and Notification System Testing 7111402 10/05/2015 10/09/2015 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 10/05/2015 10/09/2015 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 10/05/2015 10/09/2015 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 10/05/2015 10/09/2015 EP-2

- EP PERFORMANCE INDICATORS

1, 2 IP Drill/Exercise Performance 71151-EP01 10/05/2015 10/09/2015 1, 2 IP ERO Readiness 71151-EP02 10/05/2015 10/09/2015 1, 2 IP Alert & Notification System Reliability 71151-EP03 10/05/2015 10/09/2015 EXAM

- INITIAL EXAM ANO U1

1 INITIAL EXAM ANO UNIT 1 (08/2016)

X02568 07/25/2016 07/29/2016

INITIAL EXAM ANO UNIT 1 (08/2016)

X02568 08/22/2016 09/02/2016 EB2-05XT

- TRIENNIAL FIRE PROTECTION INSPECTION

1, 2 IP Fire Protection - NFPA 805 (Triennial)

7111105X 06/06/2016 06/10/2016 1, 2 IP Fire Protection - NFPA 805 (Triennial)

7111105X 06/20/2016 06/24/2016 EXAM

- INITIAL EXAM

2 INITIAL EXAM ANO UNIT 2 (02/2017)

X02585 01/09/2017 01/13/2017

INITIAL EXAM ANO UNIT 2 (02/2017)

X02585 02/06/2017 02/10/2017 RS 5678

- RADIATION SAFETY - TEAM

1, 2 IP Radiation Monitoring Instrumentation 71124.05 06/27/2016 07/01/2016 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/27/2016 07/01/2016 1, 2 IP Radiological Environmental Monitoring Program 71124.07 06/27/2016 07/01/2016 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 06/27/2016 07/01/2016 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 3 08/26/2015 14:05:01 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Arkansas Nuclear One Inspection / Activity Plan 07/01/2015 - 06/30/2017 INSP

- BIENNIAL REQUAL INSPECTION U1

1 IP Licensed Operator Requalification Program 7111111B 07/18/2016 07/22/2016 INSP

- BIENNIAL REQUAL INSPECTION U2

2 IP Licensed Operator Requalification Program 7111111B 07/18/2016 07/22/2016 EP-2

- EP PERFORMANCE INDICATORS

1 IP Drill/Exercise Performance 71151-EP01 08/22/2016 08/26/2016

IP ERO Readiness 71151-EP02 08/22/2016 08/26/2016

IP Alert & Notification System Reliability 71151-EP03 08/22/2016 08/26/2016 EP-3

- BIENNIAL EP EXERCISE INSPECTION

1, 2 IP Exercise Evaluation 7111401 08/22/2016 08/26/2016 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 08/22/2016 08/26/2016 TSB 52B

- BIENNIAL PI&R INSPECTION

1, 2 IP Problem Identification and Resolution 71152B 08/29/2016 09/02/2016 1, 2 IP Problem Identification and Resolution 71152B 09/12/2016 09/16/2016 RS 12 PI

- RADIATION SAFETY

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/26/2016 09/30/2016 1, 2 IP Occupational ALARA Planning and Controls 71124.02 09/26/2016 09/30/2016 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 09/26/2016 09/30/2016 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 09/26/2016 09/30/2016 71111.08

- INSERVICE INSPECTION 1R26

1 IP Inservice Inspection Activities - PWR 7111108P 09/26/2016 10/07/2016 EB1-21T

- ANO COMPONENT DESIGN BASIS INSPECTION

1, 2 IP Component Design Bases Inspection 7111121 10/31/2016 12/02/2016 RS 13 PI

- RADIATION SAFETY

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/13/2017 03/17/2017 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/13/2017 03/17/2017 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 03/13/2017 03/17/2017 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 03/13/2017 03/17/2017 71111.08

- INSERVICE INSPECTION 2R25

2 IP Inservice Inspection Activities - PWR 7111108P 03/13/2017 03/23/2017 EB2-03

- LICENSE RENEWAL INSPECTION (PHASE 1)

2 IP Post-Approval Site Inspection for License Renewal 71003 03/20/2017 03/24/2017 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 3 of 3 08/26/2015 14:05:01 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Arkansas Nuclear One Inspection / Activity Plan 07/01/2015 - 06/30/2017 TSB 52B

- BIENNIAL PI&R

1, 2 IP Problem Identification and Resolution 71152 05/01/2017 05/05/2017 1, 2 IP Problem Identification and Resolution 71152 05/15/2017 05/19/2017 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.