Other: BVY 06-009, 2006/01/25-Vermont Yankee Nuclear Power Station Applicant'S Environmental Report Operating License Renewal Stage, Appendix E, BVY 06-076, 2006/08/10-Vermont Yankee - License Renewal Application, Amendment 8, BVY 06-079, 2006/08/22-Vermont Yankee License Renewal Application, Amendment 11, BVY 06-083, 2006/09/05-Vermont Yankee License Renewal Application, Amendment 12, BVY 06-095, E-mail: (PA-LR) Copy of SAMA Response, BVY 06-096, 2006/10/20-Vermont Yankee - License Renewal Application, Amendment No. 17, BVY 06-097, 2006/10/31-Vermont Yankee License Renewal Application, Amendment 19, BVY 06-098, E-mail: (PA-LR) Copy of Vhs RAI Response, BVY 07-003, Email: (PA-LR) Vermont Yankee Nuclear Power Station License Renewal Commitment List, Rev. 5, BVY 07-009, License Renewal Application, Amendment 24, BVY 07-018, License Renewal Application, Amendment 26, BVY 07-034, License Renewal Application Annual Update, BVY 07-035, (PA-LR) Bvy 07-035 VY Lr SER Comments, BVY 07-047, License Renewal Application, Amendment 27, Submitted on January 25, 2006, BVY 07-058, License Renewal Application, Amendment 29, BVY 07-062, License Renewal Application, Amendment 30, BVY 07-066, License Renewal Application, Amendment 31, BVY 08-016, (PA-LR) Emailing Bvy 08-016 Final SER Review Comments, BVY 10-069, License Renewal Application Annual Update Information, ML060950195, ML060950215, ML060950218, ML060950220, ML060950224, ML060950235, ML060950250, ML060950258, ML060950262, ML060950269, ML060950271, ML060950277, ML060950279, ML060950284, ML060950290, ML060950301, ML060950311, ML060950323, ML060950328, ML060950331, ML060950347, ML060950351, ML060950356, ML060950364, ML060950370, ML060950372, ML060950375, ML060950540, ML060950549, ML060950559, ML060950567... further results
|
MONTHYEARML0629203681987-12-31031 December 1987 VY Annual Ecological Studies of the CT River Report 16-final.pdf Project stage: Other ML0629203651989-12-31031 December 1989 VY Annual Ecological Reports from the 1980's (1989) Project stage: Other ML0609503511998-02-28028 February 1998 GALL AMP: XI.M12, Thermal Aging Embrittlement of Cast Austenitic Stainless Steel (CASS) (Audit Worksheet GALL Report AMP) Project stage: Other BVY 06-009, 2006/01/25-Vermont Yankee Nuclear Power Station Applicant'S Environmental Report Operating License Renewal Stage, Appendix E2006-01-25025 January 2006 2006/01/25-Vermont Yankee Nuclear Power Station Applicant'S Environmental Report Operating License Renewal Stage, Appendix E Project stage: Other ML0609505792006-03-22022 March 2006 GALL AMP: XI.M24, Compressed Air Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506202006-03-22022 March 2006 GALL AMP: XI.M31, Reactor Vessel Surveillance (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505962006-03-22022 March 2006 GALL AMP: XI.M27, Fire Water System (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502792006-03-22022 March 2006 GALL AMP: XI.M3, Reactor Head Closure Studs (Audit Worksheet, GALL Report AMP) Project stage: Other ML0609506292006-03-22022 March 2006 GALL AMP: XI.M33, Selective Leaching of Materials (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506372006-03-22022 March 2006 GALL AMP: XI.M36, External Surfaces Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502842006-03-22022 March 2006 GALL AMP: XI.M4, BWR Vessel Id Attachment Welds (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502202006-03-22022 March 2006 GALL AMP: X.S1, Concrete Containment Tendon Prestress (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001472006-03-22022 March 2006 GALL AMP: XI.S8, Protective Coating Monitoring and Maintenance Program (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001342006-03-22022 March 2006 GALL AMP: XI.S5, Masonry Wall Progam (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502182006-03-22022 March 2006 GALL AMP: X.M1, Metal Fatigue of Reactor Coolant Pressure Boundary (Audit Worksheet, GALL Report AMP) Project stage: Other ML0609505592006-03-22022 March 2006 GALL AMP: XI.M20, Open-Cycle Cooling Water System (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503472006-03-22022 March 2006 GALL AMP: XI.M11A, Nickel Alloy Penetration Nozzles Welded to the Upper Reactor Vessel Closure Heads of Pressurized Water Reactors Project stage: Other ML0609505402006-03-22022 March 2006 GALL AMP: XI.M18, Bolting Integrity (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505672006-03-22022 March 2006 GALL AMP: XI.M21, Closed-Cycle Cooling Water System (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001012006-03-22022 March 2006 GALL AMP: XI.S2, ASME Section XI, Subsection Iwl (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505732006-03-22022 March 2006 GALL AMP: XI.M23, Inspection of Overhead Heavy Load and Light Load (Related to Refueling) Handling Systems (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506102006-03-22022 March 2006 GALL AMP: XI.M29, Aboveground Steel Tanks (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502902006-03-22022 March 2006 GALL AMP: XI.M5, BWR Feedwater Nozzle (Audit Worksheet, GALL Report AMP) Project stage: Other ML0610001382006-03-22022 March 2006 GALL AMP: XI.S6, Structures Monitoring Program (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001262006-03-22022 March 2006 GALL AMP: XI.S4, 10 CFR 50, Appendix J (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502242006-03-22022 March 2006 GALL AMP: XI.E1, Electrical Cables and Connections Not Subject to 10 CFR 50.49 Environmental Qualification Requirements (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506062006-03-22022 March 2006 GALL AMP: XI.M28, Buried Piping and Tanks Surveillance (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502152006-03-22022 March 2006 GALL AMP: X.E1. Environmental Qualification (EQ) of Electric Components (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503752006-03-22022 March 2006 GALL AMP: XI.M17, Flow-Accelerated Corrosion (Audit Worksheet GALL Report AMP) Project stage: Other ML0610000782006-03-22022 March 2006 GALL AMP: XI.M38, Inspection of Internal Surfaces in Miscellaneous Piping and Ducting Components (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505702006-03-22022 March 2006 GALL AMP: XI.M22, Boraflex Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503722006-03-22022 March 2006 GALL AMP: XI.M16, PWR Vessel Internals (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503642006-03-22022 March 2006 GALL AMP: XI.M14, Loose Part Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502772006-03-22022 March 2006 GALL AMP: XI.M2, Water Chemistry (Audit Worksheet, GALL Report AMP) Project stage: Other ML0609506242006-03-22022 March 2006 GALL AMP: XI.M32, One-Time Inspection (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503112006-03-22022 March 2006 GALL AMP: XI.M7, BWR Stress Corrosion Cracking (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502352006-03-22022 March 2006 GALL AMP: XI.E2, Electrical Cables and Connections Not Subject to 10 CFR 50.49 Environmental Qualification Requirements Used in Instrumentation Circuits (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506342006-03-22022 March 2006 GALL AMP: XI.M35, One-Time Inspection of ASME Code Class 1 Small Bore Piping (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502502006-03-22022 March 2006 GALL AMP: XI.E3, Inaccessible Medium-Voltage Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001432006-03-22022 March 2006 GALL AMP: XI.S7, Rg 1.127, Inspection of Water-Control Structures Associated with Nuclear Power Plants (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505492006-03-22022 March 2006 GALL AMP: XI.M19, Steam Generator Tube Integrity (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505872006-03-22022 March 2006 GALL AMP: XI.M26, Fire Protection (Audit Worksheet GALL Report AMP) Project stage: Other ML0609501952006-03-22022 March 2006 GALL AMP: Plant-Specific (Audit Worksheet - GALL Report AMP) Project stage: Other ML0609503702006-03-22022 March 2006 GALL AMP: XI.M15, Neutron Noise Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503012006-03-22022 March 2006 GALL AMP: XI.M6, BWR Control Rod Drive Return Line Nozzle (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503282006-03-22022 March 2006 GALL AMP: XI.M9, BWR Vessels Internals (Audit Worksheet GALL Report AMP) Project stage: Other ML0610000962006-03-22022 March 2006 GALL AMP: XI.S1, ASME Section XI, Subsection IWE (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502692006-03-22022 March 2006 GALL AMP: XI.E6, Electrical Cable Connections Not Subject to 10 CFR 50.49 Environmental Qualification Requirements (Audit Worksheet, GALL Report AMP) Project stage: Other ML0609502622006-03-22022 March 2006 GALL AMP: XI.E5, Fuse Holder (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503312006-03-22022 March 2006 GALL AMP: XI.M10, Boric Acid Corrosion (Audit Worksheet GALL Report AMP) Project stage: Other 1998-02-28
[Table View] |
|
---|
Category:Letter type:BVY
MONTHYEARBVY 24-028, Pre-Notice of Disbursement from Decommissioning Trust2024-10-31031 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-10-30030 October 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-013, Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 20232024-03-27027 March 2024 Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 2023 BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust 2024-07-30
[Table view] Category:Graphics incl Charts and Tables
MONTHYEARML24053A2582024-03-0101 March 2024 Enclosure 1 - Information Insufficiencies Related to the Acceptance of VY License Termination Plan ML24053A2592024-03-0101 March 2024 Enclosure 2 - Observations Related to the Acceptance Review of the VY License Termination Plan ML17150A2562017-06-0505 June 2017 Entergy Fleet - 2017 Onsite Insurance Submittal Review for Entergy Operations, Inc., and Entergy Nuclear Operations, Inc. (CAC No. TM3058) ML16056A1392016-03-11011 March 2016 Correction to the U.S. Nuclear Regulatory Commission Analysis of Licensees' Decommissioning Funding Status Reports ML14307B7072014-12-10010 December 2014 Supplemental Information Related to Development of Seismic Risk Evaluations for Information Request Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-T BVY 13-065, Response to Request for Additional Information Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)2013-07-19019 July 2013 Response to Request for Additional Information Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) BVY 13-054, Response to Request for Additional Information Regarding Relief Request Nos. ISI-01 and ISI-032013-06-27027 June 2013 Response to Request for Additional Information Regarding Relief Request Nos. ISI-01 and ISI-03 BVY 13-037, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2013-04-29029 April 2013 Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident BVY 10-069, License Renewal Application Annual Update Information2010-12-30030 December 2010 License Renewal Application Annual Update Information ML0934313182009-12-0101 December 2009 Updated Decommissioning Shortfalls as of December 1, 2009 ENOC-08-00040, Commitment Update Relating to Application for Order Approving Indirect Transfer of Control of Licenses2008-07-28028 July 2008 Commitment Update Relating to Application for Order Approving Indirect Transfer of Control of Licenses ML0736502282007-12-11011 December 2007 (PA-LR) VY Response to RAI 4.3.3-2 ENOC-07-00036, Entergy Operations, Inc. - Supplemental Information in Support of Application for Order Approving Indirect Transfer of Control of Licenses2007-10-31031 October 2007 Entergy Operations, Inc. - Supplemental Information in Support of Application for Order Approving Indirect Transfer of Control of Licenses ML0728203072007-10-11011 October 2007 Electronic Distribtion Initiative Letter, Licensee List, Electronic Distribution Input Information, Division Plant Mailing Lists ML0728802822007-08-23023 August 2007 E-Mail from B. Norris of USNRC to R. Powell of USNRC, Regarding Proposed Watchbill ML0728510722007-08-0707 August 2007 E-mail from R. Powell of USNRC to B. Sienel and J. Benjamin of USNRC, Regarding Watchbill ML0728509272007-07-30030 July 2007 E-mail from R. Powell of USNRC to Various, Regarding VY Strike Preps ML0719905012007-06-18018 June 2007 (PA-LR) Pg 2-38 Info ML0701705882007-01-0909 January 2007 VYNPS - SEIS Web Reference - Us Census County Business Patterns ML0712004792006-12-31031 December 2006 VYNPS - SEIS Reference - Hazardous Waste Generation 2004-2006 ML0629204172006-10-0303 October 2006 (E-Mail) Current Air Cert and Fishway Temperature Table from 2003 Annual Report ML0627802552006-06-21021 June 2006 Email: (PA) VY LRA Lists ML0617301862006-05-24024 May 2006 VYNPS, DR-53 Location Exposure Rate Status-Pre Power Up, Pre and Post Shield ML0617705932006-04-10010 April 2006 State of Vermont, Environmental Radiation Surveillance Report, 2005 Summary. Vermont Department of Health Office of Radiological Health ML0617302162006-03-28028 March 2006 Vernon VT FY2006 Municipality Reconciliation, Final Data Based on Final Education Grand Lists ML0617302372005-12-31031 December 2005 Average Connecticut River Discharge (Cfs) at Vernon Station for the Year 2005 ML0617302362005-12-31031 December 2005 VYNPS, Table 3. Vermont Yankee Effluent and Waste Disposal Annual Report ML0617303212005-08-12012 August 2005 Ltr from VYNPS to VT Anr Transmitting Additional Information and Corrected Data Indirect Permit Renewal Application, Effluent and Groundwater Data Aug 22, 2005 ML0501003432005-07-0707 July 2005 Technical Assistance Related to Auditing Vermont Yankee Containment Analysis for Evaluation of NPSH ML0617303192005-07-0606 July 2005 Ltr from VYNPS to VT Anr Transmitting the Renewal Application for Indirect Discharge Permit July 6, 2005 ML0513703142005-05-11011 May 2005 Relief Request B-5, Response to Request for Additional Information ML0617705892004-12-31031 December 2004 State of Vermont, Environmental Radiation Surveillance Report, 2004 Summary. Vermont Department of Health Office of Radiological Health ML0617301822004-12-0101 December 2004 VYNPS, Table 2. Summary of Site Boundary Direct Shine Doses and EPU Scaling Factors ML0617706062003-12-31031 December 2003 State of Vermont, Environmental Radiation Surveillance Report, 2003 Summary 2024-03-01
[Table view] |
Text
Entergy Nuclear Operations, Inc.
Vermont Yankee 320 Governor Hunt Rd Entergy Vernon, VT 05354 Tel 802 257 7711 Michael J. Colomb Site Vice President December 30, 2010 BVY 10-069 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
License Renewal Application Annual Update Vermont Yankee Nuclear Power Station Docket No. 50-271 License No. DPR-28
REFERENCES:
- 1. Letter, Entergy to USNRC, "Vermont Yankee Nuclear Power Station, License No. DPR-28, License Renewal Application," BVY 06-09, dated January 25, 2006.
Dear Sir or Madam:
On January 25, 2006, Entergy Nuclear Operations, Inc. and Entergy Nuclear Vermont Yankee, LLC (Entergy) submitted the License Renewal Application (LRA) for the Vermont Yankee Nuclear Power Station (VYNPS) as indicated by Reference 1.
During the NRC review of the VYNPS LRA, Entergy is required by 10CFR54.21 (b) to report changes to the current licensing basis (CLB) that materially affect the content of the VYNPS LRA, including the Safety Analysis Report (SAR) supplement. This information is required to be submitted annually and at least three months prior to the scheduled completion of the NRC review. In accordance with the requirements of 10 CFR 54.21(b), Entergy has completed a review and LRA impacts are-discussed in Attachment 1 of this letter.
There are no new regulatory commitments being made in this letter.
Should you have any questions or require additional information concerning this submittal, please contact Mr. Robert J. Wanczyk at 802-451-3166.
I declare under penalty of perjury, that the foregoing is true and correct.
Executed on December 30, 2010 Sincerely,
[MJC/PLC]
ýx\A
BVY 10-069 / Page 2 of 2 Attachments: 1. License Renewal Application Annual Update Information cc: Mr. Eric J. Leeds, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission One White Flint North 13H16M 11555 Rockville Pike Rockville, MD 20852-2738 Mr. William M. Dean, Regional Administrator U.S. Nuclear Regulatory Commission, Region 1 475 Allendale Road King of Prussia, PA 19406-1415 Mr. Robert Kuntz, Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint North 11 F1 11555 Rockville Pike Rockville, MD 20852-2738 Mr. James S. Kim, Project Manager Office of Nuclear Reactor. Regulation U.S. Nuclear Regulatory Commission Mail Stop 08C2A Washington, DC 20555 USNRC Resident Inspector Entergy Nuclear Vermont Yankee 320 Governor Hunt Road Vernon, Vermont 05354 Mr. David O'Brien, Commissioner VT Department of Public Service 112 State Street - Drawer 20 Montpelier, Vermont 05620-2601
BVY'10-069 Docket No. 50-271 Attachment 1 Vermont Yankee Nuclear Power Station License Renewal Application Annual Update Information
BVY 10-069 / Attachment 1 / page 1 of 2 Vermont Yankee Nuclear Power Station License Renewal Application Annual Update Information The review performed as part of the annual update identified the following impacts to the LRA.
VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL COMMITMENT LIST During the development and review of the Vermont Yankee Nuclear Power Station License Renewal Application, Entergy made commitments to provide aging management programs to manage the effects of aging on structures and components during the extended period of operation.
The following table lists those license renewal commitments that have been revised but not identified in separate correspondence, along with the implementation schedule and the source of the commitment. New text is underlined and deleted text is shown as strikethrough.
ITEM COMMITMENT IMPLEMENTATION SOURCE Related LRA SCHEDULE Section NoJ
_Comments 4 The Diesel Fuel Monitoring Program will be enhanced to specify UT March 21,2012 BVY 06-009 B.1.9 and measurements of the fuel oil storage and fire pump diesel storage (day) BVY 07-018 regional tank bottom surfaces will have acceptance criterion g 60,%Tn.m.e.in BVY 10-069 inspection accordance with the applicable American Petroleum Institute or Steel Tank Institute standard.
29 VYNPS will perform one of the following: March 21, 2012 BVY 06-009 B.1.7 BVY 10-069 Audit Item 9
- 1. Install core plate wedges, or,
- 2. Complete a plant-specific analysis to determine acceptance criteria for continued inspection of core plate hold down bolting in accordance with BWRVIP-25 and submit the inspection plan and analysis to the NRC one tw. years prior to the period of extended operation for NRC review and approval.
46 Enhance the Diesel Fuel Monitoring Program to specify that fuel oil in the March 21, 2012 BVY 07-018 Regional fire pump diesel storage (day) tank will be analyzed according tO ASTM BVY 10-069 inspection D975-02 (or later revisions of this standard) and for particulates per ASTM D2276. Also, fuel oil in the John Deere diesel storage tank will be analyzed for particulates per ASTM D2276.
BVY 10-069 / Attachment 1 / page 2 of 2 ITEM COMMITMENT IMPLEMENTATION SOURCE Related LRA SCHEDULE Section Nol Comments 47 Enhance the Diesel Fuel Monitoring Program to specify that fuel oil in the March 21, 2012 BVY 07-018 Regional common portable fuel oil storage tank will be analyzed according to ASTM BVY 10-069 inspection D975-02 (or later revisions of this standard), per ASTM D2276 for particulates, and ASTM D1796 for water and sediment.
50 During the period of extended operation, review the Vernon Dam owner March 21, 2012 BVY 06-009 RAI FERC required report(s) at a minimum of every five years to confirm that BVY 07-047 3.6.2.2.N-08-1 the Vernon Dam owner is performing the required FERC inspections. BVY 10-069 Document deficiencies in the Entergy Corrective Actions Program and evaluate operability as described in BVY 96-043 and BVY 97-02543 if it is determined that the required inspections are not being performed.