Other: BVY 06-076, License Renewal Application, Amendment 8, BVY 06-079, License Renewal Application, Amendment 11, BVY 06-083, License Renewal Application, Amendment 12, BVY 06-096, License Renewal Application, Amendment No. 17, BVY 06-097, License Renewal Application, Amendment 19, BVY 06-098, License Renewal Application, Amendment 20, BVY 07-009, License Renewal Application, Amendment 24, BVY 07-018, License Renewal Application, Amendment 26, BVY 07-034, License Renewal Application Annual Update, BVY 07-047, License Renewal Application, Amendment 27, Submitted on January 25, 2006, BVY 07-058, License Renewal Application, Amendment 29, BVY 07-062, License Renewal Application, Amendment 30, BVY 07-066, License Renewal Application, Amendment 31, BVY 08-016, (PA-LR) Emailing Bvy 08-016 Final SER Review Comments, BVY 10-069, License Renewal Application Annual Update Information, BVY-06-083, License Renewal Application, Amendment 12, ML060950195, ML060950215, ML060950218, ML060950220, ML060950224, ML060950235, ML060950250, ML060950258, ML060950262, ML060950269, ML060950271, ML060950277, ML060950279, ML060950284, ML060950290, ML060950301, ML060950311, ML060950323, ML060950328, ML060950331, ML060950347, ML060950351, ML060950356, ML060950364, ML060950370, ML060950372, ML060950375, ML060950540, ML060950549, ML060950559, ML060950567, ML060950570, ML060950573, ML060950579... further results
|
MONTHYEARML0609503511998-02-28028 February 1998 GALL AMP: XI.M12, Thermal Aging Embrittlement of Cast Austenitic Stainless Steel (CASS) (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505492006-03-22022 March 2006 GALL AMP: XI.M19, Steam Generator Tube Integrity (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506342006-03-22022 March 2006 GALL AMP: XI.M35, One-Time Inspection of ASME Code Class 1 Small Bore Piping (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506242006-03-22022 March 2006 GALL AMP: XI.M32, One-Time Inspection (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506102006-03-22022 March 2006 GALL AMP: XI.M29, Aboveground Steel Tanks (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506062006-03-22022 March 2006 GALL AMP: XI.M28, Buried Piping and Tanks Surveillance (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505732006-03-22022 March 2006 GALL AMP: XI.M23, Inspection of Overhead Heavy Load and Light Load (Related to Refueling) Handling Systems (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505702006-03-22022 March 2006 GALL AMP: XI.M22, Boraflex Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505672006-03-22022 March 2006 GALL AMP: XI.M21, Closed-Cycle Cooling Water System (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502772006-03-22022 March 2006 GALL AMP: XI.M2, Water Chemistry (Audit Worksheet, GALL Report AMP) Project stage: Other ML0610000782006-03-22022 March 2006 GALL AMP: XI.M38, Inspection of Internal Surfaces in Miscellaneous Piping and Ducting Components (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503752006-03-22022 March 2006 GALL AMP: XI.M17, Flow-Accelerated Corrosion (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503722006-03-22022 March 2006 GALL AMP: XI.M16, PWR Vessel Internals (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503642006-03-22022 March 2006 GALL AMP: XI.M14, Loose Part Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503562006-03-22022 March 2006 GALL AMP: XI.M13, Thermal Aging and Neutron Irradiation Embrittlement of Cast Austenitic Stainless Steel (CASS) (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503472006-03-22022 March 2006 GALL AMP: XI.M11A, Nickel Alloy Penetration Nozzles Welded to the Upper Reactor Vessel Closure Heads of Pressurized Water Reactors Project stage: Other ML0609503312006-03-22022 March 2006 GALL AMP: XI.M10, Boric Acid Corrosion (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502712006-03-22022 March 2006 GALL AMP: XI.M1, ASME Section XI Inservice Inspection, Subsections Iwb, Iwc, and Iwd (Audit Worksheet, GALL Report AMP) Project stage: Other ML0609502692006-03-22022 March 2006 GALL AMP: XI.E6, Electrical Cable Connections Not Subject to 10 CFR 50.49 Environmental Qualification Requirements (Audit Worksheet, GALL Report AMP) Project stage: Other ML0610000902006-03-22022 March 2006 GALL AMP: XI.M39, Lubricating Oil Analysis Program (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502902006-03-22022 March 2006 GALL AMP: XI.M5, BWR Feedwater Nozzle (Audit Worksheet, GALL Report AMP) Project stage: Other ML0609503012006-03-22022 March 2006 GALL AMP: XI.M6, BWR Control Rod Drive Return Line Nozzle (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503112006-03-22022 March 2006 GALL AMP: XI.M7, BWR Stress Corrosion Cracking (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503232006-03-22022 March 2006 GALL AMP: XI.M8, BWR Penetrations (Audit Worksheet, GALL Report AMP) Project stage: Other ML0610000962006-03-22022 March 2006 GALL AMP: XI.S1, ASME Section XI, Subsection IWE (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001012006-03-22022 March 2006 GALL AMP: XI.S2, ASME Section XI, Subsection Iwl (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001262006-03-22022 March 2006 GALL AMP: XI.S4, 10 CFR 50, Appendix J (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001342006-03-22022 March 2006 GALL AMP: XI.S5, Masonry Wall Progam (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001382006-03-22022 March 2006 GALL AMP: XI.S6, Structures Monitoring Program (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001432006-03-22022 March 2006 GALL AMP: XI.S7, RG 1.127, Inspection of Water-Control Structures Associated with Nuclear Power Plants (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001472006-03-22022 March 2006 GALL AMP: XI.S8, Protective Coating Monitoring and Maintenance Program (Audit Worksheet GALL Report AMP) Project stage: Other ML0609501952006-03-22022 March 2006 GALL AMP: Plant-Specific (Audit Worksheet - GALL Report AMP) Project stage: Other ML0609502182006-03-22022 March 2006 GALL AMP: X.M1, Metal Fatigue of Reactor Coolant Pressure Boundary (Audit Worksheet, GALL Report AMP) Project stage: Other ML0609503702006-03-22022 March 2006 GALL AMP: XI.M15, Neutron Noise Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502622006-03-22022 March 2006 GALL AMP: XI.E5, Fuse Holder (Audit Worksheet GALL Report AMP) Project stage: Other ML0610001162006-03-22022 March 2006 GALL AMP: XI.S3, ASME Section XI, Subsection Iwf (Audit Worksheet GALL Report AMP) Project stage: Other ML0609503282006-03-22022 March 2006 GALL AMP: XI.M9, BWR Vessels Internals (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502842006-03-22022 March 2006 GALL AMP: XI.M4, BWR Vessel Id Attachment Welds (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506452006-03-22022 March 2006 GALL AMP: XI.M37, Flux Thimble Tube Inspection (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506372006-03-22022 March 2006 GALL AMP: XI.M36, External Surfaces Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506322006-03-22022 March 2006 GALL AMP: XI.M34, Buried Piping and Tanks Inspection (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506292006-03-22022 March 2006 GALL AMP: XI.M33, Selective Leaching of Materials (Audit Worksheet GALL Report AMP) Project stage: Other ML0609506202006-03-22022 March 2006 GALL AMP: XI.M31, Reactor Vessel Surveillance (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502792006-03-22022 March 2006 GALL AMP: XI.M3, Reactor Head Closure Studs (Audit Worksheet, GALL Report AMP) Project stage: Other ML0609505962006-03-22022 March 2006 GALL AMP: XI.M27, Fire Water System (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505872006-03-22022 March 2006 GALL AMP: XI.M26, Fire Protection (Audit Worksheet GALL Report AMP) Project stage: Other ML0609505792006-03-22022 March 2006 GALL AMP: XI.M24, Compressed Air Monitoring (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502582006-03-22022 March 2006 GALL AMP: XI.E4, Metal Enclosed Bus (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502502006-03-22022 March 2006 GALL AMP: XI.E3, Inaccessible Medium-Voltage Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements (Audit Worksheet GALL Report AMP) Project stage: Other ML0609502352006-03-22022 March 2006 GALL AMP: XI.E2, Electrical Cables and Connections Not Subject to 10 CFR 50.49 Environmental Qualification Requirements Used in Instrumentation Circuits (Audit Worksheet GALL Report AMP) Project stage: Other 1998-02-28
[Table View] |
Text
XI.M10 Boric Acid Corrosion 1
AUDIT WORKSHEET GALL REPORT AMP PLANT: ______________________________
LRA AMP: __________________________
REVIEWER: ______________________
GALL AMP: XI.M10, Boric Acid Corrosion____
DATE: __________________________
Program Element Auditable GALL Criteria Documentation of Audit Finding Program Description A. The program relies in part on implementation of recommendations in Nuclear Regulatory Commission (NRC)
Generic Letter (GL) 88-05 to monitor the condition of the reactor coolant pressure boundary for borated water leakage. Periodic visual inspection of adjacent structures, components, and supports for evidence of leakage and corrosion is an element of the NRC GL 88-05 monitoring program. Potential improvements to boric acid corrosion programs have been identified as a result of recent operating experience with cracking of certain nickel alloy pressure boundary components (NRC Regulatory Issue Summary 2003-013). Borated water leakage from piping and components that are outside the scope of the program established in response to GL 88-05 may affect structures and components that are subject to aging management review.
Therefore, the scope of the monitoring and inspections of this program includes all components that contain borated water that are in proximity to structures and components that are subject to aging management review. The scope of the evaluations, assessments and corrective actions include all observed leakage sources and the affected structures and components.
Borated water leakage may be discovered by activities other than those established specifically to detect such leakage.
Therefore, the program includes provisions for triggering evaluations and assessments when leakage is discovered by other activities.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
XI.M10 Boric Acid Corrosion 2
Program Element Auditable GALL Criteria Documentation of Audit Finding
- 1. Scope of Program A. The program covers any structures or components on which boric acid corrosion may occur (e.g., steel and aluminum), and electrical components on which borated reactor water may leak.
The program includes provisions in response to the recommendations of NRC GL 88-05. The staff guidance of NRC GL 88-05 provides a program consisting of systematic measures to ensure that corrosion caused by leaking borated coolant does not lead to degradation of the leakage source or adjacent structures and components, and provides assurance that the reactor coolant pressure boundary will have an extremely low probability of abnormal leakage, rapidly propagating failure, or gross rupture. Such a program provides for (a) determination of the principal location of leakage, (b) examination requirements and procedures for locating small leaks, and (c) engineering evaluations and corrective actions to ensure that boric acid corrosion does not lead to degradation of the leakage source or adjacent structures or components, which could cause the loss of intended function of the structures or components.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment
- 2. Preventive Actions A. Minimizing reactor coolant leakage by frequent monitoring of the locations where potential leakage could occur and timely repair if leakage is detected prevents or mitigates boric acid corrosion. Preventive measures also include modifications in the design or operating procedures to reduce the probability of leaks at locations where they may cause corrosion damage and use of suitable corrosion resistant materials or the application of protective coatings.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
- 3. Parameters Monitored/
Inspected A. The aging management program (AMP) monitors the effects of boric acid corrosion on the intended function of an affected structure and component by detection of borated water leakage.
Borated water leakage results in deposits of white boric acid crystals and the presence of moisture that can be observed by the naked eye.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
XI.M10 Boric Acid Corrosion 3
Program Element Auditable GALL Criteria Documentation of Audit Finding
- 4. Detection of Aging Effects A. Degradation of the component due to boric acid corrosion cannot occur without leakage of borated water. Conditions leading to boric acid corrosion, such as crystal buildup and evidence of moisture, are readily detectable by visual inspection, though removal of insulation may be required in some cases. The program delineated in NRC GL 88-05 includes guidelines for locating small leaks, conducting examinations, and performing engineering evaluations. In addition, the program includes appropriate interfaces with other site programs and activities such that borated water leakage that is encountered by means other than the monitoring and trending established by this program is evaluated and corrected. Thus, the use of the NRC GL 88-05 program will assure detection of leakage before the loss of the intended function of the affected components.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
- 5. Monitoring and Trending A. The program provides monitoring and trending activities as delineated in NRC GL 88-05, timely evaluation of evidence of borated water leakage identified by other means, and timely detection of leakage by observing boric acid crystals during normal plant walkdowns and maintenance.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
- 6. Acceptance Criteria A. Any detected borated water leakage or crystal buildup will be evaluated to confirm or restore the intended functions of affected structures and components consistent with the design basis prior to continued service.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
- 7. Corrective Actions A. Borated water leakage and areas of resulting boric acid corrosion are evaluated and corrected in conformance with the applicable provisions of NRC GL 88-05 and the corrective action program. Any detected boric acid crystal buildup or deposits should be cleaned. NRC GL 88-05 recommends that corrective actions to prevent recurrences of degradation caused by Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
XI.M10 Boric Acid Corrosion 4
Program Element Auditable GALL Criteria Documentation of Audit Finding borated water leakage be included in the program implementation. These corrective actions include any modifications to be introduced in the present design or operating procedures of the plant that (a) reduce the probability of primary coolant leaks at locations where they may cause corrosion damage, and (b) entail the use of suitable corrosion resistant materials or the application of protective coatings or claddings.
As discussed in the appendix to this report, the staff finds the requirements of 10 CFR Part 50, Appendix B, acceptable to address the corrective actions.
- 8.
Confirmation Process A. Site quality assurance (QA) procedures, review and approval processes, and administrative controls are implemented in accordance with the requirements of 10 CFR Part 50, Appendix B. As discussed in the appendix to this report, the staff finds the requirements of 10 CFR Part 50, Appendix B, acceptable to address confirmation process and administrative controls.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
- 9.
Administrative Controls A. See Item 8, above.
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
- 10. Operating Experience A. Boric acid corrosion has been observed in nuclear power plants (NRC Information Notices [INs] 86-108 [and supplements 1 through 3] and 2003-02) and has resulted in significant impairment of component intended functions in areas that are difficult to access/observe (NRC Bulletin 2002-01).
Consistent with GALL AMP:
Yes No Document(s) used to confirm Criteria:
Comment:
XI.M10 Boric Acid Corrosion 5
EXCEPTIONS Item Number Program Elements LRA Exception Description Basis for Accepting Exception Documents Reviewed (Identifier, Para.# and/or Page #)
- 1.
- 2.
ENHANCEMENTS Item Number Program Elements LRA Enhancement Description Basis for Accepting Enhancement Documents Reviewed (Identifier, Para.# and/or Page #)
- 1.
- 2.
DOCUMENT REVIEWED DURING AUDIT Document Number Identifier (number)
Title Revision and/or Date
- 1.
- 2.
- 3.
- 4.
.