August 30, 2005 Mr. Gene St. Pierre Site Vice President FPL Energy Seabrook, LLC Seabrook Station c/o Mr. James M. Peschel P.O. Box 300 Seabrook, NH 03874

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - SEABROOK STATION

Dear Mr. St. Pierre:

On August 2, 2005, the NRC staff completed its performance review of Seabrook Nuclear Power Station for the first half of the calendar year 2005 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.

Plant performance for the most recent quarter for Seabrook Nuclear Power Station was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process baseline inspections at your facility.

The enclosed inspection plan lists the inspections, less those related to physical protection, scheduled through March 31, 2007. The inspection plan is provided to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

Mr. Gene St. Pierre 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARs) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5120 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Paul G. Krohn, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No. 50-443 License No: NPF-86

Enclosure:

Seabrook Nuclear Power Station Inspection/Activity Plan

Mr. Gene St. Pierre 3 cc w/encl:

J. A. Stall, FPL Senior Vice President, Nuclear & CNO J. M. Peschel, Manager - Regulatory Programs M. Kiley, Station Director - Seabrook Station J. Dent, Assistant Plant Manager R. S. Kundalkar, FPL Vice President - Nuclear Engineering D. G. Roy, Nuclear Training Manager - Seabrook Station Office of the Attorney General, Commonwealth of Massachusetts P. McLaughlin, Attorney General, State of New Hampshire P. Brann, Assistant Attorney General, State of Maine M. S. Ross, Attorney, Florida Power & Light Company R. Walker, Director, Dept. of Public Health, Commonwealth of Massachusetts B. Cheney, Director, Bureau of Emergency Management C. McCombs, Acting Director, MEMA Health Physicist, Office of Community & Public Health, State of New Hampshire Administrator, Bureau of Radiological Health, State of New Hampshire J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company T. Crimmins, Polestar Applied Technology R. Backus, Esquire, Backus, Meyer and Solomon, New Hampshire Town of Exeter Board of Selectmen S. Comley, Executive Director, We the People of the United States R. Shadis, New England Coalition Staff M. Metcalf, Seacoast Anti-Pollution League Institute of Nuclear Power Operations (INPO)

Mr. Gene St. Pierre 4 Distribution w/encl: (VIA E-MAIL)

S. Collins, RA M. Dapas, DRA B. Holian, DRP D. Lew, DRP P. Krohn, DRP G. Barber, DRP B. Norris, DRP G. Dentel, DRP - Senior Resident Inspector S. Nelson, DRP - Resident OA S. Lee, RI OEDO D. Roberts, NRR V. Nerses, NRR, PM J. Boska, NRR DRS Director and Deputy Director (Mid-Cycle/Assessment ONLY)

DRS Branch Chiefs (5) (Mid-Cycle/Assessment ONLY)

D. Screnci, PAO (Mid-Cycle/Assessment Ltrs)

C. ODaniell, DRP (Mid-Cycle/Assessment Ltrs)

RidsNrrDipmIipb@nrc.gov Region I Docket Room (with concurrences)

SISP Review Complete: PGK (Reviewers Initials)

DOCUMENT NAME: S:\ROP-6 Mid-Cycle Review\2005 Mid-Cycle Letters\Seabrook ROP 6 Mid-Cycle Assessment Letter.wpd After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure " N" = No copy OFFICE R1/DRP E R1/DRP E R1/DRP NAME SBarber/GSB SShaffer/GSB for PKrohn/PGK DATE 08/03/2005 08/05/2005 08/10/2005 OFFICIAL RECORD COPY

Page 1 of 1 Seabrook 08/30/2005 10:50:20 Inspection / Activity Plan Report 22 08/01/2005 - 03/31/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71114 - EP PROGRAM & EP PI INSPECTION 1 1 IP 7111402 Alert and Notification System Testing 08/29/2005 09/02/2005 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 08/29/2005 09/02/2005 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 08/29/2005 09/02/2005 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 08/29/2005 09/02/2005 Baseline Inspections 1 IP 71151 Performance Indicator Verification 08/29/2005 09/02/2005 Baseline Inspections 7111111B - LO REQUAL PROGRAM INPSECTION&P/F RESULTS 2 1 IP 7111111B Licensed Operator Requalification Program 12/12/2005 12/16/2005 Baseline Inspections 1 IP 7111111B Licensed Operator Requalification Program 12/19/2005 12/23/2005 Baseline Inspections 7112203 - PUB RAD SAFETY - REMP 1 1 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 12/19/2005 12/23/2005 Baseline Inspections 7112101 - OCC RAD SAFETY - ACCESS 1 1 IP 7112101 Access Control to Radiologically Significant Areas 01/17/2006 01/20/2006 Baseline Inspections MODS - MODS & 50.59 3 1 IP 7111102 Evaluation of Changes, Tests, or Experiments 03/13/2006 03/17/2006 Baseline Inspections 1 IP 7111117B Permanent Plant Modifications 03/13/2006 03/17/2006 Baseline Inspections 7111401 - EXERCISE EVALUATION & EP PI VERIFICATOIN 5 1 IP 7111401 Exercise Evaluation 04/10/2006 04/14/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 04/10/2006 04/14/2006 Baseline Inspections 7112202 - PUB RAD SAFETY - RADWASTE 1 1 IP 7112202 Radioactive Material Processing and Transportation 05/15/2006 05/19/2006 Baseline Inspections 7112103 - OCC RAD SAFETY - INSTRUMENTS 1 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 08/28/2006 09/01/2006 Baseline Inspections 7111108P - INSERVICE INSPECTION 1 1 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA-03-009) 10/23/2006 10/27/2006 Safety Issues 1 IP 7111108P Inservice Inspection Activities - PWR 10/23/2006 10/27/2006 Baseline Inspections 7112102 - OCC RAD SAFETY - ALARA 1 1 IP 7112102 ALARA Planning and Controls 10/23/2006 10/27/2006 Baseline Inspections 71152B - PI&R 5 1 IP 71152B Identification and Resolution of Problems 11/27/2006 12/01/2006 Baseline Inspections 1 IP 71152B Identification and Resolution of Problems 12/11/2006 12/15/2006 Baseline Inspections 7112101 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 01/29/2007 02/02/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.