IR 05000443/2012006

From kanterella
Jump to navigation Jump to search
Mid-Cycle Performance Review and Inspection Plan 2012 - Seabrook Station Unit 1 (Report 05000443/2012006)
ML12248A087
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 09/04/2012
From: Darrell Roberts
Division Reactor Projects I
To: Walsh K
NextEra Energy Seabrook
BURRITT, AL
References
Download: ML12248A087 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION ptember 4, 2012

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

SEABROOK STATION, UNIT NO. 1 (REPORT 05000443/2012006)

Dear Mr. Walsh:

On August 16, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Seabrook Station, Unit No. 1 (Seabrook). The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011 through June 30, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

This assessment reflects the integration of the Security Cornerstone into the ROP performance assessment program governed by IMC 0305, Operating Reactor Assessment Program.

The NRC determined the performance at Seabrook during the most recent quarter was within the Regulatory Response column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because of one low (i.e., white) safety significance Emergency Preparedness cornerstone input described in IR 05000443/2012503, dated April 19, 2012 (ML12151A036)1. This finding involved not identifying an exercise weakness during the post-exercise critique for an April 17, 2012, full-participation emergency exercise. The significance determination for this finding was finalized in our August 7, 2012, letter to you (ML12220A471)1. As stated in that letter, we plan to conduct a supplemental inspection using Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, when you inform us of your readiness. This inspection is conducted to provide assurance that the root cause and contributing causes of any performance issues are understood, the extent of condition is identified, and the corrective actions are sufficient to prevent recurrence.

The enclosed inspection plan lists the inspections scheduled through December 31, 2013.

Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, consistent with the Agencys actions related to Fukushima, the NRC will perform TI-187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns and TI-188, Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns. The NRC will also be conducting IP 92702, Follow-up on Traditional

Designation in parenthesis refers to an ADAMS accession number. Documents referenced in this letter are publicly available using the accession number in ADAMS. Enforcement Actions including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirmatory Orders, which will review actions taken in response to the confirmatory action letter dated May 15, 2012, (ML12125A172)1 which addressed the Alkali-Silica Reaction degradation of certain Seabrook concrete structures and IP 60855.1, Operation of an ISFSI at Operating Plants, which will review operations during the 2013 ISFSI loading campaign. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In accordance with 10 CFR 2.390 of the NRC=s Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agency-wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Art Burritt at 610-337-5069 with any questions you have regarding this letter.

Sincerely,

/RA/

Darrell J. Roberts, Director Division of Reactor Projects Docket Nos.: 50-443 License Nos.: NPF-86 Enclosure: Seabrook Inspection/Activity Plan cc w/encl: Distribution via ListServ

ML12248A087 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP RI/DRP NAME JGreives/LC for LCline/LC ABurritt/LC for DRoberts/DJR DATE 08/27/12 08/27/12 08/27/12 09/04/12

Page 1 of 2 Seabrook 08/31/2012 14:47:30 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 92702 - LR-ASR FOLLOWUP INSPECTION 6 1 07/16/2012 07/20/2012 IP 92702 Followup On Corrective Actions For Violations And Deviations 71124 - OCC RADIATION SAFETY 1 1 07/16/2012 07/20/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 07/16/2012 07/20/2012 IP 71124.02 Occupational ALARA Planning and Controls 1 07/16/2012 07/20/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 07/16/2012 07/20/2012 IP 71124.04 Occupational Dose Assessment TI 182 - DEGRADATION OF UNDERGROUND PIPING 1 1 08/06/2012 08/10/2012 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 71124 - RADWASTE 1 1 08/27/2012 08/31/2012 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation TI-188 - TI-188 - SEISMIC WALKDOWNS 2 1 08/29/2012 12/31/2012 IP 2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns TI-187 - TI-187 - FLOODING WALKDOWNS 2 1 09/03/2012 12/31/2012 IP 2515/175 Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 7111108P - INSERVICE INSPECTION 1 1 09/17/2012 09/21/2012 IP 7111108P Inservice Inspection Activities - PWR 1 10/01/2012 10/05/2012 IP 7111108P Inservice Inspection Activities - PWR EXM 7/16 - SEABROOK INITIAL EXAM 4 1 06/17/2013 06/22/2013 U01870 FY13-SEABROOK INITIAL OPERATOR LICENSING EXAM 1 07/15/2013 07/20/2013 U01870 FY13-SEABROOK INITIAL OPERATOR LICENSING EXAM 71124 - OCC RADIATION SAFETY 1 1 03/11/2013 03/15/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 03/11/2013 03/15/2013 IP 71124.02 Occupational ALARA Planning and Controls 1 03/11/2013 03/15/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 60855 - ISFSI LOADING INSPECTION 2 1 03/01/2013 06/30/2013 IP 60855 Operation Of An ISFSI 1 03/01/2013 06/30/2013 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 7111121 - CDBI 9 1 03/25/2013 03/29/2013 IP 7111121 Component Design Bases Inspection 1 04/08/2013 04/12/2013 IP 7111121 Component Design Bases Inspection 1 04/22/2013 04/26/2013 IP 7111121 Component Design Bases Inspection This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 Seabrook 08/31/2012 14:47:30 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP PROGR - EP PROGRAM INSPECTION 1 1 05/06/2013 05/10/2013 IP 7111402 Alert and Notification System Testing 1 05/06/2013 05/10/2013 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 05/06/2013 05/10/2013 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 05/06/2013 05/10/2013 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 71124 - RADIO EFFLUENTS 1 1 05/20/2013 05/23/2013 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 71124 - REMP 1 1 07/22/2013 07/26/2013 IP 71124.07 Radiological Environmental Monitoring Program 7111111B - SEABROOK REQUAL INSP WITH P/F RESULTS 2 1 12/09/2013 12/13/2013 IP 7111111B Licensed Operator Requalification Program This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.