MONTHYEARML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) IR 05000443/20220062023-03-0101 March 2023 Annual Assessment Letter for Seabrook Station (Report 05000443/2022006) IR 05000443/20220052022-08-31031 August 2022 Updated Inspection Plan for Seabrook Station (Report 05000443/2022005) IR 05000443/20210062022-03-0202 March 2022 Annual Assessment Letter for Seabrook Station, Unit 1 (Report 05000443/2021006) ML21322A2612021-11-18018 November 2021 Request for Information for a Triennial Baseline Design Bases Assurance Inspection (Teams); Inspection Report 05000443/2022011 IR 05000443/20210052021-09-0101 September 2021 Updated Inspection Plan for the Seabrook Station (Report 05000443/2021005) IR 05000443/20200062021-03-0303 March 2021 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2020006) IR 05000443/20210132021-01-20020 January 2021 Information Request to Support Triennial Baseline Design-Basis Capabilities of Power-Operated Valves Inspection; Inspection Reportt 05000443/2021013 IR 05000443/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000443/2020005) IR 05000443/20190062020-03-0303 March 2020 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2019006) IR 05000443/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000443/2019005) ML19141A0552019-05-21021 May 2019 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000443/2019403 IR 05000443/20180062019-03-0404 March 2019 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2018006) IR 05000443/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000443/2018005) IR 05000443/20170062018-02-28028 February 2018 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Reports 05000443/2017006, 05000443/2017402, And05000443/2017501) IR 05000443/20170052017-08-28028 August 2017 Updated Inspection Plan for Seabrook Station, Unit No. 1 (Report 05000443/2017005) IR 05000443/20160062017-03-0101 March 2017 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2016006) IR 05000443/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Seabrook Nuclear Power Plant, Unit No. 1 (Report 05000443/2016005) IR 05000443/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Seabrook Station, Unit 1 (Report 05000443/2015006) IR 05000443/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2014001) IR 05000443/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000443/2014006 IR 05000443/20130012014-03-0404 March 2014 ROP-14 2013 Seabrook Station Unit 1 Annual Assessment Letter, Report 05000443/2013001, and Inspection Plan ML13246A1072013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000443/2013006 IR 05000443/20120012013-03-0404 March 2013 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2012001) IR 05000443/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Seabrook Station Unit 1 (Report 05000443/2012006) ML12174A0192012-06-0404 June 2012 Paper - Inspection Planned for Week of 9/26/11 with Modes, Chaudhary, Thomas, Sheikh, and Erickson, USNRC IR 05000443/20110012012-03-0505 March 2012 Annual Assessment Letter for Seabrook Station, Unit 1 (Report No. 05000443-11-001) ML1124113402011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Seabrook Station, Unit 1 IR 05000443/20100012011-03-0404 March 2011 Annual Assessment Letter for Seabrook Station, Unit 1, EOC-11 (Report 05000443-10-001) ML1024403952010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Seabrook Station, Unit 1 ML1006208582010-03-0303 March 2010 EOC Annual Assessment Letter and Report 22 ML0924403172009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Seabrook Station, Unit 1 IR 05000443/20090012009-03-0404 March 2009 Annual Assessment Letter - Seabrook Station Unit 1 (05000443/2009001) ML0824700702008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Seabrook, Unit 1 IR 05000443/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Seabrook Station 05000443-08-001) ML0734706872007-12-13013 December 2007 ROP 8 - Seabrook - Change to Inspection Plan, 12/13/07 ML0724309432007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan IR 05000443/20060012006-03-0202 March 2006 Annual Assessment Letter - Seabrook Nuclear Power Station (Report 05000443/2006001) ML0524207202005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Seabrook IR 05000443/20050012005-03-0202 March 2005 Annual Assessment Letter - Seabrook Nuclear Generating Station (Report 05000443/2005001) ML0424402002004-08-30030 August 2004 Seabrook ROP5 Mid-Cycle Performance Review and Inspection Plan ML0406301482004-03-0303 March 2004 Annual Assessment Letter - Seabrook IR 05000443/20030012003-03-0303 March 2003 2003 Annual Assessment Letter - Seabrook Station (Report No. 50-443/03-001) IR 05000443/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Seabrook Station (Report No. 50-443/02-001) 2023-08-31
[Table view] Category:Letter
MONTHYEARML24009A1152024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24022A0652024-01-22022 January 2024 Senior Reactor and Reactor Operator Initial License Examinations L-2024-003, NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report2024-01-11011 January 2024 NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report ML23312A1822023-12-22022 December 2023 Issuance of Amendment No. 172 Revision to Cooling Tower Service Water Loop or Cell Requirements L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-180, Submittal of Changes to the Technical Specification Bases2023-12-13013 December 2023 Submittal of Changes to the Technical Specification Bases L-2023-177, Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-160, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule ML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20234032023-11-0707 November 2023 Security Baseline Inspection Report 05000443/2023403 and Independent Spent Fuel Storage Installation 07200063/2023401 IR 05000443/20230032023-11-0606 November 2023 Integrated Inspection Report 05000443/2023003 IR 05000443/20230102023-10-19019 October 2023 Triennial Fire Protection Inspection Report 05000443/2023010 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A0522023-10-0202 October 2023 Requalification Program Inspection IR 05000443/20234012023-09-0808 September 2023 Cybersecurity Inspection Report 05000443/2023401 (Cover Letter Only) IR 05000443/20234202023-09-0505 September 2023 Security Baseline Inspection Report 05000443/2023420 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update IR 05000443/20233022023-08-16016 August 2023 Operator Licensing Retake Examination Report 05000443/2023302 IR 05000443/20230022023-08-0808 August 2023 Integrated Inspection Report 05000443/2023002 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-104, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations L-2023-103, Inservice Inspection Examination Report2023-08-0303 August 2023 Inservice Inspection Examination Report ML23192A0782023-07-11011 July 2023 Operator Licensing Retake Examination Approval L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) SBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 ML23157A0722023-06-0606 June 2023 Notification of Conduct of a Fire Protection Team Inspection L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000443/20233012023-05-15015 May 2023 Initial Operator Licensing Examination Report 05000443/2023301 L-2023-064, License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-05-11011 May 2023 License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves IR 05000443/20230012023-05-11011 May 2023 Integrated Inspection Report 05000443/2023001 ML23129A0312023-05-0909 May 2023 Reactor Operator Retake License Examination ML23117A3652023-05-0404 May 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Remove Period of Applicability from PTL and Low Temperature Over Pressure Protection Curves SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report L-2023-053, Core Operating Limits Report for Cycle 232023-04-0505 April 2023 Core Operating Limits Report for Cycle 23 ML23088A1522023-03-29029 March 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Seabrook 4Q2022 Inspection Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications ML23073A1562023-03-23023 March 2023 Relief Request 4RA-22-01, Relief from the Requirements of the ASME Code L-2023-012, License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-03-15015 March 2023 License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves L-2023-025, Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-12023-03-15015 March 2023 Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-1 L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2023-023, Revised Steam Generator Tube Inspection Report2023-03-0303 March 2023 Revised Steam Generator Tube Inspection Report ML23020A1002023-03-0303 March 2023 OEDO-22-00419 - 2.206 Petition for Seabrook Station Structure Concrete Concerns (EPID L-2022-CRS-0000)- Closure Letter 2024-01-29
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION ptember 4, 2012
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
SEABROOK STATION, UNIT NO. 1 (REPORT 05000443/2012006)
Dear Mr. Walsh:
On August 16, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Seabrook Station, Unit No. 1 (Seabrook). The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011 through June 30, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
This assessment reflects the integration of the Security Cornerstone into the ROP performance assessment program governed by IMC 0305, Operating Reactor Assessment Program.
The NRC determined the performance at Seabrook during the most recent quarter was within the Regulatory Response column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because of one low (i.e., white) safety significance Emergency Preparedness cornerstone input described in IR 05000443/2012503, dated April 19, 2012 (ML12151A036)1. This finding involved not identifying an exercise weakness during the post-exercise critique for an April 17, 2012, full-participation emergency exercise. The significance determination for this finding was finalized in our August 7, 2012, letter to you (ML12220A471)1. As stated in that letter, we plan to conduct a supplemental inspection using Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, when you inform us of your readiness. This inspection is conducted to provide assurance that the root cause and contributing causes of any performance issues are understood, the extent of condition is identified, and the corrective actions are sufficient to prevent recurrence.
The enclosed inspection plan lists the inspections scheduled through December 31, 2013.
Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, consistent with the Agencys actions related to Fukushima, the NRC will perform TI-187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns and TI-188, Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns. The NRC will also be conducting IP 92702, Follow-up on Traditional
Designation in parenthesis refers to an ADAMS accession number. Documents referenced in this letter are publicly available using the accession number in ADAMS. Enforcement Actions including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirmatory Orders, which will review actions taken in response to the confirmatory action letter dated May 15, 2012, (ML12125A172)1 which addressed the Alkali-Silica Reaction degradation of certain Seabrook concrete structures and IP 60855.1, Operation of an ISFSI at Operating Plants, which will review operations during the 2013 ISFSI loading campaign. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with 10 CFR 2.390 of the NRC=s Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agency-wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Art Burritt at 610-337-5069 with any questions you have regarding this letter.
Sincerely,
/RA/
Darrell J. Roberts, Director Division of Reactor Projects Docket Nos.: 50-443 License Nos.: NPF-86 Enclosure: Seabrook Inspection/Activity Plan cc w/encl: Distribution via ListServ
ML12248A087 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP RI/DRP NAME JGreives/LC for LCline/LC ABurritt/LC for DRoberts/DJR DATE 08/27/12 08/27/12 08/27/12 09/04/12
Page 1 of 2 Seabrook 08/31/2012 14:47:30 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 92702 - LR-ASR FOLLOWUP INSPECTION 6 1 07/16/2012 07/20/2012 IP 92702 Followup On Corrective Actions For Violations And Deviations 71124 - OCC RADIATION SAFETY 1 1 07/16/2012 07/20/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 07/16/2012 07/20/2012 IP 71124.02 Occupational ALARA Planning and Controls 1 07/16/2012 07/20/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 07/16/2012 07/20/2012 IP 71124.04 Occupational Dose Assessment TI 182 - DEGRADATION OF UNDERGROUND PIPING 1 1 08/06/2012 08/10/2012 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 71124 - RADWASTE 1 1 08/27/2012 08/31/2012 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation TI-188 - TI-188 - SEISMIC WALKDOWNS 2 1 08/29/2012 12/31/2012 IP 2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns TI-187 - TI-187 - FLOODING WALKDOWNS 2 1 09/03/2012 12/31/2012 IP 2515/175 Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 7111108P - INSERVICE INSPECTION 1 1 09/17/2012 09/21/2012 IP 7111108P Inservice Inspection Activities - PWR 1 10/01/2012 10/05/2012 IP 7111108P Inservice Inspection Activities - PWR EXM 7/16 - SEABROOK INITIAL EXAM 4 1 06/17/2013 06/22/2013 U01870 FY13-SEABROOK INITIAL OPERATOR LICENSING EXAM 1 07/15/2013 07/20/2013 U01870 FY13-SEABROOK INITIAL OPERATOR LICENSING EXAM 71124 - OCC RADIATION SAFETY 1 1 03/11/2013 03/15/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 03/11/2013 03/15/2013 IP 71124.02 Occupational ALARA Planning and Controls 1 03/11/2013 03/15/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 60855 - ISFSI LOADING INSPECTION 2 1 03/01/2013 06/30/2013 IP 60855 Operation Of An ISFSI 1 03/01/2013 06/30/2013 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 7111121 - CDBI 9 1 03/25/2013 03/29/2013 IP 7111121 Component Design Bases Inspection 1 04/08/2013 04/12/2013 IP 7111121 Component Design Bases Inspection 1 04/22/2013 04/26/2013 IP 7111121 Component Design Bases Inspection This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Seabrook 08/31/2012 14:47:30 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP PROGR - EP PROGRAM INSPECTION 1 1 05/06/2013 05/10/2013 IP 7111402 Alert and Notification System Testing 1 05/06/2013 05/10/2013 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 05/06/2013 05/10/2013 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 05/06/2013 05/10/2013 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 71124 - RADIO EFFLUENTS 1 1 05/20/2013 05/23/2013 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 71124 - REMP 1 1 07/22/2013 07/26/2013 IP 71124.07 Radiological Environmental Monitoring Program 7111111B - SEABROOK REQUAL INSP WITH P/F RESULTS 2 1 12/09/2013 12/13/2013 IP 7111111B Licensed Operator Requalification Program This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.