MONTHYEARML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) IR 05000443/20220062023-03-0101 March 2023 Annual Assessment Letter for Seabrook Station (Report 05000443/2022006) IR 05000443/20220052022-08-31031 August 2022 Updated Inspection Plan for Seabrook Station (Report 05000443/2022005) IR 05000443/20210062022-03-0202 March 2022 Annual Assessment Letter for Seabrook Station, Unit 1 (Report 05000443/2021006) ML21322A2612021-11-18018 November 2021 Request for Information for a Triennial Baseline Design Bases Assurance Inspection (Teams); Inspection Report 05000443/2022011 IR 05000443/20210052021-09-0101 September 2021 Updated Inspection Plan for the Seabrook Station (Report 05000443/2021005) IR 05000443/20200062021-03-0303 March 2021 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2020006) IR 05000443/20210132021-01-20020 January 2021 Information Request to Support Triennial Baseline Design-Basis Capabilities of Power-Operated Valves Inspection; Inspection Reportt 05000443/2021013 IR 05000443/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000443/2020005) IR 05000443/20190062020-03-0303 March 2020 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2019006) IR 05000443/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000443/2019005) ML19141A0552019-05-21021 May 2019 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000443/2019403 IR 05000443/20180062019-03-0404 March 2019 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2018006) IR 05000443/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000443/2018005) IR 05000443/20170062018-02-28028 February 2018 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Reports 05000443/2017006, 05000443/2017402, And05000443/2017501) IR 05000443/20170052017-08-28028 August 2017 Updated Inspection Plan for Seabrook Station, Unit No. 1 (Report 05000443/2017005) IR 05000443/20160062017-03-0101 March 2017 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2016006) IR 05000443/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Seabrook Nuclear Power Plant, Unit No. 1 (Report 05000443/2016005) IR 05000443/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Seabrook Station, Unit 1 (Report 05000443/2015006) IR 05000443/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2014001) IR 05000443/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000443/2014006 IR 05000443/20130012014-03-0404 March 2014 ROP-14 2013 Seabrook Station Unit 1 Annual Assessment Letter, Report 05000443/2013001, and Inspection Plan ML13246A1072013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000443/2013006 IR 05000443/20120012013-03-0404 March 2013 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2012001) IR 05000443/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Seabrook Station Unit 1 (Report 05000443/2012006) ML12174A0192012-06-0404 June 2012 Paper - Inspection Planned for Week of 9/26/11 with Modes, Chaudhary, Thomas, Sheikh, and Erickson, USNRC IR 05000443/20110012012-03-0505 March 2012 Annual Assessment Letter for Seabrook Station, Unit 1 (Report No. 05000443-11-001) ML1124113402011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Seabrook Station, Unit 1 IR 05000443/20100012011-03-0404 March 2011 Annual Assessment Letter for Seabrook Station, Unit 1, EOC-11 (Report 05000443-10-001) ML1024403952010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Seabrook Station, Unit 1 ML1006208582010-03-0303 March 2010 EOC Annual Assessment Letter and Report 22 ML0924403172009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Seabrook Station, Unit 1 IR 05000443/20090012009-03-0404 March 2009 Annual Assessment Letter - Seabrook Station Unit 1 (05000443/2009001) ML0824700702008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Seabrook, Unit 1 IR 05000443/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Seabrook Station 05000443-08-001) ML0734706872007-12-13013 December 2007 ROP 8 - Seabrook - Change to Inspection Plan, 12/13/07 ML0724309432007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan IR 05000443/20060012006-03-0202 March 2006 Annual Assessment Letter - Seabrook Nuclear Power Station (Report 05000443/2006001) ML0524207202005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Seabrook IR 05000443/20050012005-03-0202 March 2005 Annual Assessment Letter - Seabrook Nuclear Generating Station (Report 05000443/2005001) ML0424402002004-08-30030 August 2004 Seabrook ROP5 Mid-Cycle Performance Review and Inspection Plan ML0406301482004-03-0303 March 2004 Annual Assessment Letter - Seabrook IR 05000443/20030012003-03-0303 March 2003 2003 Annual Assessment Letter - Seabrook Station (Report No. 50-443/03-001) IR 05000443/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Seabrook Station (Report No. 50-443/02-001) 2023-08-31
[Table view] Category:Letter
MONTHYEARML24009A1152024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24022A0652024-01-22022 January 2024 Senior Reactor and Reactor Operator Initial License Examinations L-2024-003, NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report2024-01-11011 January 2024 NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report ML23312A1822023-12-22022 December 2023 Issuance of Amendment No. 172 Revision to Cooling Tower Service Water Loop or Cell Requirements L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-180, Submittal of Changes to the Technical Specification Bases2023-12-13013 December 2023 Submittal of Changes to the Technical Specification Bases L-2023-177, Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-160, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule ML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20234032023-11-0707 November 2023 Security Baseline Inspection Report 05000443/2023403 and Independent Spent Fuel Storage Installation 07200063/2023401 IR 05000443/20230032023-11-0606 November 2023 Integrated Inspection Report 05000443/2023003 IR 05000443/20230102023-10-19019 October 2023 Triennial Fire Protection Inspection Report 05000443/2023010 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A0522023-10-0202 October 2023 Requalification Program Inspection IR 05000443/20234012023-09-0808 September 2023 Cybersecurity Inspection Report 05000443/2023401 (Cover Letter Only) IR 05000443/20234202023-09-0505 September 2023 Security Baseline Inspection Report 05000443/2023420 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update IR 05000443/20233022023-08-16016 August 2023 Operator Licensing Retake Examination Report 05000443/2023302 IR 05000443/20230022023-08-0808 August 2023 Integrated Inspection Report 05000443/2023002 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-104, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations L-2023-103, Inservice Inspection Examination Report2023-08-0303 August 2023 Inservice Inspection Examination Report ML23192A0782023-07-11011 July 2023 Operator Licensing Retake Examination Approval L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) SBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 ML23157A0722023-06-0606 June 2023 Notification of Conduct of a Fire Protection Team Inspection L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000443/20233012023-05-15015 May 2023 Initial Operator Licensing Examination Report 05000443/2023301 L-2023-064, License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-05-11011 May 2023 License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves IR 05000443/20230012023-05-11011 May 2023 Integrated Inspection Report 05000443/2023001 ML23129A0312023-05-0909 May 2023 Reactor Operator Retake License Examination ML23117A3652023-05-0404 May 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Remove Period of Applicability from PTL and Low Temperature Over Pressure Protection Curves SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report L-2023-053, Core Operating Limits Report for Cycle 232023-04-0505 April 2023 Core Operating Limits Report for Cycle 23 ML23088A1522023-03-29029 March 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Seabrook 4Q2022 Inspection Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications ML23073A1562023-03-23023 March 2023 Relief Request 4RA-22-01, Relief from the Requirements of the ASME Code L-2023-012, License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-03-15015 March 2023 License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves L-2023-025, Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-12023-03-15015 March 2023 Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-1 L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2023-023, Revised Steam Generator Tube Inspection Report2023-03-0303 March 2023 Revised Steam Generator Tube Inspection Report ML23020A1002023-03-0303 March 2023 OEDO-22-00419 - 2.206 Petition for Seabrook Station Structure Concrete Concerns (EPID L-2022-CRS-0000)- Closure Letter 2024-01-29
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION ber 2, 2014
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR SEABROOK STATION, UNIT NO. 1 (REPORT 05000443/2014006)
Dear Mr. Curtland:
On August 14, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Seabrook Station, Unit No. 1 (Seabrook). The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from July 1, 2013 through June 30, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Seabrook was operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Seabrook during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all performance indicators demonstrated that your performance was within the nominal, expected range (i.e, green). Therefore, the NRC plans to conduct Reactor Oversight Process baseline inspections at your facility.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310.
Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. As part of our baseline inspection program, we will maintain a focused oversight of NextEras actions to address the Alkali Silica Reaction (ASR) non-conforming condition impacting safety-related reinforced concrete structures at Seabrook. This will be accomplished through scheduled six-month inspection activities using Inspection Procedure (IP) 71152, Problem Identification and Resolution Inspection, annual sampling guidance. In addition to baseline inspections, the NRC will perform IP 60855.1, Operation of an Independent Spent Fuel Storage Installation at Operating Plants. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff.
A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's Agencywide Document Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610) 337-5233 with any questions you have regarding this letter.
Sincerely,
/RA/
Glenn T. Dentel, Chief Projects Branch 3 Division of Reactor Projects Docket No.: 50-443 License No.: NPF-86 Enclosure: Inspection Plan cc w/encl: Distribution via ListServ
ML14239A182 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME PCataldo/per email MSD MDraxton/ MSD GDentel/ GTD DATE 08/25/14 08/25/14 08/27/14 Distribution w/encl: (via e-mail)
W. Dean, RA D. Lew, DRA H. Nieh, DRP M. Scott, DRP J. Trapp, DRS B. Welling, DRS G. Dentel, DRP R. Barkley, DRP M. Draxton, DRP B. Reyes, DRP P. Cataldo, DRP, SRI C. Newport, DRP, RI A. Cass, DRP, Resident AA A. Bowers, RI, OEDO R. J. Powell, DRP DRS Branch Chiefs (6)
N. McNamara, RI, SLO D. Tifft, RI, SLO D. Screnci, RI, PAO N. Sheehan, RI, PAO RidsNrrDirslpab Resource ROPassessment Resource RidsNrrPMSeabrook Resource RidsNrrDorlLpl1-2 Resource ROPreports Resource
Page 1 of 2 Seabrook 08/25/2014 08:58:13 Inspection / Activity Plan Report 22 07/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site TRI FI - TRIENNIAL FIRE PROTECTION 4 1 07/07/2014 07/11/2014 IP 7111105T Fire Protection [Triennial]
71152B - PI&R BIENNIAL 2 1 10/06/2014 10/10/2014 IP 71152B Problem Identification and Resolution 1 10/20/2014 10/24/2014 IP 71152B Problem Identification and Resolution 71124.08 - RADWASTE 1 1 08/18/2014 08/22/2014 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation ASR - PI&R SAMPLE - ASR MONITORING 2 1 10/20/2014 10/24/2014 IP 71152 Problem Identification and Resolution EP EXER - EP EXERCISE INSPECTION 2 1 11/03/2014 11/07/2014 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event 3-23EXM - INITIAL OL EXAM 3 1 02/17/2015 03/20/2015 U01915 FY15-SEABROOK INITIAL OPERATOR LICENSING EXAM 1 03/23/2015 04/04/2015 U01915 FY15-SEABROOK INITIAL OPERATOR LICENSING EXAM 71151 - 71151 PI VERIFY IP 71124.01, 02 & 05 1 1 12/08/2014 12/12/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 12/08/2014 12/12/2014 IP 71124.02 Occupational ALARA Planning and Controls 1 12/08/2014 12/12/2014 IP 71124.05 Radiation Monitoring Instrumentation 1 12/08/2014 12/12/2014 IP 71151-OR01 1 12/08/2014 12/12/2014 IP 71151-PR01 ISFSI - ISFSI OPERATIONAL INSPECTION 1 1 03/01/2015 04/30/2015 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants ASR - PI&R SAMPLE - ASR MONITORING 2 1 03/02/2015 03/06/2015 IP 71152 Problem Identification and Resolution MODS - PERMANENT PLANT MODIFICATIONS 3 1 03/02/2015 03/06/2015 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1 03/16/2015 03/20/2015 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 71124 - RAD EFFLUENT CONTROL RETS 1 1 04/20/2015 04/23/2015 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 7111107T - TRIENNIAL HEAT SINK 1 1 06/01/2015 06/05/2015 IP 7111107T Heat Sink Performance 71124 - REMP 1 1 07/06/2015 07/09/2015 IP 71124.07 Radiological Environmental Monitoring Program This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Seabrook 08/25/2014 08:58:13 Inspection / Activity Plan Report 22 07/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site ASR - PI&R SAMPLE - ASR MONITORING 2 1 09/14/2015 09/18/2015 IP 71152 Problem Identification and Resolution 7111108P - INSERVICE INSPECTION 1 1 10/05/2015 10/16/2015 IP 7111108P Inservice Inspection Activities - PWR 7111111B - REQUAL INSP W/ P/F RESULTS 2 1 12/07/2015 12/11/2015 IP 7111111B Licensed Operator Requalification Program 71124 - HP 71124.01 02 03 04 1 1 10/19/2015 10/23/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/19/2015 10/23/2015 IP 71124.02 Occupational ALARA Planning and Controls 1 10/19/2015 10/23/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 10/19/2015 10/23/2015 IP 71124.04 Occupational Dose Assessment EP - EP PROGRAM INSPECTION 1 1 11/02/2015 11/06/2015 IP 7111402 Alert and Notification System Testing 1 11/02/2015 11/06/2015 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 11/02/2015 11/06/2015 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 71151 - HP PI VERIFY RAD HAZARD ALARA 1 1 12/07/2015 12/10/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 12/07/2015 12/10/2015 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.