MONTHYEARML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) IR 05000443/20220062023-03-0101 March 2023 Annual Assessment Letter for Seabrook Station (Report 05000443/2022006) IR 05000443/20220052022-08-31031 August 2022 Updated Inspection Plan for Seabrook Station (Report 05000443/2022005) IR 05000443/20210062022-03-0202 March 2022 Annual Assessment Letter for Seabrook Station, Unit 1 (Report 05000443/2021006) ML21322A2612021-11-18018 November 2021 Request for Information for a Triennial Baseline Design Bases Assurance Inspection (Teams); Inspection Report 05000443/2022011 IR 05000443/20210052021-09-0101 September 2021 Updated Inspection Plan for the Seabrook Station (Report 05000443/2021005) IR 05000443/20200062021-03-0303 March 2021 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2020006) IR 05000443/20210132021-01-20020 January 2021 Information Request to Support Triennial Baseline Design-Basis Capabilities of Power-Operated Valves Inspection; Inspection Reportt 05000443/2021013 IR 05000443/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000443/2020005) IR 05000443/20190062020-03-0303 March 2020 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2019006) IR 05000443/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000443/2019005) ML19141A0552019-05-21021 May 2019 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000443/2019403 IR 05000443/20180062019-03-0404 March 2019 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2018006) IR 05000443/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000443/2018005) IR 05000443/20170062018-02-28028 February 2018 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Reports 05000443/2017006, 05000443/2017402, And05000443/2017501) IR 05000443/20170052017-08-28028 August 2017 Updated Inspection Plan for Seabrook Station, Unit No. 1 (Report 05000443/2017005) IR 05000443/20160062017-03-0101 March 2017 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2016006) IR 05000443/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Seabrook Nuclear Power Plant, Unit No. 1 (Report 05000443/2016005) IR 05000443/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Seabrook Station, Unit 1 (Report 05000443/2015006) IR 05000443/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2014001) IR 05000443/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000443/2014006 IR 05000443/20130012014-03-0404 March 2014 ROP-14 2013 Seabrook Station Unit 1 Annual Assessment Letter, Report 05000443/2013001, and Inspection Plan ML13246A1072013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000443/2013006 IR 05000443/20120012013-03-0404 March 2013 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2012001) IR 05000443/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Seabrook Station Unit 1 (Report 05000443/2012006) ML12174A0192012-06-0404 June 2012 Paper - Inspection Planned for Week of 9/26/11 with Modes, Chaudhary, Thomas, Sheikh, and Erickson, USNRC IR 05000443/20110012012-03-0505 March 2012 Annual Assessment Letter for Seabrook Station, Unit 1 (Report No. 05000443-11-001) ML1124113402011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Seabrook Station, Unit 1 IR 05000443/20100012011-03-0404 March 2011 Annual Assessment Letter for Seabrook Station, Unit 1, EOC-11 (Report 05000443-10-001) ML1024403952010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Seabrook Station, Unit 1 ML1006208582010-03-0303 March 2010 EOC Annual Assessment Letter and Report 22 ML0924403172009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Seabrook Station, Unit 1 IR 05000443/20090012009-03-0404 March 2009 Annual Assessment Letter - Seabrook Station Unit 1 (05000443/2009001) ML0824700702008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Seabrook, Unit 1 IR 05000443/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Seabrook Station 05000443-08-001) ML0734706872007-12-13013 December 2007 ROP 8 - Seabrook - Change to Inspection Plan, 12/13/07 ML0724309432007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan IR 05000443/20060012006-03-0202 March 2006 Annual Assessment Letter - Seabrook Nuclear Power Station (Report 05000443/2006001) ML0524207202005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Seabrook IR 05000443/20050012005-03-0202 March 2005 Annual Assessment Letter - Seabrook Nuclear Generating Station (Report 05000443/2005001) ML0424402002004-08-30030 August 2004 Seabrook ROP5 Mid-Cycle Performance Review and Inspection Plan ML0406301482004-03-0303 March 2004 Annual Assessment Letter - Seabrook IR 05000443/20030012003-03-0303 March 2003 2003 Annual Assessment Letter - Seabrook Station (Report No. 50-443/03-001) IR 05000443/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Seabrook Station (Report No. 50-443/02-001) 2023-08-31
[Table view] Category:Letter
MONTHYEARML24009A1152024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24022A0652024-01-22022 January 2024 Senior Reactor and Reactor Operator Initial License Examinations L-2024-003, NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report2024-01-11011 January 2024 NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report ML23312A1822023-12-22022 December 2023 Issuance of Amendment No. 172 Revision to Cooling Tower Service Water Loop or Cell Requirements L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-180, Submittal of Changes to the Technical Specification Bases2023-12-13013 December 2023 Submittal of Changes to the Technical Specification Bases L-2023-177, Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-160, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule ML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20234032023-11-0707 November 2023 Security Baseline Inspection Report 05000443/2023403 and Independent Spent Fuel Storage Installation 07200063/2023401 IR 05000443/20230032023-11-0606 November 2023 Integrated Inspection Report 05000443/2023003 IR 05000443/20230102023-10-19019 October 2023 Triennial Fire Protection Inspection Report 05000443/2023010 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A0522023-10-0202 October 2023 Requalification Program Inspection IR 05000443/20234012023-09-0808 September 2023 Cybersecurity Inspection Report 05000443/2023401 (Cover Letter Only) IR 05000443/20234202023-09-0505 September 2023 Security Baseline Inspection Report 05000443/2023420 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update IR 05000443/20233022023-08-16016 August 2023 Operator Licensing Retake Examination Report 05000443/2023302 IR 05000443/20230022023-08-0808 August 2023 Integrated Inspection Report 05000443/2023002 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-104, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations L-2023-103, Inservice Inspection Examination Report2023-08-0303 August 2023 Inservice Inspection Examination Report ML23192A0782023-07-11011 July 2023 Operator Licensing Retake Examination Approval L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) SBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 ML23157A0722023-06-0606 June 2023 Notification of Conduct of a Fire Protection Team Inspection L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000443/20233012023-05-15015 May 2023 Initial Operator Licensing Examination Report 05000443/2023301 L-2023-064, License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-05-11011 May 2023 License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves IR 05000443/20230012023-05-11011 May 2023 Integrated Inspection Report 05000443/2023001 ML23129A0312023-05-0909 May 2023 Reactor Operator Retake License Examination ML23117A3652023-05-0404 May 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Remove Period of Applicability from PTL and Low Temperature Over Pressure Protection Curves SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report L-2023-053, Core Operating Limits Report for Cycle 232023-04-0505 April 2023 Core Operating Limits Report for Cycle 23 ML23088A1522023-03-29029 March 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Seabrook 4Q2022 Inspection Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications ML23073A1562023-03-23023 March 2023 Relief Request 4RA-22-01, Relief from the Requirements of the ASME Code L-2023-012, License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-03-15015 March 2023 License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves L-2023-025, Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-12023-03-15015 March 2023 Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-1 L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2023-023, Revised Steam Generator Tube Inspection Report2023-03-0303 March 2023 Revised Steam Generator Tube Inspection Report ML23020A1002023-03-0303 March 2023 OEDO-22-00419 - 2.206 Petition for Seabrook Station Structure Concrete Concerns (EPID L-2022-CRS-0000)- Closure Letter 2024-01-29
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 September 1~ 2010 Mr. Paul Freeman Site Vice President Seabrook Nuclear Power Plant NextEra Energy Seabrook, LLC.
c/o Mr. Michael O'Keefe P.O. Box 300 Seabrook, NH 03874
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN SEABROOK STATION, UNIT NO.1
Dear Mr. Freeman:
On August 10, 2010, the NRC staff completed its performance review of Seabrook Station, Unit No.1 (Seabrook). Our technical staff reviewed performance indicators (Pis) for the most recent quarter and inspection results for the period from July 1, 2009, through June 3D, 2010. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter at Seabrook was within the Regulatory Response column of the NRC's Action Matrix, based on one White inspection finding with low to moderate safety significance, all other inspection findings being classified as having very low safety significance (Green), and all Pis indicating performance at a level requiring no additional NRC oversight (Green). The White finding, for which the final significance determination was documented in a letter dated November 12,2009, (ML093160351)1, involved the failure to establish adequate design control measures to modify a cooling water flange on the B emergency diesel generator (EDG), which led to the failure of the diesel during a test on February 25,2009.
You performed an evaluation and implemented corrective actions to address the issues associated with this White finding. On June 7, the NRC initiated a supplemental inspection, in accordance with Inspection Procedure 95001, "Inspection for One or Two White Inputs in a Strategic Performance Area." to review your actions to address the White finding. During this inspection, we communicated to you several significant weaknesses in your evaluation, extent of condition and cause, and corrective actions. You initiated prompt actions to correct these weaknesses, and informed us of those actions on June 22. We subsequently independently assessed the adequacy of those additional corrective actions, completing our inspection on June 30, as documented in NRC Inspection Report 05000443/20100007 (ML102250493)'.
Based on results of IP 95001 inspection, this finding is now closed and will no longer be considered for plant assessment purposes effective July 1! 2010. We communicated the results I Designation in parenthesis refers to an ADAMS accession number. Documents referenced in this letter are publicly available using the accession number in ADAMS.
P. Freeman 2 I of our 95001 inspection to you during a Regulatory Performance meeting that was conducted on \'
June 30,2010, and as of July 1, 2010, Seabrook returned to the Licensee Response column of the NRC's; Action Matrix. Therefore, we plan to conduct reactor oversight (ROP) baseline inspections at your facility for the remainder of 2010.
I The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31! 2011. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of I
inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
As you may know, an Operational Safety Review Team (OSART), performed by senior staff members from the International Atomic Energy Agency (IAEA), will be conducted at Seabrook in June 2011. The scope of the OSART evaluation may encompass portions of the ROP baseline inspection program. NRC Inspection Manual Chapter 2515, Section 08.05, "Baseline Inspection Credit for Operational Safety Review Team Effort" allows a reduction in baseline inspection in those areas that are determined to overlap with the OSART review. If the results of this evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Arthur Burritt at 610-337-5069 with any questions you may have regarding this letter or the inspection plan.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html (the Public Electronic Reading Room).
Sincerely, JaF, tL-f{)AIj/
cli~tcting Director DiVision of Reactor Projects Docket Nos. 50-443 License Nos. NPF-86
Enclosure:
Seabrook Station Inspection/Activity Plan cc w/encr: Distribution via ListServ
P. Freeman 2 the results of our 95001 inspection to you during a Regulatory Performance meeting that was conducted on June 30,2010, and as of July 1, 2010, Seabrook returned to the Licensee Response column of the NRC's Action Matrix. Therefore, we plan to conduct reactor oversight (ROP) baseline inspections at your facility for the remainder of 2010.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2011. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
As you may know, an Operational Safety Review Team (OSART), performed by senior staff members from the International Atomic Energy Agency (IAEA), will be conducted at Seabrook in June 2011. The scope of the OSART evaluation may encompass portions of the ROP baseline inspection program. NRC Inspection Manual Chapter 2515, Section 08.05, "Baseline Inspection Credit for Operational Safety Review Team Effort" allows a reduction in baseline inspection in those areas that are determined to overlap with the OSART review. If the results of this evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Arthur Burritt at 610-337-5069 with any questions you mc:lY have regarding this letter or the inspection plan.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).
Sincerely, IRA!
James W. Clifford, Acting Director Division of Reactor Projects Docket Nos. 50-443 License Nos. NPF-86
Enclosure:
Seabrook Station Inspection/Activity Plan cc w/encl: Distribution via ListServ Distribution: See attached page ML102440395 SUNSI REVIEW COMPLETED: LC (Reviewer's Initials)
DOCUMENT NAME: S:\ROP-11 MID-CYCLE REVIEw\BRANCH 3\SEABROOK MID-CYCLE LEnER2010 REV2.DOCX After declaring this document "An Official Agency Record" it will be released to the Public.
To receive acopy ofthis document, indicate in box:'C" = Copy w/o attachment/enclosure, En '" Copy wI attachmentlenclosure"N'=No copy OFFICE mmt RI/DRP J RI/DRP I RI/DRP RI/DRP I NAME WRaymondl LC for LClineJ LC ABurrittl ALB JCliffordl JWC
~TE PSI 25 110 108/31110 08131110 09/01/10 OFFICIAL RECORD COPY
Page 1 of2 Seabrook 08/30/2010 14:40:32 Inspection I Activity Plan Report 22 07/01/2010
- 1213112011 Planned Dates Start End h L.----------------------------------------------.-~:7*---'*-*-----------------------------------------,
11129 EX - INITIAL OPERATOR LICENSING EXAM 5 10/25/2010 1012912010 U01694 FY11 - SEABROOK INITIAL OPERATOR EXAM 11129/2010 12110/2010 U01694 FY11 - SEABROOK INITIAL OPERATOR EXAM 71152B - PI&R 4 09/13/2010 09/17/2010 IP 711526 Identification and Resolution of Problems 09/27/2010 10/01/2010 IP 711526 Identification and Resolution of Problems 71124 -OCC RAD SAFETY 1 08/1612010 08120/2010 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 0811612010 08120/2010 IP 71124.02 Occupational ALARA Planning and Controls 0811612010 08120/2010 IP 71124.04 Occupational Dose Assessment 71124 - PUB RAD SAFETY* RADWASTE 1 1 09/20/2010 09/2412010 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Ma~erial Handling. Storage. and Transportation 0912012010 0912412010 IP 71151 Performance Indicator Verification 71124 - OCC RAD SAFETY - INSTRUMENTS 1 11/01/2010 11/0512010 IP 71124.05 Radiation Monitoring Instrumentation TI179 - TI179 NSTS VERIFICATION 1 11/08/2010 11/12/2010 I P 2515/179 Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 71124 - oce RAD SAFETY - ALARA & ISFSI 1 1210612010 12(10/2010 IP 60855 Operation Of An ISFSI 12/06/2010 12/10/2010 IP 71124.04 Occupational Dose Assessment 1210612010 1211 Oi201 0 IP 71151 Performance Indicator Verification 71124 - oce RAD SAFETY 1 01/24/2011 01/28/2011 IP 71124.01 Radiological Hazard ASSessment and Exposure Controls 1 01124/2011 01/2812011 Ip 71124.02 Occupational AlARA Planning and Controls EP PROGR - EP PROGRAM INSPECTION 1 1 02/28/2011 03/0412011 IP 71114()2 Alert and Notification System Testing 1 02128/2011 03/0412011 IP 71114()3 Emergency Preparedness Organization Staffing and Augmentation System 02128/2011 03/0412011 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 02/2812011 03104/2011 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 0212812011 0310412011 IP 71151-EP01 Drill/Exercise Performance 02/2812011 03/0412011 lP 71151-EP02 ERO Drill Participation 02/28/2011 03/04/2011 IP 71151-EP03 Alert & Notification System 7111108P .INSERVICE INSPECTION 1 04/04/2011 0411512011 IP 7111108P Inservice Inspection Activities* PWR is report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 20f2 Seabrook 08130/2010 14:40:32 Inspection I Activity Plan Report 22 07/01/2010
- 12/3112011 Planned Dates Start End f!iSD8ction Activit Title 71124
- OCC RAn SAFETY 1 1 0412512011 04/2912011 IP 71124.Q1 Radiological Hazard Assessment and Exposura Controls 1 04/2512011 04/29/2011 IP 71124.02 Occupational ALARA Planning and Controls 04125/2011 04/2912011 IP 71124.04 Occupational Dose Assessment 7112402 *AlARA 04/2512011 04/2912011 IP 71124.02 Occupational ALARA Planning and Controls TRIFIRE
- TRIENNIAL FIRE PROTECTION INSPECTION 4 07/25/2011 07129/2011 IP 7111105T Fire Protection [Triennial]
08/08/2011 08/1212011 IP 7111105T Fire Protection [Triennial]
71124 *REMP 1 09112/2011 09/1612011 lP 71124.07 Radiological Environmental Monitoring Program 7111118
- SEABROOK REQUAL INSP WI P/F RESULTS 3 1210512011 12109/2011 IP 71111116 Licensed Operator Requalification Program 71124
- EFFLUENTS 1 11/28/2011 1210212011 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment trhlSreporfdoes not include INPO and OLlTAGE activities.
jThiS report shows only on-site and announced inspection procedures.