Updated Inspection Plan for the Seabrook Station (Report 05000443/2021005)
ML21242A027
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 09/01/2021
From: Brice Bickett
Division of Operating Reactors
To: Coffey R
Florida Power & Light Co
References
IR 2021005
Download: ML21242A027 (5)


Text

September 1, 2021

SUBJECT:

UPDATED INSPECTION PLAN FOR THE SEABROOK STATION (REPORT 05000443/2021005)

Dear Mr. Coffey,

The enclosed inspection plan lists the inspections scheduled through June 30, 2023, for Seabrook Station (Seabrook). The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:

https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling. The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections is being developed by the NRC staff. The staff expects to communicate the schedule for these inspections to each utility separately.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR)2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 610-337-5312 with any questions you have regarding this letter.

Sincerely, Brice A. Bickett, Chief Projects Branch 3 Division of Operating Reactor Safety Docket No.

50-443 License No. NPF-86 Enclosure:

Seabrook Inspection Plan Distribution via ListServ Brice A.

Bickett Digitally signed by Brice A. Bickett Date: 2021.09.01 05:27:22 -04'00'

ML21242A027

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE RI/DORS RI/DORS NAME PFinney BBickett/BB DATE 08/30/21 09/01/21

Seabrook 07/01/2021 - 06/30/2023 Unit Start End Activity CAC Title Staff Count Seabrook Requal Inspection with P/F Results

1 7/5/2021 12/31/2021 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance

7/5/2021 7/30/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance MATERIAL CONTROL AND ACCOUNTABILITY

1 7/18/2021 7/24/2021 IP 71130.11 000742 Material Control and Accounting (MC&A)

HEAT SINK INSPECTION

1 8/8/2021 8/14/2021 IP 71111.07T 000700 Heat Sink Performance EP EXERCISE INSPECTION - SEABROOK

1 8/9/2021 8/13/2021 IP 71114.01 000716 Exercise Evaluation

8/9/2021 8/13/2021 IP 71151 001397 Performance Indicator Verification RP ALARA / PI's (71124.02 / 71151) REMOTE - SB

1 8/23/2021 8/27/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls

8/23/2021 8/27/2021 IP 71151 000746 Performance Indicator Verification RP Rad Hazard Assess & Control / Radwaste & Transportation / PIs (71124.01/.08/71151) - SB

1 10/4/2021 10/8/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

10/4/2021 10/8/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation

10/4/2021 10/8/2021 IP 71151 000746 Performance Indicator Verification INSERVICE INSPECTION

1 10/10/2021 10/23/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Design Basis Assurance Inspection - Teams - Seabrook

1 1/23/2022 1/29/2022 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

RP Rad Hazard Assessment 71124.01 - SB

1 2/28/2022 3/4/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls EP EXERCISE INSPECTION - SEABROOK

1 4/4/2022 4/8/2022 IP 71114.01 000716 Exercise Evaluation

4/4/2022 4/8/2022 IP 71151 001397 Performance Indicator Verification RP Rad Instrumentation 71124.05 - SB

1 6/13/2022 6/17/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation Access Control, Protective Strat, TSR, SPR, PI-SB

1 6/13/2022 6/17/2022 IP 71130.02 000734 Access Control

6/13/2022 6/17/2022 IP 71130.05 000737 Protective Strategy Evaluation Prepared on 8/16/2021 11:13:08 AM 1 of 2 IP 22b Site Inspection Activity Plan

6/13/2022 6/17/2022 IP 71130.09 001656 Security Plan Changes

6/13/2022 6/17/2022 IP 71130.14 000743 Review of Power Reactor Target Sets

6/13/2022 6/17/2022 IP 71151 001338 Performance Indicator Verification ISFSI Operational Inspection (60855) - SB

1 8/15/2022 8/19/2022 IP 60855 001001 Operation Of An ISFSI RP Rad Environmental Monitoring Program 71124.07 - SB

1 8/22/2022 8/26/2022 IP 71124.07 000731 Radiological Environmental Monitoring Program RP Rad Gas and Liq Effluent Treatment / PIs (71124.06/71151)

1 10/31/2022 11/4/2022 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment

10/31/2022 11/4/2022 IP 71151 000746 Performance Indicator Verification PI&R BIENNIAL TEAM INSPECTION - SB

1 10/31/2022 11/4/2022 IP 71152B 000747 Problem Identification and Resolution

11/14/2022 11/18/2022 IP 71152B 000747 Problem Identification and Resolution AA, FFD-SB

1 2/6/2023 2/10/2023 IP 71130.01 000733 Access Authorization

2/6/2023 2/10/2023 IP 71130.08 000740 Fitness For Duty Program FY23 Seabrook Initial License Exam

1 2/5/2023 2/17/2023 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

3/6/2023 3/17/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

Inservice Inspection - Seabrook

1 4/10/2023 4/21/2023 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Rad Hazards (71124.01)

1 4/10/2023 4/14/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls FORCE-ON-FORCE PLANNING AND EXERCISE - SB

1 6/12/2023 6/16/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Prepared on 8/16/2021 11:13:08 AM 2 of 2 IP 22b Site Inspection Activity Plan