MONTHYEARIR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) IR 05000443/20220062023-03-0101 March 2023 Annual Assessment Letter for Seabrook Station (Report 05000443/2022006) IR 05000443/20220052022-08-31031 August 2022 Updated Inspection Plan for Seabrook Station (Report 05000443/2022005) IR 05000443/20210062022-03-0202 March 2022 Annual Assessment Letter for Seabrook Station, Unit 1 (Report 05000443/2021006) ML21322A2612021-11-18018 November 2021 Request for Information for a Triennial Baseline Design Bases Assurance Inspection (Teams); Inspection Report 05000443/2022011 IR 05000443/20210052021-09-0101 September 2021 Updated Inspection Plan for the Seabrook Station (Report 05000443/2021005) IR 05000443/20200062021-03-0303 March 2021 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2020006) IR 05000443/20210132021-01-20020 January 2021 Information Request to Support Triennial Baseline Design-Basis Capabilities of Power-Operated Valves Inspection; Inspection Reportt 05000443/2021013 IR 05000443/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000443/2020005) IR 05000443/20190062020-03-0303 March 2020 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2019006) IR 05000443/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000443/2019005) ML19141A0552019-05-21021 May 2019 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000443/2019403 IR 05000443/20180062019-03-0404 March 2019 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2018006) IR 05000443/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000443/2018005) IR 05000443/20170062018-02-28028 February 2018 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Reports 05000443/2017006, 05000443/2017402, And05000443/2017501) IR 05000443/20170052017-08-28028 August 2017 Updated Inspection Plan for Seabrook Station, Unit No. 1 (Report 05000443/2017005) IR 05000443/20160062017-03-0101 March 2017 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2016006) IR 05000443/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Seabrook Nuclear Power Plant, Unit No. 1 (Report 05000443/2016005) IR 05000443/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Seabrook Station, Unit 1 (Report 05000443/2015006) IR 05000443/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2014001) IR 05000443/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000443/2014006 IR 05000443/20130012014-03-0404 March 2014 ROP-14 2013 Seabrook Station Unit 1 Annual Assessment Letter, Report 05000443/2013001, and Inspection Plan ML13246A1072013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000443/2013006 IR 05000443/20120012013-03-0404 March 2013 Annual Assessment Letter for Seabrook Station, Unit No. 1 (Report 05000443/2012001) IR 05000443/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Seabrook Station Unit 1 (Report 05000443/2012006) ML12174A0192012-06-0404 June 2012 Paper - Inspection Planned for Week of 9/26/11 with Modes, Chaudhary, Thomas, Sheikh, and Erickson, USNRC IR 05000443/20110012012-03-0505 March 2012 Annual Assessment Letter for Seabrook Station, Unit 1 (Report No. 05000443-11-001) ML1124113402011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Seabrook Station, Unit 1 IR 05000443/20100012011-03-0404 March 2011 Annual Assessment Letter for Seabrook Station, Unit 1, EOC-11 (Report 05000443-10-001) ML1024403952010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Seabrook Station, Unit 1 ML1006208582010-03-0303 March 2010 EOC Annual Assessment Letter and Report 22 ML0924403172009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Seabrook Station, Unit 1 IR 05000443/20090012009-03-0404 March 2009 Annual Assessment Letter - Seabrook Station Unit 1 (05000443/2009001) ML0824700702008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Seabrook, Unit 1 IR 05000443/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Seabrook Station 05000443-08-001) ML0734706872007-12-13013 December 2007 ROP 8 - Seabrook - Change to Inspection Plan, 12/13/07 ML0724309432007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan IR 05000443/20060012006-03-0202 March 2006 Annual Assessment Letter - Seabrook Nuclear Power Station (Report 05000443/2006001) ML0524207202005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Seabrook IR 05000443/20050012005-03-0202 March 2005 Annual Assessment Letter - Seabrook Nuclear Generating Station (Report 05000443/2005001) ML0424402002004-08-30030 August 2004 Seabrook ROP5 Mid-Cycle Performance Review and Inspection Plan ML0406301482004-03-0303 March 2004 Annual Assessment Letter - Seabrook IR 05000443/20030012003-03-0303 March 2003 2003 Annual Assessment Letter - Seabrook Station (Report No. 50-443/03-001) IR 05000443/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Seabrook Station (Report No. 50-443/02-001) 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000443/20240032024-10-30030 October 2024 Integrated Inspection Report 05000443/2024003 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24303A0352024-10-29029 October 2024 Operator Licensing Examination Approval IR 05000443/20244022024-10-17017 October 2024 Material Control and Accounting Program Inspection Report 05000443/2024402 (Cover Letter Only) L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-159, Core Operating Limits Report for Reload Cycle 242024-10-15015 October 2024 Core Operating Limits Report for Reload Cycle 24 ML24254A2552024-09-25025 September 2024 Alternative Request No. 4A-01 for the Fourth 10-Year Inservice Inspection Interval L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24239A5382024-09-20020 September 2024 Issuance of Amendment No. 175 One-Time Allowable Outage Time Extension to the Technical Specification 3.8.1.1, A.C. Sources – Operating, Limiting Condition for Operation L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML24232A1142024-08-21021 August 2024 Correction to Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves L-2024-141, Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit2024-08-15015 August 2024 Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Be L-2024-137, Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent .2024-08-12012 August 2024 Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent . IR 05000443/20240022024-08-0606 August 2024 Integrated Inspection Report 05000443/2024002 and Independent Spent Fuel Storage Installation Inspection Report 07200063/2024001 L-2024-127, Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent2024-08-0505 August 2024 Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite.2024-07-16016 July 2024 Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite. ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-098, Preparation and Scheduling of Operator Licensing Examinations2024-06-12012 June 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-084, Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-05-30030 May 2024 Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20240102024-05-29029 May 2024 Biennial Problem Identification and Resolution Inspection Report 05000443/2024010 IR 05000443/20240112024-05-24024 May 2024 Age-Related Degradation Inspection Report 05000443/2024011 IR 05000443/20240012024-05-13013 May 2024 Integrated Inspection Report 05000443/2024001 L-2024-061, NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distribut2024-05-10010 May 2024 NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distributio ML24046A0512024-05-0707 May 2024 Issuance of Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-078, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report L-2024-077, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000443/20245012024-04-22022 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000443/2024501 05000443/LER-2024-001, Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources2024-04-19019 April 2024 Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources SBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-038, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0808 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24067A2622024-03-0808 March 2024 Issuance of Amendment No. 173 Revise Technical Specification 3/4.8.1 to Allow Replacement of Reserve Auxiliary Transformer (Emergency Circumstances) L-2024-037, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0606 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24065A2522024-03-0505 March 2024 Notice of Enforcement Discretion for Seabrook Station, Unit No. 1 (EPID: L-2024-033) L-2024-035, Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0505 March 2024 Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-033, Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B2024-03-0404 March 2024 Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B L-2024-032, Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0404 March 2024 Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-019, Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-02-28028 February 2024 Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20230062024-02-28028 February 2024 Annual Assessment Letter for Seabrook Station (Report 05000443/2023006) L-2024-016, Radiological Emergency Plan (Ssrep), Revision 822024-02-13013 February 2024 Radiological Emergency Plan (Ssrep), Revision 82 IR 05000443/20230042024-02-12012 February 2024 Integrated Inspection Report 05000443/2023004 ML24009A1152024-01-29029 January 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) 2024-09-25
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COM M ISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 August 31, 2007 Mr. Gene St. Pierre Site Vice President FPL Energy Seabrook, LLC Seabrook Station c/o Mr. James M. Peschel P.O. Box 300 Seabrook, NH 03874
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
SEABROOK STATION
Dear Mr. St. Pierre,
On August 14, 2007, the NRC staff completed its performance review of Seabrook Station for the first half of the calendar year 2007 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as Official Use Only--Security Information will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter of 2007 at Seabrook was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan to conduct inspections to review modifications of the containment sump and alloy 82/182 pressurizer butt welds.
While plant performance for the most recent quarter was within the Licensee Response column of the Action Matrix, Seabrook was within the Regulatory Response column in the third quarter of 2006 due to one White (low to moderate safety significance) PI. Specifically, the Emergency AC Power System PI crossed the Green/White threshold in late August 2006 when both emergency diesel generators (EDGs) became inoperable due to voltage regulator problems.
Following repairs of both EDGs in early September 2006, your staff performed a root cause evaluation of the failures that was completed in December 2006. The NRC performed a 95001 supplemental inspection in May 2007. Based on the results of this inspection, we concluded that you have adequately evaluated the causes of the EDG failures and the associated performance deficiencies and implemented appropriate corrective actions. Given your acceptable performance in addressing the causes of the EDG failures, and the PI returning to Green status in the fourth quarter of 2006, the issue will no longer be used in assessing Seabrook Station performance.
G. St. Pierre 2 The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.
Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5069 with any questions you may have regarding this letter or the inspection plan.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Arthur Burritt, Chief Projects Branch 3 Division of Reactor Projects Docket No. 50-443 License No. NPF-86
Enclosure:
Seabrook Station Inspection/ Activity Plan cc w/encl:
see next page
G. St. Pierre 3 cc w/encl:
J. A. Stall, FPL Senior Vice President, Nuclear & CNO M. Warner, Vice President, Nuclear Operations R. S. Kundalkar, FPL Vice President, Nuclear Technical Svcs M. Mashhadi, Senior Attorney, Florida Power & Light Company M. S. Ross, Managing Attorney, Florida Power & Light Company J. M. Peschel, Manager, Regulatory Programs M. Kiley, Plant General Manager J. Dent, Assist Plant Manager K. Wright, Manager, Nuclear Training, Seabrook Station R. Poole, FEMA, Region I Office of the Attorney General, Commonwealth of Mass K. Ayotte, Attorney General, State of NH O. Fitch, Deputy Attorney General, State of NH P. Brann, Assistant Attorney General, State of Maine R. Walker, Director, Radiation Control Program, Dept. of Public Health, Commonwealth of MA C. Pope, Director, Homeland Security & Emergency Management, State of NH J. Giarrusso, MEMA, Commonwealth of Mass D. O'Dowd, Administrator, Radiological Health Section, DPHS, DHHS, State of NH J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company T. Crimmins, Polestar Applied Technology R. Backus, Esquire, Backus, Meyer and Solomon, NH Town of Exeter, State of New Hampshire Board of Selectmen, Town of Amesbury S. Comley, Executive Director, We the People of the United States R. Shadis, New England Coalition Staff M. Metcalf, Seacoast Anti-Pollution League Institute of Nuclear Power Operations (INPO)
G. St. Pierre 2 The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.
Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5069 with any questions you may have regarding this letter or the inspection plan.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Arthur Burritt, Chief Projects Branch 3 Division of Reactor Projects Docket No. 50-443 License No. NPF-86
Enclosure:
Seabrook Station Inspection/ Activity Plan cc w/encl:
see next page Distribution w/encl: (VIA E-MAIL)
S. Collins, RA H. Chernoff, NRR M. Dapas, DRA J. Lubinski, NRR D. Lew, DRP E. Miller, NRR, PM J. Clifford, DRP R. Ennis, NRR, Backup A. Burritt, DRP T. Valentine, NRR C. Khan, DRP ROPreports@nrc.gov (All Irs)
L. Cline, DRP RidsNrrdirslpab@nrc.gov W. Raymond, DRP - Sr Resident Inspector JWT1@nrc.gov J. Bream, Acting RI Region I Docket Room (with concurrences)
R. Laufer, RI OEDO SUNSI REVIEW COMPLETE:__ALB____(Reviewers Initials)
After declaring this document An Official Agency Record it will be released to the Public.
DOCUMENT NAME: S:\ROP 8 Mid Cycle Review\Letters for Mid Cycle\Branch 3 Mid-cycle letters\SB 2007 Mid-cycle letter.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP NAME SMcCarver/sm LCline/lc ABurritt/ALB DATE 08/24 /07 08/ 27 /07 08/ 27 /07 OFFICIAL RECORD COPY
Page 1 of 2 Seabrook 08/27/2007 13:54:20 Inspection / Activity Plan Report 22 07/01/2007 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7/09+EXM - INITIAL OPERATOR LICENSING EXAMS 4 1 U01666 FY07-SEABROOK INITIAL OPERATOR EXAM 07/09/2007 07/13/2007 Not Applicable 7111107 - HEAT SINK INSP 1 1 IP 7111107B Heat Sink Performance 07/30/2007 08/03/2007 Baseline Inspections 71114 - EP PRGM INSP 1 1 IP 7111402 Alert and Notification System Testing 08/27/2007 08/31/2007 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 08/27/2007 08/31/2007 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 08/27/2007 08/31/2007 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 08/27/2007 08/31/2007 Baseline Inspections 1 IP 71151-EP01 Drill/Exercise Performance 08/27/2007 08/31/2007 Baseline Inspections 1 IP 71151-EP02 ERO Drill Participation 08/27/2007 08/31/2007 Baseline Inspections 1 IP 71151-EP03 Alert & Notification System 08/27/2007 08/31/2007 Baseline Inspections 7112203 - PUB RAD SAFETY - REMP 1 1 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 09/03/2007 09/07/2007 Baseline Inspections 7112103 - OCC RAD SAFETY - INSTRUMENTS 1 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 09/04/2007 09/07/2007 Baseline Inspections 7111111B - L.O. REQUAL. PROG. + P/F REVIEW 3 1 IP 7111111B Licensed Operator Requalification Program 11/26/2007 11/30/2007 Baseline Inspections 1 IP 7111111B Licensed Operator Requalification Program 12/03/2007 12/07/2007 Baseline Inspections 7112102 - PUB RAD SAFETY - RETS 1 1 IP 7112102 ALARA Planning and Controls 12/03/2007 12/07/2007 Baseline Inspections 1 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 12/03/2007 12/07/2007 Baseline Inspections 7112101 - OCC RAD SAFETY - ACCESS 1 1 IP 7112101 Access Control to Radiologically Significant Areas 01/28/2008 02/01/2008 Baseline Inspections MODS - MODS AND 50.59 4 1 IP 7111102 Evaluation of Changes, Tests, or Experiments 02/04/2008 02/08/2008 Baseline Inspections 1 IP 7111117B Permanent Plant Modifications 02/04/2008 02/08/2008 Baseline Inspections 7112102 - OCC RAD SAFETY - ALARA 1 1 IP 7112102 ALARA Planning and Controls 04/14/2008 04/18/2008 Baseline Inspections 7111108P - INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/14/2008 04/18/2008 Baseline Inspections 1 IP 7111108P Inservice Inspection Activities - PWR 04/21/2008 04/25/2008 Baseline Inspections TI-166 - CONTAINMENT SUMP MODIFICATIONS 1 1 IP 2515/166 Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02] 04/21/2008 04/25/2008 Safety Issues This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Seabrook 08/27/2007 13:54:20 Inspection / Activity Plan Report 22 07/01/2007 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71111.12 - MAINTENANCE RULE 1 1 IP 7111112B Maintenance Effectiveness 06/16/2008 06/20/2008 Baseline Inspections TRI FIRE - TRIENNIAL FIRE PROTECTION INSPECTION 3 1 IP 7111105T Fire Protection [Triennial] 07/14/2008 07/18/2008 Baseline Inspections 1 IP 7111105T Fire Protection [Triennial] 07/28/2008 08/01/2008 Baseline Inspections 7112202 - PUB RAD SAFETY - RADWASTE 1 1 IP 7112202 Radioactive Material Processing and Transportation 09/29/2008 10/03/2008 Baseline Inspections 7112103 - OCC RAD SAFETY - INSTRUMENTS 1 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 11/03/2008 11/07/2008 Baseline Inspections EP - EP EXERCISE EVALUATION 4 1 IP 7111401 Exercise Evaluation 11/03/2008 11/07/2008 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 11/03/2008 11/07/2008 Baseline Inspections 1 IP 71151-EP01 Drill/Exercise Performance 11/03/2008 11/07/2008 Baseline Inspections 1 IP 71151-EP02 ERO Drill Participation 11/03/2008 11/07/2008 Baseline Inspections 1 IP 71151-EP03 Alert & Notification System 11/03/2008 11/07/2008 Baseline Inspections 71152B - PI&R 4 1 IP 71152B Identification and Resolution of Problems 11/17/2008 11/21/2008 Baseline Inspections 1 IP 71152B Identification and Resolution of Problems 12/08/2008 12/12/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.