UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 September 2, 2008 Mr. Gene St. Pierre Site Vice President FPL Energy Seabrook, LLC Seabrook Station c/o Mr. Michael OKeefe P. O. Box 300 Seabrook, NH 03874
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
SEABROOK STATION, UNIT NO. 1
Dear Mr. St. Pierre:
On August 6, 2008, the NRC staff completed its performance review for Seabrook Station, Unit No. 1 (Seabrook). Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2007, through June 30, 2008. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Information" will include the Security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter at Seabrook was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan to conduct independent spent fuel storage installation inspections.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
G. St. Pierre 2
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise that cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5069 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Arthur L. Burritt, Chief Division of Reactor Projects Projects Branch 3 Docket Nos. 50-443 License Nos. NFP-86
Enclosure:
Seabrook Station Inspection/ Activity Plan cc w/encl:
J. A. Stall, FPL Senior Vice President, Nuclear & CNO M. Warner, Vice President, Nuclear Operations R. S. Kundalkar, FPL Vice President, Nuclear Technical Svcs M. Mashhadi, Senior Attorney, Florida Power & Light Company M. S. Ross, Managing Attorney, Florida Power & Light Company M. OKeefe, Manager, Regulatory Programs P. Freeman, Plant General Manager K. Wright, Manager, Nuclear Training, Seabrook Station R. Poole, FEMA, Region I Office of the Attorney General, Commonwealth of Mass K. Ayotte, Attorney General, State of NH O. Fitch, Deputy Attorney General, State of NH P. Brann, Assistant Attorney General, State of Maine R. Walker, Director, Radiation Control Program, Dept. of Public Health, Commonwealth of MA C. Pope, Director, Homeland Security & Emergency Management, State of NH J. Giarrusso, MEMA, Commonwealth of Mass D. O'Dowd, Administrator, Radiological Health Section, DPHS, DHHS, State of NH J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company T. Crimmins, Polestar Applied Technology R. Backus, Esquire, Backus, Meyer and Solomon, NH Town of Exeter, State of New Hampshire Board of Selectmen, Town of Amesbury S. Comley, Executive Director, We the People of the United States R. Shadis, New England Coalition Staff M. Metcalf, Seacoast Anti-Pollution League
Seabrook Inspection / Activity Plan 08/01/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/28/2008 17:27:08 Report 22 1
- ISFSI INSPECTIONS Other Routine Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 01/28/2008 10/31/2008 1
60854.1 IP Other Routine Operation of an Independent Spent Fuel Storage Installation at Operating Plants 01/28/2008 10/31/2008 1
60855.1 IP 3
TRI FIRE
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections Fire Protection [Triennial]
07/28/2008 08/01/2008 1
7111105T IP 3
7111111
- REQUAL INSPECTION WITH P/F RESULTS Baseline Inspections Licensed Operator Requalification Program 12/01/2008 12/05/2008 1
7111111B IP 1
7112202
- PUB RAD SAFETY - RADWASTE Baseline Inspections Radioactive Material Processing and Transportation 09/29/2008 10/03/2008 1
7112202 IP 4
TI 171
- TI 171 Generic Safety Inspectio Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 10/20/2008 10/24/2008 1
2515/171 IP 6
- EP EXERCISE EVALUATION EP Baseline Inspection Exercise Evaluation 11/03/2008 11/07/2008 1
7111401 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 11/03/2008 11/07/2008 1
7111404 IP Baseline Inspections Drill/Exercise Performance 11/03/2008 11/07/2008 1
71151-EP01 IP Baseline Inspections ERO Drill Participation 11/03/2008 11/07/2008 1
71151-EP02 IP Baseline Inspections Alert & Notification System 11/03/2008 11/07/2008 1
71151-EP03 IP 1
TI 176
- TI 176 Generic Safety Inspectio Emergency Diesel Generator Tech Spec Surveillance Requirements Re: Endurance & Margin Testing 10/27/2008 10/31/2008 1
2515/176 IP 1
7112103
- OCC RAD SAFETY - INSTRUMENTS Baseline Inspections Radiation Monitoring Instrumentation and Protective Equipment 11/03/2008 11/07/2008 1
7112103 IP 4
- PI&R Baseline Inspections Identification and Resolution of Problems 11/17/2008 11/21/2008 1
71152B IP Baseline Inspections Identification and Resolution of Problems 12/01/2008 12/05/2008 1
71152B IP 1
71121
- OCC RAD SAFETY Baseline Inspections Access Control to Radiologically Significant Areas 01/26/2009 01/30/2009 1
7112101 IP Baseline Inspections ALARA Planning and Controls 01/26/2009 01/30/2009 1
7112102 IP 4
6/15EXAM
- OPERATOR LICENSING INITIAL EXAMS Not Applicable FY-09 SEABROOK INITIAL OPERATOR LICENSING EXAM 05/11/2009 05/15/2009 1
U01759 Not Applicable FY-09 SEABROOK INITIAL OPERATOR LICENSING EXAM 06/15/2009 06/26/2009 1
U01759 3
MODS
- PERMANENT PLANT MODIFICATIONS Baseline Inspections Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 03/09/2009 03/13/2009 1
7111117T IP Baseline Inspections Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 03/23/2009 03/27/2009 1
7111117T IP 2
EP PROGR
- EP PROGRAM INSPECTION EP Baseline Inspection Alert and Notification System Testing 08/02/2009 08/08/2009 1
7111402 IP This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Seabrook Inspection / Activity Plan 08/01/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/28/2008 17:27:08 Report 22 2
EP PROGR
- EP PROGRAM INSPECTION EP Baseline Inspection Emergency Response Organization Augmentation Testing 08/02/2009 08/08/2009 1
7111403 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 08/02/2009 08/08/2009 1
7111404 IP EP Baseline Inspection Correction of Emergency Preparedness Weaknesses and Deficiencies 08/02/2009 08/08/2009 1
7111405 IP Baseline Inspections Drill/Exercise Performance 08/02/2009 08/08/2009 1
71151-EP01 IP Baseline Inspections ERO Drill Participation 08/02/2009 08/08/2009 1
71151-EP02 IP Baseline Inspections Alert & Notification System 08/02/2009 08/08/2009 1
71151-EP03 IP 1
7111107T
- HEAT SINK INSP Baseline Inspections Heat Sink Performance 08/10/2009 08/14/2009 1
7111107T IP 1
- PUB RAD SAFETY - REMP Generic Safety Inspectio Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 09/21/2009 09/25/2009 1
2515/173 IP Baseline Inspections Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 09/21/2009 09/25/2009 1
7112203 IP 1
7111108P
- INSERVICE INSPECTION Baseline Inspections Inservice Inspection Activities - PWR 10/05/2009 10/09/2009 1
7111108P IP Baseline Inspections Inservice Inspection Activities - PWR 10/19/2009 10/23/2009 1
7111108P IP 1
71121
- OCC RAD SAFETY Baseline Inspections ALARA Planning and Controls 10/19/2009 10/23/2009 1
7112102 IP 1
- PUB RAD SAFETY - RETS Generic Safety Inspectio Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 11/16/2009 11/20/2009 1
2515/173 IP Baseline Inspections Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 11/16/2009 11/20/2009 1
7112201 IP 1
71121
- OCC RAD SAFETY Baseline Inspections ALARA Planning and Controls 12/07/2009 12/11/2009 1
7112102 IP Baseline Inspections Occupational Exposure Control Effectiveness 12/07/2009 12/11/2009 1
71151-OR01 IP Baseline Inspections RETS/ODCM Radiological Effluent 12/07/2009 12/11/2009 1
71151-PR01 IP This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.