ML041910206

From kanterella
Jump to navigation Jump to search
IR 05000528-04-011, IR 05000529-04-011 and IR 05000530-04-011 on January 26 Through June 10, 2004; Palo Verde Nuclear Generating Station, Units 1, 2, and 3
ML041910206
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/08/2004
From: Chamberlain D
Division of Reactor Safety IV
To: Overbeck G
Arizona Public Service Co
References
4-2002-052, EA-04-100 IR-04-011
Download: ML041910206 (25)


See also: IR 05000528/2004011

Text

July 8, 2004

EA-04-100

Gregg R. Overbeck, Senior Vice President, Nuclear

Arizona Public Service Company

P.O. Box 52034

Phoenix, AZ 85072-2034

SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 - NRC

INSPECTION REPORT 05000528/2004011, 05000529/2004011,

05000530/2004011 AND INVESTIGATION REPORT 4-2002-052

Dear Mr. Overbeck:

This refers to the inspection conducted by the Nuclear Regulatory Commission (NRC) into the

circumstances of an October 4, 2002, incident involving the movement of irradiated fuel. The

purpose of the inspection was to follow up on a failure to follow procedural requirements that

resulted in damage to an irradiated fuel assembly. In addition, certain aspects of this incident

were investigated by the NRCs Office of Investigations. On June 10, 2004, Mr. Anthony Gody

of my staff discussed the results of the NRCs review of this incident with you and members of

your staff.

This inspection was an examination of activities conducted under your license as they relate to

safety and compliance with the Commissions rules and regulations and with the conditions of

your license. Within these areas, the inspection consisted of selected examination of

procedures and representative records, observations of activities, and interviews with

personnel.

Based on the results of this inspection, an apparent violation of NRC requirements was

identified involving a failure to promptly and adequately communicate important aspects of this

incident to appropriate Palo Verde Nuclear Generating Station (PVNGS) management

personnel. A detailed discussion of the apparent violation is in the enclosed inspection report.

Based on its review of all of the circumstances surrounding this incident, the NRC is concerned

that this communication failure may have involved willfulness, i.e., careless disregard for

PVNGS procedural requirements that are designed to assure that incidents of this significance

are promptly communicated to appropriate levels of plant management. Specifically, it appears

that details regarding the seriousness of the incident and steps taken by the spent fuel handling

machine operator immediately following the incident were not communicated to appropriate

levels of plant management. The NRC is concerned that these communication failures

prevented PVNGS management from assessing the circumstances of this incident in a timely

manner and taking appropriate corrective actions before fuel handling resumed.

Arizona Public Service Company -2-

This apparent violation is being considered for escalated enforcement action in accordance with

the "General Statement of Policy and Procedure for NRC Enforcement Actions" (Enforcement

Policy), NUREG-1600. The current Enforcement Policy is available on the NRCs Web site at

www.nrc.gov; select What We Do, Enforcement, then Enforcement Policy. Since the NRC

has not made a final determination in this matter, no Notice of Violation is being issued for this

apparent violation at this time. In addition, please be advised that the characterization of the

apparent violation described in the enclosed inspection report may change as a result of further

NRC review.

As discussed with you by telephone, before making a final enforcement decision in this matter,

the NRC would like to discuss the apparent violation in a predecisional enforcement

conference. The conference, which will be closed to public observation and transcribed, has

been scheduled for August 20, 2004, in the NRCs Region IV office in Arlington, Texas. The

decision to hold a predecisional enforcement conference does not mean that the NRC has

made a final determination that a violation has occurred or that enforcement action will be

taken. This conference is being held to obtain information to assist the NRC in making an

enforcement decision. This may include information to determine whether a violation occurred,

information to determine the significance of a violation, including whether willfulness was

involved, and information related to any corrective actions taken or planned. The conference

will provide an opportunity for you to provide your perspective on these matters and any other

information that you believe the NRC should take into consideration in making a final

enforcement decision. You will be advised by separate correspondence of the results of our

deliberations on this matter. No response regarding the apparent violation is required at this

time.

In addition to the apparent violation, the NRC also has identified four issues that were evaluated

under the risk significance determination process as having very low safety significance

(green). Three of the findings were determined to be violations of NRC requirements. These

violations, which are described in the enclosed inspection report, are being treated as noncited

violations, consistent with Section VI.A of the Enforcement Policy. If you contest the violations

or the significance of the noncited violations, you should provide a response within 30 days of

the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to the

Regional Administrator, NRC Region IV, the Director, Office of Enforcement, United States

Nuclear Regulatory Commission, Washington, DC 20555-0001, and the NRC Resident

Inspector at PVNGS.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be made available electronically for public inspection in the NRC Public

Document Room or from the NRCs document system (ADAMS), accessible from the NRC

Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

//RA//

Dwight D. Chamberlain, Director

Division of Reactor Safety

Arizona Public Service Company -3-

Dockets: 50-528; 50-529; 50-530

Licenses: NPF-41; NPF-51; NPF-74

Enclosure:

Inspection Report 05000528/2004-011; 05000529/2004-011

w/Attachment Supplemental Information

cc w/enclosure:

Steve Olea

Arizona Corporation Commission

1200 W. Washington Street

Phoenix, AZ 85007

Douglas K. Porter, Senior Counsel

Southern California Edison Company

Law Department, Generation Resources

P.O. Box 800

Rosemead, CA 91770

Chairman

Maricopa County Board of Supervisors

301 W. Jefferson, 10th Floor

Phoenix, AZ 85003

Aubrey V. Godwin, Director

Arizona Radiation Regulatory Agency

4814 South 40 Street

Phoenix, AZ 85040

M. Dwayne Carnes, Director

Regulatory Affairs/Nuclear Assurance

Palo Verde Nuclear Generating Station

Mail Station 7636

P.O. Box 52034

Phoenix, AZ 85072-2034

Hector R. Puente

Vice President, Power Generation

El Paso Electric Company

310 E. Palm Lane, Suite 310

Phoenix, AZ 85004

Jeffrey T. Weikert

Assistant General Counsel

El Paso Electric Company

Mail Location 167

123 W. Mills

El Paso, TX 79901

Arizona Public Service Company -4-

John W. Schumann

Los Angeles Department of Water & Power

Southern California Public Power Authority

P.O. Box 51111, Room 1255-C

Los Angeles, CA 90051-0100

John Taylor

Public Service Company of New Mexico

2401 Aztec NE, MS Z110

Albuquerque, NM 87107-4224

Cheryl Adams

Southern California Edison Company

5000 Pacific Coast Hwy. Bldg. DIN

San Clemente, CA 92672

Robert Henry

Salt River Project

6504 East Thomas Road

Scottsdale, AZ 85251

Brian Almon

Public Utility Commission

William B. Travis Building

P.O. Box 13326

1701 North Congress Avenue

Austin, TX 78701-3326

Arizona Public Service Company -5-

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

Senior Resident Inspector (GXW2)

Branch Chief, DRP/D (TWP)

Senior Project Engineer, DRP/D (JAC)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (KEG)

Jennifer Dixon-Herrity, OEDO RIV Coordinator (JLD)

PV Site Secretary (vacant)

C. Nolan, OE (MCN)

G. Sanborn, ACES (GFS)

M. Vasquez, ACES (GMV)

S. Lewis, OGC (SHL)

PV Site Secretary (vacant)

DPowers (STA)(DAP)

ADAMS: : Yes * No Initials: __JFD____

Publicly Available * Non-Publicly Available * Sensitive : Non-Sensitive

DOCUMENT: R:\_PV\2004\PV2004-011rp-jfd.wpd

OE:OB SOE:OB C:OB ACES C:PBD D:DRS

JFDrake/lmb PCGage ATGody GSanborn TPruett DDChamberlain

/RA/ GEWerner for /RA/ RXWise for CJPaulk for /RA/

7 /1 /04 7/8 /04 7/8/04 7/8 /04 7/8/04 7/8/04

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Dockets: 50-528; 50-529; 50-530

Licenses: NPF-41; NPF-51; NPF-74

Report No.: 05000528/2004-011; 05000529/2004-011; 05000530/2004-011

Licensee: Arizona Public Service Company

Facility: Palo Verde Nuclear Generating Station, Units 1, 2, and 3

Location: 5951 S. Wintersburg Road

Tonopah, Arizona

Dates: January 26 through June 10, 2004

Inspectors: J. F. Drake, Operations Engineer, Operations Branch

P. C. Gage, Senior Operations Engineer, Operations Branch

Approved By: Anthony T. Gody, Chief

Operations Branch

Division of Reactor Safety

-2-

SUMMARY OF FINDINGS

IR 05000528/2004011; 05000529/2004011; 05000530/2004011; January 26 through June 10,

2004; Palo Verde Nuclear Generating Station, Units 1, 2, and 3

The report covered a period of an announced inspection by two regional operations engineers

Three Green noncited violations, one Green finding, and one apparent violation with the safety

significance to be determined were identified. The significance of most findings is indicated by

its color (Green, White, Yellow, Red) using Inspection Manual Chapter 0609, "Significance

Determination Process." Findings for which the Significance Determination Process does not

apply may be green or be assigned a severity level after NRC management review. The NRCs

program for overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.

NRC-Identified and Self Revealing Findings

Cornerstone: Initiating Events

Inspector Identified Findings

GREEN. The inspectors identified a noncited violation of Technical Specification 5.4.1

associated with a failure to operate the spent fuel handling machine in accordance with

Procedure 78OP-9FX03, Spent Fuel Handling Machine, Revision 16. There were

three instances of this: (1) On October 4, 2002, the spent fuel handling machine

operator moved fuel assemblies of two differing weights and was not cognizant of

design differences of the fuel assemblies and did not stop fuel movement when the load

was greater than 50 lbs. different from expected; (2) On October 4, 2002, the spent fuel

handling machine operator failed to verify that the hoist was in its full up position prior to

moving a spent fuel assembly, and (3) later on October 4, 2002, another spent fuel

handling operator failed to verify that the hoist was in its full up position prior to moving a

spent fuel assembly. In both Examples (2) and (3), the operators failed to verify the UP

LIMIT light was on and failed to verify the hoist indicator was at the UPLIMIT. As a

result, in Example (3), the one fuel assembly was damaged. These issues were

contrary to Procedure 78OP-9FX03 and resulted in damage to the lower grid assembly

of Fuel Assembly P1M316.

This finding is greater than minor because it had an actual impact of damage to an

irradiated fuel assembly and, therefore, could be reasonably viewed as a precursor to a

significant event. If the fuel cladding had failed, it could have caused a release of fission

products to the environment. The finding is of very low safety significance because all

mitigation systems were available during the fuel movement operations and should have

prevented an unplanned release of radioactive material to the environment above the

limits of 10 CFR Part 100. This finding also had crosscutting aspects in the area of

human performance. (Section 4OA2 1.b.1.a)

GREEN. The inspectors identified a noncited violation of Technical Specification 5.4.1

associated with an inadequate abnormal operating procedure. Specifically, the

inspectors determined that PVNGS Procedure 40AO-9ZZ22, Fuel Damage,

-3-

Revisions 1 through 6, were not adequate in that the entry conditions never required

operations personnel to enter the procedure and take actions to mitigate the event.

Step 1.1 states, in part, Section 3.0, Irradiated Fuel Damage may be entered when any

of the following conditions exist . . . when equipment or component failures result in any

of the following: irradiated fuel assembly contacting a solid structure; bubbles emerging

from a spent fuel assembly; bent, twisted, or warped spent fuel assembly; or visual

damage to spent fuel pin cladding. Since this abnormal operating procedure was never

entered, applicable actions were never considered during the Fuel Assembly P1M316

event.

This finding is greater than minor because actions taken in response to fuel handling

errors could result in significant fuel cladding damage and effect the barrier cornerstone.

The finding is of very low safety significance because all mitigation systems were

available and should have prevented an unplanned release of radioactive material to the

environment above the limits of 10 CFR Part 100. This finding also had crosscutting

aspects in the area of problem identification and resolution. (Section 4OA2 1.b.1.b)

GREEN. The inspectors identified a self-revealing finding of very low safety significance

(green) associated with the material condition of the spent fuel handling machine. A

number of issues related to material condition, which affected spent fuel handling

machine operations, was identified. These included intermittent overload and underload

conditions with no identified cause, upender limit switches that often failed or required

adjustments during fuel movement, an unreliable hydraulic power unit for the upender

machine which occasionally resulted in the upender drifting from the vertical position,

and the spent fuel handling machine trolley occasionally stopped for no apparent

reason.

This finding is greater than minor because it had an actual impact resulting in damage to

an irradiated fuel assembly and, therefore, could be reasonably viewed as a precursor to

a significant event. If the fuel cladding had failed, it could have caused a release of

fission products. The finding is of very low safety significance because all mitigation

systems were available and should have prevented an unplanned release of radioactive

material to the environment above the limits of 10 CFR Part 100. (Section 4OA2 1.b.2)

TBD. The inspectors identified an apparent violation of 10 CFR Part 50, Appendix B,

Criterion XVI. Specifically, the licensee established measures to assure that conditions

adverse to quality are promptly identified and corrected in Procedure 90DP-0IP10,

Condition Reporting. Procedure 90DP-0IP10, Revision 15, Step 3.1.2, required that

the shift manager be promptly notified if a condition required immediate action to ensure

the safety of plant personnel or equipment. Additionally, Procedure 90DP-0IP10,

Appendix B, requires verbal notification to the leader and to the appropriate shift

manager. The SFHM operator failed to notify the shift manager and department leader

for fuel operations that he took actions which he felt were necessary to place the fuel

assembly in a safe condition. Additionally, it appears that details regarding the

seriousness of the incident and steps taken by the SFHM operator immediately following

the incident were not communicated to appropriate levels of plant management (See

Section 4OA2 1.b). The failure to notify the shift manager and department leader for

fuel operations resulted in an inappropriate organizational response to the Fuel

-4-

Assembly P1M316 event that did not involve station management in the decision-

making process.

This apparent violation was greater than minor because it had an actual impact on

management response for damage to an irradiated fuel assembly and, therefore, could

be reasonably viewed as a precursor to a significant event. If the fuel cladding had

failed, it could have caused a release of fission products. The safety significance of this

finding will be determined pending the outcome of the predecisional enforcement

conference. (Section 4OA2 1.b.3)

GREEN. The inspectors identified a noncited violation of 10 CFR Part 50, Appendix B,

Criterion XVI, Corrective Action, for failing to effectively correct conditions adverse to

quality that contributed to the damage to irradiated Fuel Assembly P1M316.

Specifically, Criterion XVI states, in part, that . . . conditions adverse to quality, such as

malfunctions, deficiencies, deviations, defective material and equipment, and

nonconformances are promptly identified and corrected." The licensee failed to

effectively correct conditions adverse to quality, which included repeated violations of

equipment operating procedures and conduct of operations procedures, as well as

long-standing degraded material condition of the fuel handling equipment, that ultimately

contributed to the damage of irradiated Fuel Assembly P1M316.

This finding is greater than minor because it had an actual impact of damage to an

irradiated fuel assembly and, therefore, could be reasonably viewed as a precursor to a

significant event. If the fuel cladding had failed, it could have caused a release of fission

products. The finding is of very low safety significance because all mitigation systems

were available and should have prevented an unplanned release of radioactive material

to the environment above the limits of 10 CFR Part 100. This finding also had

crosscutting aspects in the area of problem identification and resolution. (Section 4OA2

1.b.4)

REPORT DETAILS

4. OTHER ACTIVITIES

4OA2 Problem Identification and Resolution

1. Spent Fuel Handling

a. Inspection Scope

The inspectors evaluated the circumstances surrounding a series of spent fuel handling

errors that culminated in damage to an irradiated fuel assembly (P1M316) on October 4,

2002, and a failure to enter the issues related to the fuel handling errors into the

corrective action program until NRC involvement. The scope of the inspection included

a review of: (1) procedural requirements associated with spent fuel handling in the fuel

building, such as, communications with licensed operators and the control room, the

conduct of operations, equipment operating procedures, abnormal and emergency

operations, and the decision making command structure following an abnormal event

involving potentially damaged fuel; (2) training and qualifications of refueling machine

operators, spent fuel handling machine (SFHM) operators, senior reactor operators

limited to fuel handling (LRSO), and other personnel involved in the movement of fuel;

(3) the specific circumstances associated with fuel movement errors which occurred on

October 4, 2002; (4) the failure to identify and correct operating issues associated with

previous fuel handling issues; and (5) a detailed review of external factors, such as, the

material condition and reliability of refueling equipment, quality of and adherence to

procedures, refueling operations command and control, fatigue, schedule related

pressures, human interactions, effectiveness of peer reviews, etc.

b. Assessment

Introduction. On October 4, 2002, improper spent fuel handling operations at the facility

resulted in damage to an irradiated fuel assembly. While specific corrective actions had

been implemented from previous events, they were not entirely effective in addressing

the cumulative effects of fuel handling issues. These problems were found to include

procedural issues, ineffective communications, and a tolerance for operating degraded

equipment.

In the Procedure Issues Section below, the inspectors identified one self-revealing

Green noncited violation associated with the licensees failure to follow refueling

procedure and one self-revealing Green noncited violation associated with an

inadequate abnormal operating procedure for damaged fuel. In the Material Condition

Issues Section below, the inspectors identified one self-revealing Green finding

associated with the poor material condition of the SFHM and its effect on operations. In

the Communications Issues Section below, the inspectors identified one apparent

violation associated with inadequate communications between the SFHM operator, the

shift manager, and the department leader for fuel handling. Finally, in the Corrective

Actions Section below, the inspectors identified one self-revealing Green noncited

violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for failing to

effectively correct numerous operating issues associated with previous fuel movements

which ultimately resulted in damage to Fuel Assembly P1M316.

-2-

Event Description, Root and Contributing Causes

According to the licensees investigation, at approximately 10 p.m. on October 4, 2002,

the SFHM operator grappled Fuel Assembly P1M316 from the upender machine.

While hoisting Fuel Assembly P1M316 out of the upender, the SFHM operator thought

the UPLIMIT light on the SFHM control console was lit, which was one of the

indications that Fuel Assembly P1M316 had cleared the upender machine. The SFHM

Procedure 78OP-9FX03, Revision 16, Step 4.3.18, stated, Raise hoist until UPLIMIT

light is on. Check hoist indicator to ensure UPLIMIT has been reached. Although the

UPLIMIT light was believed to be checked, the hoist indicator was not checked by the

operator. The SFHM operator trolleyed the SFHM out of the fuel handling zone of the

spent fuel pool and gave permission to the second operator to sequence the upender

machine to the containment position. As the upender machine was sequencing to the

containment position, the SFHM trolley motion stalled. Once the operators recognized

that Fuel Assembly P1M316 had not cleared the upender machine, the upender

machine sequence was stopped. According to interviews with personnel both directly

and remotely involved in the event, approximately 7 inches of the lower part of Fuel

Assembly P1M316 was stuck in the upender machine while the top of Fuel

Assembly P1M316 was still grappled to the SFHM. Descriptions of the actual position of

Fuel Assembly P1M316 were varied, but it is believed that the upender was

approximately 5 to 10 degrees from vertical, and the SFHM trolley had traveled

approximately 1.5 to 3 feet from the upender position.

The licensee identified that the root cause of the October 4, 2002, fuel damage event

was that the SFHM operator failed to ensure that Fuel Assembly P1M316 was clear of

the upender machine before moving the SFHM trolley away and authorizing the

movement of the upender machine back to the containment position. This was

contrary to Procedure 78OP-9FX03 and resulted in damage to the lower grid of Fuel

Assembly P1M316. Other notable issues contributed to the failure to verify that Fuel

Assembly P1M316 was clear of the upender machine before moving the SFHM, these

included: inadequate self- and peer-checking, inadequate procedure use, schedule

pressure, unclear definitions of responsibilities and authorities between the SFHM

operator and the peer checker, inadequate communications on the spent fuel handling

machine, weaknesses in training of fuel handling personnel, and a number of equipment

design and reliability issues resulting in a lack of sensitivity to certain alarms and

indications. Each of these issues, their regulatory implications, and corrective actions

are discussed in the sections below.

Recovery Actions, Root and Contributing Causes

As discussed above, the SFHM operator recognized that Fuel Assembly P1M316 was

stuck in the upender machine because the SFHM trolley had stalled during SFHM

trolley movement. The SFHM operator stated that he believed he had notified the on-

shift LSRO and the reactor engineer stationed in the control room of the problem with

Fuel Assembly P1M316. The SFHM operator stated that he also believed that the shift

manager had been appropriately notified. The licensees investigation found that

implementation of the procedural requirement to maintain direct communications

between the control room and personnel at the refueling station described in

Procedure 72IC-9RX03, Nuclear Administrative and Technical Manual, Appendix C,

-3-

was not effective. This became apparent through interviews, which demonstrated that,

in reality, communications between personnel on the SFHM, LSRO1 in the containment

building, the reactor engineer, and the shift manager did not result in a clear

understanding of what occurred with Fuel Assembly P1M316.

After the SFHM trolley had stalled and the SFHM operator found the electrical SFHM

controls inoperable, the SFHM operator then installed a manual hand wheel on the

SFHM trolley and manually hand cranked the SFHM trolley toward the upender machine

in an effort to more vertically orient Fuel Assembly P1M316. During interviews, the

SFHM operator indicated that the safest orientation for Fuel Assembly P1M316 was

vertical over the hoist. The hand-cranking evolution, although not prohibited by

procedures, was conducted without authorization from LSRO1 or from the control room.

During interviews, LSRO1 indicated that he ordered the SFHM operator to stop fuel

movement in the fuel building. The actual timing of LSRO1s order and hand-cranking

of the SFHM trolley could not be confirmed. Therefore, the team could not establish if

the SFHM trolley was moved after the order was given. Regardless, no other individuals

but those on the SFHM were aware that the SFHM trolley had been manually

repositioned over the upender machine. Interviews with the SFHM operator indicated

that the SFHM trolley was manually moved to place Fuel Assembly P1M316 in a safe

condition. With respect to the premise behind moving the SFHM trolley manually to

place Fuel Assembly P1M316 in a safe condition, the team concluded that the manual

movement of the SFHM trolley with Fuel Assembly P1M316 suspended between the

SFHM and the upender machine without LSRO1 and shift manager involvement was not

appropriate. Furthermore, the team concluded that it would have been a more

appropriate decision to evaluate the potential for additional damage to or dropping Fuel

Assembly P1M316 before manually hand-cranking the SFHM trolley. After reviewing

the design of the grapple assembly and the position of Fuel Assembly P1M316, the

team concluded the following: (1) Fuel Assembly P1M316 was stable following the

overload trip of the SFHM trolley, and (2) dropping Fuel Assembly P1M316 during hand-

cranking was not a probable event.

In an effort to understand the communications that took place between the SFHM

operator and others on the communications circuit, a number of personnel were

interviewed. The LSRO1 indicated that he remembered being informed by the SFHM

operator that Fuel Assembly P1M316 was stuck in the upender. The LSRO1 indicated

that even though he asked a number of pertinent questions, he was not getting a clear

picture of what happened in the fuel building. The LSRO1 indicated that he surmised

that the SFHM trolley had been moved out of the refueling zone because the interlocks

would have prevented the upender machine from sequencing to the containment

position until the SFHM trolley was at that location. After LSRO1 gave the order to stop

all activities in the fuel building, he contacted another licensed operator limited to fuel

movement (LSRO2), who was not on watch at the time to investigate the status of Fuel

Assembly P1M316. When LSRO2 arrived in the fuel building, he noted that personnel

on the SFHM were about to install a handwheel on the hoist and ordered them to stop.

The LSRO2 asked the personnel on the SFHM what they intended to do and if they had

moved the upender machine. The SFHM operator replied they were about to manually

lift Fuel Assembly P1M316 out of the upender machine and no, they had not moved

the upender machine. It was determined through interviews with the fuel handling team

that the upender machine actually had been sequenced to the containment position

-4-

after the SFHM trolley had been moved out of the fuel handling zone and that the SFHM

trolley had been manually repositioned over the upender after the overload trips had

been received prior to LSRO2 arriving in the fuel building.

The licensee identified that the root cause of the improper actions associated with not

involving LSRO1 and the shift manager in the decision making process following the

Fuel Assembly P1M316 event was that SFHM operators lacked sensitivity to fuel

handling events. Contributing causes identified by the licensee included: (1) previous

corrective actions to improve communications were not effective, (2) pre-job briefings

did not address the notification process for off-normal conditions, (3) the event checklist

did not accomplish its purpose, (4) training and pre-job briefs did not ensure SFHM

operators were knowledgeable of the entry conditions for the abnormal operating

procedure for fuel damage, and (5) senior reactor operators limited to fuel handling were

reluctant to establish communications directly with control room supervision. Each of

these issues, their regulatory implications, and corrective actions are discussed in the

sections below.

Corrective Actions, Root and Contributing Causes

On October 9, 2002, an NRC manager contacted the department leader for fuel

operations to discuss fuel bowing issues. During that discussion, the NRC manager

inquired about operator errors noted in reactor engineering logs. The NRC manager

found that the department leader was not aware of what the operator errors referred to

(ultimately, the Fuel Assembly P1M316 event) and that no corrective actions had been

taken. Following the teleconference, the licensee initiated a Significant Condition

Report/Deficiency Report (CRDR) 2559423 and an investigation was commenced. On

October 10, 2002, the licensee conducted inspections of Fuel Assembly P1M316 and

found damage that resulted in the fuel assembly not being reloaded.

The inspectors identified several issues related to the implementation of the licensees

problem identification and resolution program. The first issue was that the initial actions

taken by the SFHM operator to recover Fuel Assembly P1M316 were not in accordance

with procedures on conduct of operations and condition reporting (see below). Second,

the licensee failed to take corrective actions to resolve previous operational issues

surrounding the fuel movement (some of which involved procedural violations, see

below). This was particularly important since it was noted in the licensees subsequent

investigation that a precursor event had occurred when an SFHM operator was moving

an irradiated fuel assembly while it was not at the UPLIMIT position. Third, no CRDR

had been initiated and no verbal notification to the SFHM operators leader (department

leader for fuel operations) or the shift manager until the NRC manager contacted the

department leader for fuel operations 5 days later. Although the SFHM operator drafted

a statement regarding the events that took place while he was on watch before he left

for home, he did not share that statement with anyone. These issues were contrary to

the condition reporting process (see below). The actual communications that took place

were vague and failed to communicate the pertinent details of the Fuel Assembly

P1M316 event nor did the SFHM operator communicate the subsequent recovery

actions taken independently by the SFHM operator on his own volition. The SFHM

operator indicated that he needed to take those actions to place Fuel Assembly P1M316

in a safe condition.

-5-

.1 Procedure Issues

.1a Failure to follow Procedures

Introduction. Three examples of a Green noncited violation were identified for failure to

follow procedures as prescribed in Technical Specification 5.4.1.

Description. On October 4, 2002, during core offload, there were three instances where

licensee personnel failed to operate the spent fuel handling machine in accordance with

Procedure 78OP-9FX03, Spent Fuel Handling Machine, Revision 16. As a result of

failing to follow procedures, Fuel Assembly P1M316 was damaged and was

subsequently not reloaded into the core due to the damage. These errors were

documented in CRDR 2711453.

In the root cause analysis for CRDR 2711453 and subsequent interviews with refueling

personnel, it was determined that there had been numerous overload trips of the spent

fueling handling machine, with no apparent cause. The licensee identified the cause of

these overload trips as being associated with the overload setpoint of the spent fuel

handling machine (approximately 1633+ 12.5lbs). The core was loaded with two

different fuel assembly designs. One fuel assembly weighed approximately 1600 lbs.

and the other weighed approximately 1750 lbs. The SFHM operators were not aware of

the differences in the weight of the fuel assemblies and did not follow Procedure

Step 4.3.17, which required the operator to monitor fuel assembly weights and to stop

and determine the problem if the load was greater than 50 lbs over the expected load.

There were two instances where the SFHM operators failed to verify the hoist had

reached its upper travel limit. Procedure Step 4.3.18, required the operators to verify

that the UPLIMIT light was lit and that the UPLIMIT was reached. The UPLIMIT

was verified by checking a manual position indicator called a Durant counter. Earlier in

the day, the licensee documented an event where the SFHM operators traversed the

spent fuel handling machine trolley out of the fuel handling zone without the fuel

assembly being fully retracted. No fuel damage occurred during this event; however, it

was a precursor to the next event that resulted in fuel damage.

As fuel movement continued, the operators damaged Fuel Assembly P1M316. This

damage was the result of failing to verify the fuel assembly was at the UPLIMIT prior to

moving the fuel assembly away from the upender in the spent fuel pool. For details on

this event see Section 4AO2 1.b.

Analysis. The deficiency associated with this event was that licensee personnel failed to

follow procedures required by Technical Specifications, which resulted in fuel damage.

This finding was more than minor because damage to irradiated Fuel Assembly P1M316

occurred as a result of a failure to follow prescribed procedures. The operating issues

associated with fuel handling operations could be reasonably viewed as a precursor to a

more significant event affecting the barrier integrity cornerstone. The finding is of very

low safety significance because all mitigation systems were available and should have

prevented an unplanned release of radioactive material to the environment above the

limits of 10 CFR Part 100. This finding had crosscutting aspects in the area of human

performance.

-6-

Enforcement

Technical Specification 5.4.1 requires, in part, that written procedures be established,

implemented, and maintained as recommended in Appendix A of Regulatory

Guide 1.33, "Quality Assurance Program Requirements (Operation)," Revision 2,

February 1978. Regulatory Guide 1.33, Revision 2, Appendix A, provides the typical

activities that should be covered by written procedures. Section 2.l. specifies that

general plant operating procedures be developed for refueling and core alterations.

Accordingly, (1) Procedure 78OP-9FX03, Step 4.3.17, required the SFHM operator to

"Monitor load cell indication. It should be +/-50 lbs. of assembly weight (if exceeded, stop

and determine problem before continuing)," and (2) Procedure 78OP-9FX03,

Step 4.3.18, required the SFHM operator to, Raise hoist until UP LIMIT light is on.

Check hoist indicator to ensure UPLIMIT has been reached, prior to moving irradiated

fuel as required by the fuel transfer form.

Contrary to the above: (1) On October 4, 2002, the SFHM operator moved fuel

assemblies of two differing weights and was not cognizant of design differences of the

fuel assemblies and did not stop fuel movement when the load was 50 lbs. greater than

expected. One fuel assembly design weighed approximately 1600 lbs. and the other

weighed approximately 1750 lbs. Because of the lack of knowledge of the two differing

designs of fuel weight, the operator could not have adequately followed the guidance of

the procedural steps listed above. (2) On October 4, 2002, on two occasions, SFHM

operators failed to verify that the hoist was in its full up position prior to moving a spent

fuel assembly. The operators failed to verify the UPLIMIT light was on and failed to

verify the hoist indicator was at the UPLIMIT. As a result, one fuel assembly was

damaged. Because these examples of failure to follow refueling procedures are of very

low safety significance and have been entered into the licensees corrective action

program (CRDR 2711971), this violation is being treated as a noncited violation,

consistent with Section VI.A of the NRC Enforcement Policy: Noncited

Violation 05000528; 05000529;05000530/2004011-01, Failure to Follow Refueling

Procedure 78OP-9FX03, Spent Fuel Handling Machine, Revision 16.

.1b Inadequate Procedure

Introduction. A Green noncited violation was identified for failure to establish an

adequate procedure for an abnormal condition (damaged irradiated fuel assembly) as

prescribed in Technical Specification 5.4.1.

Description. The inspectors determined that the fuel damage abnormal operating

procedure was not adequate. Following the Fuel Assembly P1M316 event, the licensee

identified that SFHM operators were not adequately trained or pre-briefed on the entry

conditions for Procedure 40AO-9ZZ22, Fuel Damage. This, combined with

inadequately defined entry conditions for Procedure 40AO-9ZZ22, contributed to the

failure to take the appropriate actions immediately following the Fuel Assembly P1M316

event. The inspectors determined that PVNGS Procedure 40AO-9ZZ22, Revisions 1

through 6, were inadequate, in that, the entry conditions did not require operations

personnel to enter the procedure and take any immediate actions to mitigate the event.

Specifically, Step 1.1 states, in part, Section 3.0, Irradiated Fuel Damage may be

-7-

entered when any of the following conditions exist . . . when equipment or component

failures result in any of the following: irradiated fuel assembly contacting a solid

structure; bubbles emerging from a spent fuel assembly; bent, twisted, or warped spent

fuel assembly; or visual damage to spent fuel pin cladding. The SFHM operator

contacted a solid structure and damaged the fuel assembly but did not enter

Procedure 40AO-9ZZ22. Although no actual fuel cladding damage occurred during this

event, the inspectors concluded the procedure failed to require any immediate corrective

actions.

Analysis. The inspectors determined this deficiency was an inadequate abnormal

procedure for combating emergencies as required by Technical Specification 5.4.1.

This finding is more than minor because actions taken in response to fuel handling

errors could result in significant fuel cladding damage and effect the barrier cornerstone.

The finding is of very low safety significance because all mitigation systems were

available and should have prevented an unplanned release of radioactive material to the

environment above the limits of 10 CFR Part 100. This finding had crosscutting aspects

in the area of problem identification and resolution.

Enforcement

Technical Specification 5.4.1 requires, in part, that written procedures be established,

implemented, and maintained as recommended in Appendix A of Regulatory

Guide 1.33, "Quality Assurance Program Requirements (Operation)," Revision 2,

February 1978. Regulatory Guide 1.33, Revision 2, Appendix A, provides the typical

activities that should be covered by written procedures. Section 6.x. specifies

procedures for combating emergencies for irradiated fuel damage, including immediate

operator actions.

Contrary to the above, Procedure 40AO-9ZZ22, Fuel Damage, Revisions 1 through 6,

failed to develop entry conditions and required steps that would have resulted in the

immediate operator actions taking place after irradiated Fuel Assembly P1M316 was

stuck in the upender (contacted a solid structure) and was damaged during movement

on October 4, 2004. Specifically, the inspectors determined Procedure 40AO-9ZZ22,

Revisions 1 through 6, were inadequate, in that, the entry conditions did not require

operations personnel to enter the procedure and take immediate actions to mitigate the

event. Step 1.1 states, Section 3.0, Irradiated Fuel Damage may be entered when any

of the following conditions exist: . . . when equipment or component failures result in any

of the following: irradiated fuel assembly contacting a solid structure; bubbles emerging

from a spent fuel assembly; bent, twisted, or warped spent fuel assembly; or visual

damage to spent fuel pin cladding. Since this abnormal operating procedure was never

entered, applicable actions were never considered during the Fuel Assembly P1M316

event. Because this example of an inadequate procedure is of very low safety

significance and has been entered into the licensees corrective action program

(CRDR 2711453), this violation is being treated as a noncited violation, consistent with

Section VI.A of the NRC Enforcement Policy: noncited violation 05000528; 05000529;05000530/2004011-02, Inadequate Procedure 40AO-9ZZ22, Fuel Damage,

Revisions 1 through 6.

-8-

.2 Material Condition

Introduction. The inspectors identified a self-revealing Green finding associated

with a number of SFHM material condition issues that contributed to damage to Fuel

Assembly P1M316.

Description. A number of issues related to material condition, which affected SFHM

operation, were identified. These included intermittent overload and underload

conditions with no identified cause, upender limit switches that often failed or required

adjustments during fuel movement, an unreliable hydraulic power unit for upender

machine, which occasionally resulted in the upender drifting from the vertical position,

and an instance, when the SFHM trolley occasionally stopped for no apparent reason.

The intermittent overload and underload trips and alarms desensitized SFHM operators

to those alarms and may have contributed to the Fuel Assembly P1M316 event because

an overload condition stops hoist movement in a manner similar to the uplimit condition.

The overload condition could be mistaken for an uplimit condition if the SFHM operator

did not verify other indications. That could explain why Fuel Assembly P1M316 had not

cleared the upender machine prior to trolley movement. Past problems with the

upender, such as, limit switch adjustments and hydraulic leakage, resulted in the

upender drifting off vertical and causing overload conditions while moving irradiated fuel

in and out of the upender. These past problems, combined with misstatements about

operation of the upender during the Fuel Assembly P1M316 event, misled operators in

thinking that the Fuel Assembly P1M316 event may have been a result of upender

drifting problems.

During interviews of operators and technicians, the inspectors found that these material

condition problems occasionally resulted in operators opening control cabinets and

manipulating wires and hardware to get the machinery to operate again. In addition, the

inspectors noted that the licensee used a general open work order to document and

facilitate repairs to fuel handling equipment. The general open work order would be

periodically closed and disposed of since it was not considered a quality record. The

practice of not documenting material condition problems in a program capable of

tracking the issues resulted in several problems: (1) many material condition issues

were not retrievable, (2) material condition issues resulting in operational work-arounds

were not reported to station management unless they had a schedule impact,

(3) problem trending was not possible, and (4) no assessment of the cumulative impact

of the material condition problems and their impact on operations was conducted. On

May 17, 2002, CRDR 2506874 was written in an apparent effort to inform management

of continued problems with refueling equipment reliability. The CRDR indicated that

during the last two refueling outages . . . manual operations of limit switches or

associated equipment had to be used to complete core off-load or re-load . . . these are

not ideal means . . . and are precursors to more serious events. The inspectors

reviewed the closure of CRDR 2506874 and found that it had been closed in two other

CRDRs (2507835 and 2512708), which were limited to specific material issues rather

than an overall assessment of the cumulative impacts that the poor SFHM material

condition had on operations.

The licensee implemented a number of corrective actions on or after October 17, 2002,

to address the aforementioned material condition issues. The team reviewed these

-9-

corrective actions and found them to be appropriate with some notable comments,

which are discussed in the Corrective Action section below.

Analysis. The inspectors identified a self-revealing Green finding associated with a

number of SFHM material condition issues that contributed to the Fuel

Assembly P1M316 event. These findings were more than minor because damage to

irradiated Fuel Assembly P1M316 occurred as a result of operational issues that

involved a failure to follow prescribed operating procedures complicated by SFHM

material condition issues. The operational issues associated with fuel handling

operations and Fuel Assembly P1M316 post event actions could be reasonably viewed

as precursors to a more significant event affecting the barrier integrity cornerstone. The

finding is of very low safety significance because all mitigation systems were available

and would have prevented an unplanned release of radioactive material to the

environment above the limits of 10 CFR Part 100 .

Enforcement. None.

.3 Communications

Introduction. An apparent violation was identified for inadequate communications

between the SFHM operator, the shift manager, and the department leader for fuel

handling as prescribed in Procedure 90DP-0IP10, Condition Reporting, Revision 15.

Description. The inspectors identified one apparent violation associated with inadequate

communications between the SFHM operator, the shift manager, and the department

leader for fuel handling. As discussed earlier, LSRO1 indicated he was unable to obtain

a clear picture of what had happened in the fuel building. Also during interviews, the

shift manager and other licensed operators in control indicated that they were not aware

of the spent fuel handling errors that culminated in damage to Fuel Assembly P1M316.

Although the SFHM operator wrote a statement describing the event at the end of the

shift, he did not share the statement with responsible licensee managers until several

days after the event. Finally, the organizational response to the Fuel Assembly P1M316

event indicated that communications between the shift manager, LSRO1, and the SFHM

operator were ineffective in keeping the licensee management informed of the status of

Fuel Assembly P1M316.

As a result of the inadequate communications, responsible licensee managers were not

aware of the event, its significance, and the circumstances until NRC questioning 5 days

later. Given the SFHM operators normal position in the organization (LSRO1 and

LSRO2's supervisor) and familiarity with the condition reporting procedure, it appears he

should have ensured that communication to the appropriate levels of management

occurred to properly identify the causes of the event and to take effective corrective

actions before resuming fuel movement.

Analysis. TBD. The inspectors identified an apparent violation of PVNGS corrective

action procedure. The apparent violation involved inadequate notification and

communications between the SFHM operator, the shift manager, and the department

leader for fuel operations. This finding was more than minor because damage to

irradiated Fuel Assembly P1M316 occurred and ineffective communications contributed

-10-

to the inadequate organizational response to place equipment in a safe condition and

correct operational issues prior to resuming fuel movement. The operational issues

associated with fuel handling operations and Fuel Assembly P1M316 post event actions

could be reasonably viewed as precursors to a more significant event affecting the

barrier integrity cornerstone.

Enforcement. Criterion XVI of 10 CFR Part 50, Appendix B, states, in part, that,

[m]easures shall be established to assure that conditions adverse to quality, such as

malfunctions, deficiencies, deviations, defective material and equipment, and

nonconformances are promptly identified and corrected. In the case of significant

conditions adverse to quality, the measures shall assure that the cause of the condition

is determined and corrective action taken to preclude repetition. The identification of the

significant condition adverse to quality, the cause of the condition, and the corrective

action taken shall be documented and reported to appropriate levels of management.

Accordingly, the licensee established measures to assure that conditions adverse to

quality were promptly identified and corrected in Procedure 90DP-0IP10.

Procedure 90DP-0IP10, Step 3.1.2, required that the shift manager be promptly notified

if a condition required immediate action to ensure the safety of plant personnel or

equipment. Procedure 90DP-0IP10, Appendix B, indicated that if the condition required

immediate action to ensure the safety of plant personnel or equipment, the originator

shall provide verbal notification to his or her leader and to the appropriate shift manager.

In addition, it required a CRDR to be completed as soon as practical.

Contrary to the above, on October 4, 2002, the SFHM operator failed to notify the shift

manager and department leader for fuel operations that he took actions which he felt

were necessary to place the fuel assembly in a safe condition. Additionally, it appears

that details regarding the seriousness of the incident and steps taken by the SFHM

operator immediately following the incident were not communicated to appropriate levels

of plant management (See Section 4OA2 1.b). The failure to notify the shift manager

and department leader for fuel operations resulted in an inappropriate organizational

response to the Fuel Assembly P1M316 event that did not involve station management

in the decision-making process. (AV 05000528; 05000529;05000530/2004011-03)

.4 Corrective Actions

Introduction. The inspectors noted a number of failures to correct the operational issues

associated with refueling activities. This contributed to the damage to Fuel

Assembly P1M316 and was a self-revealing Green noncited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Action.

Description. The inspectors reviewed condition reports, root cause analyses, interviews,

and evaluation reports that revealed a broad pattern of operational issues that had not

been corrected before the damaged Fuel Assembly P1M316 event. These previous

operational issues included: failure to conduct adequate pre-job briefs, moving the

spent fuel handling machine with a fuel assembly without the UPLIMIT light, no

second/peer checker, lack of oversight at the spent fuel pool, failure to use the Event

Check List for notification of off normal issues, and failure to reset the SFHM overload

setpoint. The licensee identified all (except moving the SFHM without the "UPLIMIT"

-11-

light, which became self-revealing after damage occurred to Fuel Assembly P1M316) of

the above operational issues after the fall 2001 and spring 2002 refueling outages. The

licensee took corrective actions to address each of these issues; however, while specific

fuel handling program issues were addressed, the corrective actions were not adequate

to correct broad operational issues. For instance, the licensee instituted pre-job briefs,

but the briefs failed to identify the occurrence of hoist overloads and necessity to ensure

the fuel assembly was clear of the upender. In addition, a peer checker was assigned to

the SFHM, but no procedural requirements or guidance was given to or discussed with

the peer checker. In fact, this peer checker was relatively new to the site and had never

done fuel movement and was not aware of his responsibilities as a peer checker. The

inspectors found that these same issues contributed to the damage to Fuel

Assembly P1M316.

The licensee implemented a number of corrective actions before the Fuel

Assembly P1M316 event to address the operational issues. As noted by the licensees

investigation, the corrective actions taken before October 4, 2002, were ineffective at

preventing the Fuel Assembly P1M316 event.

As discussed in Section 4OA2 b.1, the procedural requirements to verify that the

indicated weight of a fuel assembly being moved is within + 50 lbs. of the expected

weight could not be effectively implemented. The problem was, in part, due to no

documentation being provided to the fuel handlers as to the expected weight of the

assembly. In addition, the different assembly weights combined with one set of alarm

setpoints resulted in a number of overload alarms when no overload condition existed.

Preconditioning of operators to alarms resulted in a decrease in the sensitivity to

potential abnormal conditions. The licensee had in fact identified the differences in fuel

assembly weights and had reset the refueling machine overloads to a higher setpoint,

but did not reset the SFHM overload setpoints.

Analysis. The inspectors identified a noncited violation associated with a failure to

properly implement corrective actions associated with previous conditions adverse to

quality. This finding was more than minor because damage to irradiated Fuel

Assembly P1M316 occurred as a result of identified adverse conditions not being

corrected. The operational issues associated with fuel handling operations and Fuel

Assembly P1M316 post event actions could be reasonably viewed as precursors to a

more significant event affecting the barrier integrity cornerstone. The finding is of very

low safety significance because all mitigation systems were available and should have

prevented an unplanned release of radioactive material to the environment above the

limits of 10 CFR Part 100. The finding had crosscutting aspects in the area of problem

identification and resolution.

Enforcement. Criterion XVI of 10 CFR Part 50, Appendix B, states, in part, that,

Measures shall be established to assure that conditions adverse to quality, such as

malfunctions, deficiencies, deviations, defective material and equipment, and

nonconformances are promptly identified and corrected.

Contrary to the above, the licensee failed to effectively correct conditions adverse to

quality that contributed to the damage of irradiated Fuel Assembly P1M316. Because

the damage to Fuel Assembly P1M316 did not involve damage to the cladding, the

-12-

ineffective corrective actions were of very low safety significance and have been entered

into the licensees corrective action program as CRDR 2711971. This violation is being

treated as a noncited violation consistent with Section VI.A of the NRC Enforcement

Policy: Noncited Violation 05000528; 05000529;05000530/2004011-04, Ineffective

Corrective Actions.

4OA6 Meetings, Including Exit

On June 10, 2004, the inspectors presented the inspection results to Greg Overbeck

and other members of his staff who acknowledged the findings. The inspectors

confirmed that proprietary information was not provided or examined during this

inspection

ATTACHMENT

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

G. Overbeck, Senior Vice President

David Mauldin, Vice President Engineering and Support

D. Smith, Plant Manager

W. Chapin, Nuclear Fuel Management Department Leader

S. Bauer, Regulatory Affairs Department Leader

J. Taylor, Operations Department Leader

P. Crawley, Life Cycle Management Director

C. Seaman, Nuclear Fuel Management Director

R. Henry, Site Representative

R. Buzzard, Regulatory Affairs Senior Consultant

K. Manne, Senior Attorney

J. Gutierrez, Attorney

NRC personnel

N. Salgado, Senior Resident Inspector

J. Melfi, Resident Inspector

LIST OF ITEMS OPENED AND CLOSED

Opened and Closed

05000528; 05000529; NCV Failure to Follow Refueling Procedure 78OP-9FX03,05000530/2004011-01 Spent Fuel Handling Machine, Revision 16, resulting in

damage to irradiated Fuel Assembly P1M316

(Section 40A2 1.b.1.a)

05000528; 05000529; NCV Inadequate Procedure 40AO-9ZZ22, Fuel Damage,05000530/2004011-02 Revisions 1 through 6 (Section 40A2 1.b.1.b)

05000528; 05000529; NCV Inadequate corrective actions contributed to damage to

05000530/2004011-04 fuel assembly. (Section 40A2 1.b.4)

-2-

Opened

05000528; 05000529; AV Failure to effectively notify the shift manager and

05000530/2004011-03 department leader for fuel operations resulted in an

inappropriate organizational response to the Fuel

Assembly P1M316 event that did not involve station

management in the decision-making process

(Section 40A2 1.b.3)

LIST OF DOCUMENTS REVIEWED

Procedures

78OP-9FX03 Spent Fuel Handling Machine, Revision 14

78OP-9FX03 Spent Fuel Handling Machine, Revision 15

78OP-9FX03 Spent Fuel Handling Machine, Revision 16

78OP-9FX03 Spent Fuel Handling Machine, Revision 17

78OP-9FX03 Spent Fuel Handling Machine, Revision 18

78OP-9FX03 Spent Fuel Handling Machine, Revision 19

78OP-9FX03 Spent Fuel Handling Machine, Revision 20

78OP-9FX03 Spent Fuel Handling Machine, Revision 21

78OP-9FX02 Fuel Transfer Machine, Revision 7

78OP-9FX02 Fuel Transfer Machine, Revision 8

78OP-9FX02 Fuel Transfer Machine, Revision 9

78OP-9FX01 Refueling Machine Operations, Revision 12

78OP-9FX01 Refueling Machine Operations, Revision 13

78OP-9FX01 Refueling Machine Operations, Revision 14

78OP-9FX01 Refueling Machine Operations, Revision 15

78OP-9FX01 Refueling Machine Operations, Revision 16

78ST-9FH02 Fuel Building Crane Travel, Revision 5

40DP-9AP18 Abnormal Operating Procedures Users Guide, Revision 2

40DP-9OP33 Shift Turnover, Revision 12

72IC-9RX03 Core Reloading, Revision 15

72IC-9RX03 Core Reloading, Revision 16

72IC-9RX03 Core Reloading, Revision 17

72IC-9RX03 Core Reloading, Revision 18

72IC-9RX03 Core Reloading, Revision 19

72IC-9RX03 Core Reloading, Revision 20

72IC-9RX03 Core Reloading, Revision 21

40AO-9ZZ22 Fuel Damage, Revision 1

40AO-9ZZ22 Fuel Damage, Revision 2

40AO-9ZZ22 Fuel Damage, Revision 3

40AO-9ZZ22 Fuel Damage, Revision 4

40AO-9ZZ22 Fuel Damage, Revision 5

-3-

40AO-9ZZ22 Fuel Damage, Revision 6

40AO-9ZZ22 Irradiated Fuel Damage, Revision 0

40DP-9OP02 Conduct of Shift Operations, Revision 17

40DP-9OP02 Conduct of Shift Operations, Revision 18

40DP-9OP02 Conduct of Shift Operations, Revision 19

40DP-9OP02 Conduct of Shift Operations, Revision 20

40DP-9OP02 Conduct of Shift Operations, Revision 21

40DP-9OP02 Conduct of Shift Operations, Revision 22

40DP-9OP02 Conduct of Shift Operations, Revision 23

40DP-9OP02 Conduct of Shift Operations, Revision 24

40DP-9OP02 Conduct of Shift Operations, Revision 25

40DP-9OP02 Conduct of Shift Operations, Revision 26

40DP-9OP02 Conduct of Shift Operations, Revision 27

40DP-9OP02 Conduct of Shift Operations, Revision 28

78TI-9RX01 Spent Fuel Inspection, Revision 1

30DP-9MP12 Overhead Hoisting Systems, Revision 10

90DP-0IP10 Condition Reporting, Revision 15

84DP-0RM30 Record Control and Turnover, Revision 15

72DP-9NF01 Control of SNM and Inventory, Revision 9

40ST-9ZZM6 Operations Mode 6 Surveillance Logs, Revision 5

70DP-0OP18 Engineering Test Conduct

01DP-0EM10 Fitness for Duty Program, Revision 13

40OP-9ZZ23 Outage GOP, Revision 25

Limited Senior Reactor Operator Initial Training Program

Fuel Handlers Training Program

Training Records for Fuel Handlers

Training Records for Reactor Engineers

Training Records for LSROs

Qualification Records for various operators

Palo Verde Nuclear Fuel System Design Dimensions Fuel Assembly plus Rod Assemblies

Condition Report Deficiency Reports related to Refueling from 27 April 2001 to 24 January 2004.

Work Orders associated with refueling equipment

Controlled Work Packages for refueling equipment