Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011)
ML24262A097
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 09/23/2024
From: Shiattin Makor
NRC/RGN-IV/DORS/EB2
To: Heflin A
Arizona Public Service Co
Makor S
References
IR 2024001
Download: ML24262A097 (6)


See also: IR 05000529/2024011

Text

September 23, 2024

Adam Heflin, Executive Vice President

and Chief Nuclear Officer

Arizona Public Service

P.O. Box 52034, MS 7602

Phoenix, AZ 85702-2034

SUBJECT:

PALO VERDE NUCLEAR GENERATING STATION, UNIT 2 - NOTIFICATION

OF POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL AND

REQUEST FOR INFORMATION INSPECTION (05000529/2024011)

Dear Adam. Heflin:

On October 21, 2024, the U. S. Nuclear Regulatory Commission (NRC) will begin a Post-

Approval Site Inspection for License Renewal for your facility. Two inspectors will perform this

one week inspection in accordance with NRC Inspection Procedure 71003. This inspection

focuses on activities associated with license renewal implementation of aging management

programs, regulatory commitments, as well as any tests or inspections of structures, systems,

or components which are only accessible at reduced power levels.

To minimize the inspection impact on the site and to ensure a productive inspection for both

parties, we have enclosed a request for information needed for the inspection. It is important

that all these documents are up to date and complete to minimize the number of additional

documents requested during the preparation and/or the on-site portions of the inspection.

Please provide this information electronically to the lead inspector. The information request has

two groups:

The first group lists information necessary for our initial inspection scoping and in-office

preparation activities. During the in-office preparation activities, the team will identify as

much as possible the information and activities to be reviewed during the inspection.

This information should be provided to the lead inspector by October 14, 2024.

The second group includes additional information required for the team to review the

selected activities. This information should be available to the team on October 21, 2024. It

is also requested that corrective action documents and/or questions developed during the

inspection be provided to the lead inspector as the documents are generated.

The schedule for the inspection is as follows:

Offsite Preparation Week: October 14 - 18, 2024

Onsite Inspection Week: October 21 - 25, 2024

A. Heflin

2

PAPERWORK REDUCTION ACT STATEMENT

This letter contains mandatory information collections that are subject to the Paperwork

Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)

approved these information collections (approval number 3150-0011). Send comments

regarding this information collection to the Information Services Branch, Office of the Chief

Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington, DC

20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of

Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and

Budget, Washington, DC 20503.

PUBLIC PROTECTION NOTIFICATION

The NRC may not conduct nor sponsor, and a person is not required to respond to, a request

for information or an information collection requirement unless the requesting document

displays a currently valid OMB control number.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Shiattin T. Makor, Senior Reactor Inspector

Engineering Branch 2

Division of Operating Reactor Safety

Signed by Makor, Shiattin

on 09/23/24

A. Heflin

3

Docket No. 05000529

License No. NPF-51

Enclosure:

1.

License Renewal Phase 2 Document Request

cc w/ encl: Distribution via LISTSERV

ML24262A097

X

SUNSI Review

X

Non-Sensitive

Sensitive

X

Publicly Available

Non-Publicly Available

OFFICE

SRI:DORS:EB2

NAME

SMakor

SIGNATURE

/RA/

DATE

09/23/24

Enclosure 1

Enclosure 1

License Renewal Phase 1 Document Requests

Inspection Report:

2024-011

Onsite Inspection Dates:

October 21 - 25, 2024

Inspection Procedure:

IP 71003 Post-Approval Site Inspection for License

Renewal

The documents and information requested below should generally be made available to the

inspection team for the team's use both on-site and off-site. Electronic format is the preferred

media, preferably in a searchable format. Electronic media should contain descriptive names

and be indexed and hyperlinked to facilitate ease of use. Information in lists should contain

enough information to be easily understood by someone who has knowledge of light water

reactor technology. If electronic media is made available via an internet based remote document

management system, then the remote document access must allow inspectors to download,

save, and print the documents in the NRC's regional office. Electronic media on compact disc

or paper records (hard copy) are acceptable. At the end of the inspection, the documents in the

team's possession will not be retained.

This document request is based on typical documents that a generic plant might have. As such,

this document request is not meant to imply that any specific plant is required to have all of the

listed documents. In addition, your plant specific document titles may vary from the document

titles listed below. We also request that the information provided be sorted by the list below.

I.

Documents requested prior to on-site inspection October 14, 2024 (Week Prior to

Inspection)

1.

Provide a list of your license renewal commitments associated with appropriate aging

management programs. Include the completion status of each. For those not yet

complete, please provide an estimated completion date.

2.

Provide a list of your aging management programs, copies of the program basis

document for each, and a listing of the tracking items for each.

3.

For aging management programs that are one-time inspection programs, provide a list of

completed work order numbers for inspections that have been completed. This should

include identification of the inspected component.

4.

Provide a listing of planned inspections that will be conducted during the onsite week,

credited for license renewal, that provide observations of areas that are generally

inaccessible at power (e.g., containment liner and containment coating inspections). If

there are no inspections planned, the inspectors will select areas normally inaccessible

that will need to be reviewed.

2

5.

Provide current management and license renewal organizational charts, electronic

copies of Updated Final Safety Analysis Report, Technical Specifications, Technical

Specifications Bases, and Technical Requirements Manual.

6.

Provide copies of any internal/external self-assessments and associated corrective

action documents generated in preparation for the inspection.

II.

Documents requested for on-site inspection (October 21, 2024)

1.

Copies of the work orders requested during the preparation week related to the selected

commitments/aging management programs. This will include work orders of inspections to

be observed and completed work orders to be reviewed by the team.

2.

Contact information to facilitate inspector observation of the selected work activities or

evaluation of inaccessible areas.

3.

Documentation demonstrating completion of license renewal commitments considered

completed as of the inspection date. For example, this may be in the form of a binder for

each commitment that includes the implementing documentation and references.

III.

Documents requested through the inspection

1.

Copies of any corrective action documents generated because of the teams questions or

queries during this inspection.

2.

Copies of the list of questions submitted by the team members and the status/resolution of

the information requested (provide daily during the inspection to each team member).

If you have questions regarding the information requested, please contact the lead inspector.

Inspector Contact Information:

Shiattin Makor (Lead)

Senior Reactor Inspector

817-200-1507

shiattin.makor@nrc.gov

Nnaerika Okonkwo

Reactor Inspector

817-200-1114

nnaerika.okonkwo@nrc.gov

Mailing Address:

U.S. NRC, Region IV

Attn: First Last Name

1600 East Lamar Blvd.

Arlington, TX 76011-4511