August 05, 2025

SUBJECT:

WOLF CREEK GENERATING STATION - INTEGRATED INSPECTION REPORT 05000482/2025002

Dear Cleve Reasoner:

On June 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Wolf Creek Generating Station. On July 8, 2025, the NRC inspectors discussed the results of this inspection with Jamie McCoy, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Ami N. Agrawal, Chief Reactor Projects Branch B Division of Operating Reactor Safety Docket No. 05000482 License No. NPF-42

Enclosure:

As stated:

Inspection Report

Docket Number:

05000482

License Number:

NPF-42

Report Number:

05000482/2025002

Enterprise Identifier:

I-2025-002-0009

Licensee:

Wolf Creek Nuclear Operating Corp.

Facility:

Wolf Creek Generating Station

Location:

Burlington, KS

Inspection Dates:

April 1 to June 30, 2025

Inspectors:

J. Allen, Physical Security Inspector

S. Hedger, Senior Emergency Preparedness Inspector

C. Henderson, Senior Resident Inspector

J. Kirkland, Senior Operations Engineer

L. Moore, Emergency Preparedness Inspector

C. Sigel, Resident Inspector

J. Vera, Senior Resident Inspector

Approved By:

Ami N. Agrawal, Chief

Reactor Projects Branch B

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Wolf Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000482/2024003-01 Failure to Perform Adequate Audit of the Integrated Public Alert Warning System 71114.02 Closed

PLANT STATUS

Wolf Creek Generating Station began the inspection period at full power. On April 10, 2025, the unit commenced a down power to 60 percent reactor power at the request of the grid operator due to the loss of the 345 kV Rose Hill line. The unit returned to full power on April 11, 2025, where it remained for the rest of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)train B essential service water system on April 4, 2025 (2)loss of service water and circulating water systems on April 29, 2025 (3)loss of train A and B non-safety-related 13.8 kilovolt (kV), PA01 and PA02, buses on May 2, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)turbine building elevations 1984, 2000, and 2015; fire areas T-1, T-2, T-3, and T-5, on April 1, 2025 (2)turbine building elevation 2033, fire areas T-2, T-6, T-7, T-8, and T-9, on April 1, 2025 (3)train A emergency diesel generator fire walkdown following rocker arm oil overflow, fire area D-1, on April 9, 2025 (4)train B safety-related 4160 volt switch gear room with class 1E recirculation system in service, fire area C-10, on May 1, 2025 (5)radwaste building, fire area RW, on May 2, 2025

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) train A class 1E air conditioning system heat exchanger on April 16, 2025

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during train B emergency diesel generator testing on April 1, 2025, and train B solid state protection testing with multiple individuals performing under instruction watches for initial operator license qualification on April 7, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a simulator scenario and critique of a main steam isolation inside containment with a failure of the turbine to trip and the main steam isolation valves to close on April 28, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)non-safety switchgear 13.8 kV, PA01 and PA02, maintenance effectiveness on May 20, 2025 (2)class 1E air conditioning system damper maintenance effectiveness on June 2, 2025

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)safety-related 4160 volt breakers stationary auxiliary switch maintenance effectiveness on May 28, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)train A essential service water planned technical specification equipment outage on April 14, 2025 (2)train A class 1E air conditioning system technical specification equipment outage on April 18, 2025 (3)train B essential service water planned technical specification equipment outage on April 23, 2025 (4)emergent work and unplanned limited condition of operation entry for emergency diesel generator B keep warm lube oil pump hand switch failure on May 11, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)battery charger safety function determination program operability determination on April 30, 2025 (2)pressurizer safety valves B and C potential seat leakage operability determination on May 12, 2025 (3)train B emergency diesel generator keep warm lube oil pump hand switch failure past operability determination on May 18, 2025 (4)train B auxiliary feedwater pump outboard oil sample water percentage above the action level operability determination on May 29, 2025 (5)train A offsite circuit transformer number 9 current transformer wiring error operability determination on June 16, 2025 (6)emergency diesel generator train A operability following rocker arm oil reservoir tank overflow on June 20, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1)emergent work for train A motor-driven auxiliary feedwater pump discharge header to steam generator motor-operated isolation valve troubleshooting and repair post-maintenance testing on April 25, 2025 (2)emergent work and repair of train B emergency diesel generator keep warm lube oil system post-maintenance testing on May 13, 2025 (3)turbine-driven auxiliary feedwater pump discharge to A and C steam generators, ALHV0008/12, during the turbine-driven auxiliary feedwater system technical specification equipment outage post-maintenance testing on May 20, 2025 (4)condensate storage to turbine-driven auxiliary feedwater pump, ALHV0036, limitorque maintenance and essential service water system supply valve from essential service water system, ALHV0033, valve stroke and position indication test on May 20, 2025 (5)gas supply check valve, ALV0153, for the D steam generator flow control valve from the turbine-driven auxiliary feedwater pump on May 21, 2025

Surveillance Testing (IP Section 03.01) (3 Samples)

(1)train A class 1E air condition system airflow surveillance testing and signal point vulnerabilities on May 29, 2025 (2)class 1E recirculation system halon testing on May 29, 2025 (3)train A class 1E air condition system heat exchanger flow and differential pressure surveillance testing on June 16, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1)train A residual heat removal heat exchanger outlet air-operated valve, EJHCV0606, stroke time in the alert range on June 12, 2025

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1)full load performance test of spent fuel FLEX generator and pump testing on June 11, 2025

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated input provided by the Federal Emergency Management Agency (FEMA) regarding an observed deviation from the licensee's Alert and Notification System (ANS) audit process as described in the approved ANS design report. The deviation was identified during an inspection conducted August 5-9, 2024.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • APF 06-002-02, "Emergency Action Levels Technical Bases", Revision 3

[NRC notified on December 12, 2024 (Agencywide Documents Access and Management System [ADAMS] Accession No. ML24284A284)]

  • EPP 06-001, "Control Room Operations", Revision 33 [NRC notified on November 27, 2024 (ML24332A094)]
  • EPP 06-010, "Personnel Accountability and Evacuation", Revision 12

[NRC notified on November 27, 2024 (ML24332A094)]

This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1)hostile action emergency plan drill on April 9, 2025

71114.07 - Exercise Evaluation - Hostile Action Event

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors observed the biennial hostile action event exercise and evaluated emergency plan performance on June 3, 2025. The exercise scenario involved hostile action events, including simulated site impact by small aircraft. This resulted in a rapid escalation to a Site Area Emergency classification; activation of alternative response facilities, coordination to move plant staff into the plant for damage assessment with law enforcement; response actions to fuel damage and steam generator rupture; and a simulated radiological release offsite.

71114.08 - Exercise Evaluation - Scenario Review

Inspection Review (IP Section 02.01 - 02.04) (1 Sample)

(1) The inspectors reviewed the licensee's preliminary exercise scenario that was submitted to the NRC on April 2, 2025 (ML25092A192), for the exercise scheduled on June 3, 2025. The inspectors discussed the preliminary scenario comments with Joshua Bousum, Manager, Emergency Planning, and other members of the emergency planning staff on April 28, 2025. The inspector's review does not constitute NRC approval of the scenario.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS07: High Pressure Injection Systems (IP Section 02.06)===

(1) April 1, 2024, through March 31, 2025

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) April 1, 2024, through March 31, 2025 BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)
(1) April 1, 2024, through March 31, 2025

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) April 1, 2024, through March 31, 2025

EP01: Drill/Exercise Performance Sample (IP Section 02.12) (1 Sample)

(1) July 1, 2024, through March 31, 2025 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) July 1, 2024, through March 31, 2025 EP04: Emergency Response Facility and Equipment Readiness (ERFER) (IP Section 02.14) (1 Sample)
(1) January 1 through March 31, 2025

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)class 1E recirculation system heat load not evaluated for with swing safety-related inverters NN015 and 016 in service on May 13, 2025

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in procedure and work order quality that might be indicative of a more significant safety issue.

INSPECTION RESULTS

Unresolved Item (Closed)

Failure to Perform Adequate Audit of the Integrated Public Alert Warning System URI 05000482/2024003-01 71114.02

Description:

During an inspection conducted August 5-9, 2024, the inspectors identified a deviation between the audit practices implemented by the licensee compared to what is described in their FEMA approved ANS design report and its implementing procedures. Therefore, inspectors documented the apparent deviation between audit practices implemented and the design report description in Unresolved Item 05000482/20204003-02 (ML24295A379). On November 22, 2024, the NRC requested a review by FEMA to establish whether the licensee was in compliance with the ANS requirements (ML24306A176).

On February 10, 2025, FEMA's response (ML25042A621) indicated agreement that the documentation available supporting the associated audit report was not sufficient to support the report's conclusions. Input from the Policy and Oversight Branch within the Office of Nuclear Security & Incident Response following this communication indicated that the design and responsibilities associated with the Integrated Public Alert Warning System (IPAWS)program audit are being re-assessed in consultation with FEMA. Therefore, assessment of licensee performance related to audit practices will be paused until later notice. This has no effect on the NRC's established reasonable assurance position (ML25160A112).

Feedback provided in FEMA's assessment was provided to licensee staff on June 4, 2025. Actions based on the feedback will be documented in the corrective action program.

Corrective Action Reference(s): Condition Report 10035589 Observation: Semiannual Trend Review 71152S The inspectors reviewed the licensees corrective action program, performance indicators, system health reports, and other documentation available to help identify performance trends that might indicate the existence of a more significant safety issue. The inspectors verified that the licensee was taking corrective actions to address the identified adverse trends. The inspectors did not review any cross-cutting themes because none existed at the site.

To verify that the licensee was taking corrective actions to address identified adverse trends that might indicate the existence of a more significant safety issue, the inspectors reviewed the corrective action program documentation associated with a potential adverse trend in procedure and work order quality. Specifically, the inspectors reviewed the licensees process through the corrective action program and procedure change process when a deficiency of a procedure or work instruction was identified. From this review the inspectors identified the following examples that did not contain interim corrective action or timely in the implementation of the procedure prior to its next use:

1. Condition Reports 10041256 and 10041490: Condition Report 10041256 documented

a train B class 1E 4160 volt switchgear (NB02) undervoltage relay was found outside technical specification allowed limits during the performance of Procedure STS IC-208B, 4kV Loss of Voltage and Degraded Voltage Trip Actuating Device Operational Test NB02 Bus, Revision 7. A change to Procedure STS IC-208B was still open to adjust the as-left setpoints for the undervoltage relays to account for relay drift. The licensee concluded the condition report owner did not assign a corrective action to change Procedure STS IC-208B, which would have prevented the error from happening. The inspectors did not identify an interim corrective action to adjust the setpoint prior to revising Procedure STS IC-208B with the updated setpoints or placing the procedure on hold until it was updated prior to its next performance.

2. Condition Report 10038872: This condition report documented a minor inspector

identified violation of Technical Specification 5.4.1.d, Fire Protection Program Implementation, for the licensees failure to implement the fire protection program. Specifically, the licensee failed to identify a halon boundary door did not meet the criteria in accordance with Procedure STN FP-440, Fire Door Visual Inspection, Revision 19, due to the door seal not in contact with the threshold area.

The licensees corrective action was to update Procedure STN FP-440 to provide the method for measuring halon boundary door gaps and provide the acceptance criteria to ensure halon boundary functionality. However, the inspectors identified the corrective action was due September 25, 2025, and there were no interim corrective actions to provide guidance to the individuals in the field prior to the update to Procedure STN FP-440.

From the above, the inspectors questioned the procedure change process had sufficient guidance to ensure procedure changes were implemented in a timely fashion prior to the next performance or ensure interim guidance was provided until the procedure update. The licensee initiated Condition Report 10042726 to capture the inspectors observations.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 28, 2025, the inspectors presented the emergency preparedness exercise scenario review inspection results to Joshua Bousum, Manager, Emergency Planning, and other members of the licensee staff.
  • On July 8, 2025, the inspectors presented the ANS IPAWS audit practices unresolved item inspection results to Jaime McCoy, Site Vice President, and other members of the licensee staff.
  • On July 8, 2025, the inspectors presented the emergency preparedness exercise inspection results to Jaime McCoy, Site Vice President, and other members of the licensee staff.
  • On July 8, 2025, the inspectors presented the integrated inspection results to Jamie McCoy, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Condition Report

(CR)

10039173, 10039177, 10040444

E-11PA01

Higher Medium Voltage System 13.8 kV Single Line Meter

and Relay Diagram

E-11PG02

Low Voltage System Non-Class 1E 480V. Single Line Meter

and Relay Diagram

KD-7496

One Line Diagram

M-12EF01

Piping Instrumentation Diagram Essential SVC Water

System

M-12EF02

Piping and Instrumentation Diagram Essential Service Water

System

Drawings

M-K2EF01

Piping and Instrumentation Diagram Essential Service Water

System

Miscellaneous

E-10PA

System Description Higher Medium Voltage System 13.8 kV

(Non-Class 1E Power System)

AI 21-016

Operator Time Critical Actions Validation

ALR 00-008B

Serv WTR Press HI LO

18A

ALR 00-010B

SL3 UV/DC CTRL PWR Loss

7A

ALR 00-010D

SL31 Bus Trouble

6B

ALR 00-015A

PA01/PA02 BKR Lockout

6A

CKL EF-120

Essential Service Water Valve, Breaker and Switch Lineup

EMG E-0

Reactor Trip or Safety Injection

71111.04

Procedures

SYS EF-200

Operation of the ESW System

Calculations

XX-E-013

Post-Fire Safe Shutdown (PFSSD) Analysis

Corrective Action

Documents

Condition Report

(CR)

10006354, 10031492, 10039059

Corrective Action

Documents

Resulting from

Inspection

Condition Report

(CR)

10041813

E-1F9910

Post-Fire Safe Shutdown Area Analysis

71111.05

Drawings

KD-7496

One Line Diagram

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

DCP 14269

SGK05 Permanent Compensatory Modifications

E-1F9905

Fire Hazard Analysis

M-618.4

Technical Specification for Compensatory Ductwork,

Dampers, and Appurtenances for the Class 1E Equipment

Air Conditioning System for Wolf Creek Generating Station

M-618.4-00018

Damper Test Data

WCNOC-171

Post-Fire Safe Shutdown Associated Circuits Study

WCNOC-PSA-

067

Wolf Creek Generating Station PRA Internal Fire -

Qualitative Screening, Quantitative Screening and

Quantification Notebook

Miscellaneous

WCRE-35

Boundary Matrix

ALR KC-888

Fire Protection Panel KC-008 Alarm Response

AP 10-100

Fire Protection Program

AP 10-106

Fire Preplans

MPE VD-001

M627A Ventilation Damper Maintenance

OFN KC-016

Fire Response

STN FP-401A

HALON System/ESF Switchgear Room 1 (KC-222)

8A

STN FP-401B

Halon System/ESF Switchgear Room 2 (KC-222)

8A

STN FP-402A

Train A HALON System Checkout for KC-230

11B

STN FP-402B

Train B Halon System Checkout for KC-230

Procedures

SYS GK-201

Mitigating Actions for Inoperable SGK05 train

5A

Work Orders

WO

16-414781-050, 16-414781-150, 16-414781-226,

16-414781-331, 16-414781-337, 16-414781-346,

16-414781-350

71111.07A

Procedures

AP 23L-002

Heat Exchanger Program

STN RP-002E

EDG B Control CKT and FO XFER Pump ISO Switch

STS NB-005

Breaker Alignment Verification

STS-IC-211A

Actuation Logic Test Train A Solid State Protection System

37A

Procedures

SYS KJ-200

Inoperable Emergency Diesel

71111.11Q

Work Orders

WO 049248, 23-489131-026

71111.12

Corrective Action

Documents

Condition Report

(CR)

144171, 10037622, 10037823, 10039233, 10039395

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Resulting from

Inspection

Condition Report

(CR)

10041538, 10041885, 10041987, 10042406, 10042508,

10042724, 10042725

E-13EJ01

Schematic Diagram Residual Heat Removal Pumps

E-13GL05

Schematic Diagram Pump Room Coolers

E-13NB04

Lower Medium Voltage Sys. Class 1E 4.16kV Three Line

Meter and Relay Diagram

Drawings

M-12GK03

Piping and Instrumentation Diagram Control Building HVAC

Engineering

Changes

CCP 013145

Type SB-12 Auxiliary Switch Assembly Screws

A-2801-05

Instruction Manual for Indoor Metal-Glad Switchgear

W13

E-009-00318

Instructions for Type SB-12 Auxiliary Switch SD# GEI-74670

W02

E-10PA

System Description Higher Medium Voltage System 13.8 kV

(Non-Class 1E Power System)

WCNOC-171

Post-Fire Safe Shutdown Associated Circuits Study

Miscellaneous

WCRE-35

Boundary Matrix

AI 16C-005

Toolpouch and Minor Maintenance Preparation and

Implementation

AI 16C-006

Troubleshooting

AP 10-100

Fire Protection Program

AP 16C-006

Work Activity Process Controls

AP 16E-002

Post Maintenance Testing Development

21D

EDI 23M-010

Determination of Structures, Systems, and Components

within the Scope of Maintenance Rule

MGE RA-006

Raychem WCSF In-Line Splicing and Terminations

MPE E009-01

Siemens Breaker Cubicle Maintenance, Testing and

Swapping

MPE E009Q-01

13.8 kV and 4.16 kV Switchgear Inspection and Testing

MPE VD-001

M627A Ventilation Damper Maintenance

STN FP-402A

Train A Halon System Checkout for KC-230

11B

STN FP-402B

Train B HALON System Checkout for KC-230

11B

Procedures

STN FP-450

Fire Damper Inspection and Drop Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

STN NB-001B

B Train Breaker Operability and ECCS Pump Recirc

STN PA-106

PG Load Center FDR Breaker 252PA0106 Trip Circuit

Verification

SYS OPS-004

Breaker Operation

Work Orders

WO 3959, 46491, 78677, 109872, 110284, 15-397643-000,

16-414781-229, 16-414781-259, 18-441883-000,

18-441884-000, 20-464389-001, 20-464983-000,

20-464984-000, 22-477371-000, 23-487860-000,

23-487984-000

Corrective Action

Documents

Condition Report

(CR)

10041571

Drawings

E-13KJ11

Schematic Diagram Lube Oil/Keep Warm Pump

AI 23M-007

Structures Monitoring Program

ALR 00-023D

DG NE02 Trouble

ALR 502

Standby Diesel Engine System Control Panel KJ-122

34A

AP 10-103

Fire Protection Impairment Control

AP 22C-003

On-line Nuclear Safety and Generation Risk Assessment

AP 22C-007

Risk Management and Contingency Planning

Procedures

SYS KJ-200

Inoperable Emergency Diesel

71111.13

Work Orders

WO 28209

Corrective Action

Documents

Condition Report

(CR)

28368, 91588, 100377920, 10037795, 10040061, 10040407,

10040854, 10040867, 10041158, 10041326, 10041387,

10041571, 10041589, 10041608

E-13KJ04

Schematic Diagram Diesel Generator KKJ01B Annunciator

and Miscellaneous Circuits

E-13KJ10

Schematic Diagram Standby Lube Oil Heater

E-13KJ11

Schematic Diagram Lube Oil/Keep Warm Pump

Drawings

M-12KJ06

Piping and Instrumentation Diagram Standby Diesel

Generator B Lube Oil System

Engineering

Changes

CCP 08052

KKJ01A/B Lube Oil/Jacket Water Alarm Setpoints

M-018-00309

Instruction Manual for Emergency Diesel Generator System

W141

M-021-00061

Instruction Manual for Auxiliary Feedwater Pumps

W29

71111.15

Miscellaneous

WCLR-08

Lubricating Oil Analysis B2.1.23 NUREG-1801 Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

XI.M39 Aging Management Program

ALR 00-023D

DG NE2 Trouble

ALR 502

Standby Diesel Engine System Control Panel KJ-122

34A

AP 21D-006

Safety Function Determination Program

AP 26C-004

Operability Determination and Functionality Assessments

CKL ZL-004

Turbine Building Reading Sheets

186

I-ENG-004

Lubricating Oil Analysis

MPE ML-001

Motor Sampling and Lubrication PM Activity on Various

Equipment

17A

STS CR-001

Shift Log for Modes 1, 2, and 3

117A

SYS GK-201

Mitigating Actions for Inoperable SGK05 Train

5A

SYS KJ-122

Standby Emergency Diesel Main Lube Oil Strainer Fill and

Vent

SYS KJ-130

Removal and Restoration of EDG Support Systems

Procedures

SYS KJ-300

Emergent and Unplanned Removal of EDG Support

Systems

Calculations

GK-M-016

Wolf Creek Control Building Loss of Class 1E A/C Gothic

Room Heat Up Analysis with Installed Crosstie Fans and

Louvers

Corrective Action

Documents

Condition Report

(CR)

144171, 94961, 10035295, 10037828, 10038890, 10040061,

10040455, 10040458, 10041217, 10041220, 10041539,

10041571, 10041809

E-13KJ11

Schematic Diagram Lube Oil/Keep Warm Pump

M-12AL01

Piping and Instrumentation Diagram Auxiliary Feedwater

System

M-12FC02

Piping and Instrumentation Diagram Auxiliary Turbines

Auxiliary Feedwater Pump Turbine

M-12GK03

Piping and Instrumentation Diagram Control Building HVAC

M-12GK04

Piping and Instrumentation Diagram Control Building HVAC

M-12KA05

Piping & Instrumentation Diagram, Compressed Air System

M-1H3311

Heating Ventilation and Air Cond. Control Building El. 2000-

Area 1

71111.24

Drawings

M-1H3411

Heating Ventilation and Air Cond. Control Building El. 2016-

Area 1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

DCP 014269

SGK05 Permanent Compensatory Measure

137-P0004

Commercial Grade Dedication Package

WCRE-34

Fourth 10-Year Interval Inservice Testing Basis Document

Miscellaneous

WCRE-35

Boundary Matrix

AP 10-100

Fire Protection Program

AP 21A-002

Diverse and Flexible Coping Mitigation Strategies (FLEX)

Program

3A

AP 23L-002

Heat Exchanger Program

STN FP-402A

Train A Halon System Checkout for KC-230

11B

STN FP-402B

Train B Halon System Checkout for KC-230

11B

STN FP-450

Fire Damper Inspection and Drop Test

STN GK-001A

Class 1E Recirculation System Train A Functional Test

STN GK-001B

Class 1E Recirculation System Train

B Functional Test

STS AL-103

TDAFW Pump Inservice Pump Test

76A

STS AL-120

Motor Driven or Turbine Driven AFW Pump Operations

56A

STS AL-201C

Turbine Driven Auxiliary Feedwater System Inservice Valve

Test

STS AL-211

TD AFP Comprehensive Pump Testing, Flow Path

Verification, & CV testing

STS PE-016A

A Train Class 1E Electrical System A/C Flow Rate

Verification

STS PE-016B

B Train Class 1E Electrical System A/C Flow Rate

Verification

Procedures

SYS AL-123

TDAFW Pump Post Maintenance Run

Work Orders

WO 66608, 66618, 78317, 85089, 86080, 88013, 88017, 118544,

118644, 125656, 128209, 128233, 128236, 415260,

13-374721-012, 13-374721-013, 13-374721-021

Corrective Action

Documents

Condition Reports

10035589

71114.02

Miscellaneous

Electronic Mail

from Don

Johnson to Sean

RE: Discussion with IPAWS Audit Expectations

04/15/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Hedger (Nuclear

Regulatory

Commission

Staff)

Letter from Caty

Nolan, Nuclear

Regulatory

Commission to

Nan Williams,

Federal

Emergency

Management

Agency

Request for Assistance to Address a Concern Regarding

Wolf Creek Nuclear Power Plant Alert and Notification

System Integrated Public Alert and Warning System Audit

Documentation

11/22/2024

Letter from Nan

Williams, Federal

Emergency

Management

Agency, to Caty

Nolan, Nuclear

Regulatory

Commission

Wolf Creek Alert and Annual Audit

2/10/2025

Corrective Action

Documents

Condition Report

(CR)

10039349, 10042133

AIF 26A-003-03

APF 06-002-02 Rev 3 - E-Plan Effectiveness Evaluation

AIF 26A-003-03

EPP 06-001 Rev 33, EPF 06-001-02 Rev 3, EPF 06-001-03,

Rev 6 - E-Plan Effectiveness Evaluation

AIF 26A-003-03

EPP 06-010 - Personnel Accountability and Evacuation

APF 06-002-02

EAL Technical Bases

EPF 06-001-02

Alert Emergency Announcement

EPF 06-001-03

Site Area Emergency Announcement

EPP 06-001

Control Room Operations

71114.04

Miscellaneous

EPP 06-010

Personnel Accountability and Evacuation

71114.06

Corrective Action

Documents

Condition Report

(CR)

10040924, 10040940, 10040941, 10040947, 10040951,

10040953, 10040962

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Condition Report

(CR)

10021975, 10022519, 10023888, 10024030, 10026252,

10027295, 10028475, 10028489, 10029045, 10029208,

10034490, 10035058, 10035470, 10035589, 10038140,

10040386, 10042013, 10042015, 10042019, 10042019,

10042021, 10042116, 10042035, 10042045, 10042049,

10042058, 10042170, 10042171, 10042176

Drill Report: 25-B-Drill (3/18/25)

04/30/2025

Miscellaneous

25 Hostile Action Based Exercise, Leadership Team

Briefing

06/05/2025

AI 28A-010

Screening Condition Reports

AI 28A-100

Condition Report Resolution

EPP 06-002

Technical Support Center Operations

46C

EPP 06-003

Emergency Operations Facility Operation

29A

EPP 06-006

Protective Action Recommendations

EPP 06-007

Emergency Notifications

27A

EPP 06-009

Drill and Exercise Requirements

EPP 06-012

Dose Assessment

18B

71114.07

Procedures

OFN SK-039

Security Event

2e 2015 HAB Exercise Report

2/08/2015

2f 2015 HAB Based Drills and Training 2015 to Present

2015-2025

Emergency Planning Drill Report: ERO Team (C) Pre-

Exercise

04/09/2025

000133

Docket No. 50-482: Submittal of the Radiological Emergency

Response Plan Scenario for the 2023 Evaluated Exercise at

Wolf Creek Generating Station

09/12/2023

000917

Docket No. 50-482: Submittal of the Radiological Emergency

Response Plan Scenario for the 2025 Evaluated Exercise at

Wolf Creek Generating Station

04/02/2025

Miscellaneous

RA 15-0076

Docket No. 50-482: Submittal of the Radiological Emergency

Response Plan Scenario for the 2015 Evaluated Exercise at

Wolf Creek Generating Station

10/06/2015

APF 06-002-02

Emergency Action Levels Technical Bases

71114.08

Procedures

EPP 06-006

Protective Action Recommendations

10A

71151

Corrective Action

Condition Report

10026933, 10035067, 10038452, 10041664, 10042071

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

(CR)

Wolf Creek Generating Station, Emergency Planning Drill -

24-C-Drill

07/08/2024

Drill Report: 24-C-Drill (7/17/24)

07/31/2024

EPF 06-023-01,

Rev. 4

Emergency Response Facility Functionality Evaluation -

TSC, EOF - Date: 01/06/25, Time: 09:10

01/06/2025

EPF 06-023-01,

Rev. 4

Emergency Response Facility Functionality Evaluation -

Facility: TSC, EOF; Date: 03/28/2025; Time: 0800

03/27/2025

GE1135662

Wolf Creek Generating Station, Emergency Planning

Tabletop Exercise

09/24/2024

GE4251601

Wolf Creek Generating Station, Emergency Planning

Simulator Exercise

10/30/2024

Miscellaneous

GE4251601

Wolf Creek Generating Station, Emergency Planning

Simulator Exercise

2/06/2025

AI 26A-004

Emergency Planning Performance Indicators

Procedures

AI 26A-008

NRC/INPO/WANO Performance Indicator and MOR

Reporting

GK-E-001

Electrical Equipment Heat Loads in ESF SWGR, DC SWBD,

and Battery Rooms

Calculations

GK-M-016

Wolf Creek Control Building Loss of Class 1E A/C Gothic

Room Heat Up Analysis with Installed Crosstie Fans and

Louvers

Corrective Action

Documents

Condition Report

(CR)

10035295, 10036590, 10038890, 10040061

Corrective Action

Documents

Resulting from

Inspection

Condition Report

(CR)

10041459

M-12GK03

Piping and Instrumentation Diagram Control Building HVAC

M-12GK04

Piping and Instrumentation Diagram Control Building HVAC

M-1H3311

Heating Ventilation and Air Cond. Control Building El. 2000-

Area 1

71152A

Drawings

M-1H3411

Heating Ventilation and Air Cond. Control Building El. 2016-

Area 1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

WCRE-08

WCGS Fuse List

STN GK-001A

Class 1E Recirculation System Train A Functional Test

STN GK-001B

Class 1E Recirculation System Train B Functional Test

STS PE-016A

A Train Class 1E Electrical System A/C Flow Rate

Verification

STS PE-016B

B Train Class 1E Electrical System A/C Flow Rate

Verification

Procedures

SYS GK-201

Mitigating Actions for Inoperable SGK05 Train

5A

Work Orders

WO

23-487727-000

Corrective Action

Documents

Condition Report

(CR)

10015381, 10018059, 10037622, 10038872, 10039109,

10039286, 10039304, 10041256, 10041459, 10041490,

10041501

Corrective Action

Documents

Resulting from

Inspection

Condition Report

(CR)

10042323, 10042726

Drawings

M-12GK01

Piping and Instrumentation Diagram Control Building HVAC

Engineering

Changes

CCP 015070

NN Power to GK Damper

Miscellaneous

WCRE-35

Boundary Matrix

AP 10-104

Breach Authorization

AP 15C-004

Preparation, Review and Approval of Procedures,

Instructions and Forms

AP 16C-006

Work Activities Process Controls

25B

AP 21D-005

Plant Component Status Control

18A

AP 21G-001

Control of Locked Component Status

078E

AP 21I-001

Temporary Configuration Changes

16B

CKL EN-120

Containment Spray System Lineup

15A

OFN NN-021

Loss of Vital 120 VAC Instrumentation Bus

31A

STN FP-440

Fire Door Visual Inspection

Procedures

SYS NN-332

Deenergizing NN Buses

71152S

Work Orders

WO 65589, 92142, 92776, 111184