IR 05000482/2025003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000482/2025003
ML25345A432
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 12/15/2025
From: Ami Agrawal
NRC/RGN-IV/DORS/PBB
To: Reasoner C
Wolf Creek
Sigel C
References
IR 2025003
Download: ML25345A432 (0)


Text

December 15, 2025

SUBJECT:

WOLF CREEK GENERATING STATION - INTEGRATED INSPECTION REPORT 05000482/2025003

Dear Cleve Reasoner:

On September 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Wolf Creek Generating Station. On November 18, 2025, the NRC inspectors discussed the results of this inspection with Eric Carlson, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

Due to the temporary cessation of government operations, which commenced on October 1, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations.

However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the Regional Offices an extension on the issuance of the calendar year 2025 inspection reports that should have been issued by November 13, 2025, to December 31, 2025. The NRC resumed the routine cycle of issuing inspection reports on November 13, 2025.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be Severity Level IV is documented in this report. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Wolf Creek Generating Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Ami N. Agrawal, Chief Reactor Projects Branch B Division of Operating Reactor Safety Docket No. 05000482 License No. NPF-42

Enclosure:

As stated

Inspection Report

Docket Number:

05000482

License Number:

NPF-42

Report Number:

05000482/2025003

Enterprise Identifier:

I-2025-003-0005

Licensee:

Wolf Creek Nuclear Operating Corp.

Facility:

Wolf Creek Generating Station

Location:

Burlington, KS

Inspection Dates:

July 1, 2025, to September 30, 2025

Inspectors:

C. Henderson, Senior Resident Inspector

C. Sigel, Resident Inspector

Approved By:

Ami N. Agrawal, Chief

Reactor Projects Branch B

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Wolf Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71114.0

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Wolf Creek Generating Station began the inspection period at full power. On September 23, 2025, the unit commenced power coast down for refueling outage 27, which was scheduled to start on October 2,

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)train B residual heat removal system on July 14, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)switchboard and battery rooms 2 and 4, fire area C-15, on July 16, 2025 (2)circulatory water and service water building, fire area CW/SW, on July 16, 2025 (3)upper cable spreading room, fire area C-22, on July 22, 2025 (4)reactor coolant pump A seal chiller temporary modification, fire areas A-8, A-12, and A-25, on July 31, 2025

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered between July 14, 2025, and September 9, 2025.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the annual dynamic exam for licensed operator requalification on July 29, 2025, and just-in-time training for reactor shutdown for refueling outage 27 on September 15, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1)essential service water and service water system maintenance effectiveness review on September 30, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)rod control logic cabinet power supply failure emergent work and risk review on July 16, 2025 (2)refueling outage 27 schedule and risk assessment review on September 18, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)train A motor-driven auxiliary feedwater pump outboard seal leak off degraded trend operability determination on July 17, 2025 (2)containment spray and centrifugal charging pump room cooler operability determination on July 21, 2025 (3)emergency boration path during planned maintenance of motor-operated valve BGHV8104 operability determination on August 21, 2025 (4)train A offsite circuit and component cooling water system with two pumps running for normal operation operability determination on August 22, 2025

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1)rod control power supply temporary modification for a failed power supply on July 18, 2025 (2)temporary chiller for reactor coolant pump A seal injection on August 7, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (3 Samples)

(1)train B control room air conditioning system technical specification equipment outage post-maintenance testing on August 29, 2025 (2)train B control room emergency ventilation system technical specification equipment outage post-maintenance testing on September 30, 2025 (3)emergency diesel generator A technical specification equipment outage post-maintenance testing on September 30, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1)emergency boration and alternate boration paths on August 14, 2025

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (2 Samples)

The inspectors evaluated:

(1)licensed operator response to a natural event and loss of service water and essential service water on August 6, 2025 (2)licensed operator response to an independent spent fuel storage facility event on August 13,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures Sample (IP Section 02.04)===

(1) July 1, 2024, through June 30, 2025

MS06: Emergency AC Power Systems (IP Section 02.05) (1 Sample)

(1) July 1, 2024, through June 30, 2025

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)off normal procedure for loss of safety-related inverters

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71114.04 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Paragraph 50.54(q)(3) of 10 CFR states, in part, the licensee may make changes to its emergency plan without NRC approval only if the licensee performs and retains an analysis demonstrating that the changes do not reduce the effectiveness of the plan. Contrary to the above, Wolf Creek made changes to its emergency plan without NRC approval but failed to perform and retain an analysis demonstrating that the changes do not reduce the effectiveness of the plan. Specifically, Procedure APF 06-002-02, "Emergency Action Level Technical Bases," Revision 3, was put into effect December 4, 2024, and a report of the changes was made to the NRC on December 12, 2024. Additional changes were added to Procedure APF 06-002-02 which had not been evaluated to ensure that they do not reduce the effectiveness of the plan and were not on the report of the changes made to the NRC.

The inspectors determined that changes to Procedure APF 06-02-002 did not reduce the effectiveness of the emergency plan.

Significance/Severity: Severity Level IV. Using the NRC Enforcement Policy, dated August 23, 2024, Section 6.6.d.1, because it involves the licensees ability to meet or implement a regulatory requirement not related to assessment or notification such that the effectiveness of the emergency plan is reduced.

Corrective Action References: Condition Report

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On November 18, 2025, the inspectors presented the integrated inspection results to Eric Carlson, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Condition Report

(CR)

10042607

71111.04

Procedures

CKL EJ-120

RHR System Lineup

47A

Calculations

XX-X-004

Combustible Fire Loading for Each Room in the Various Fire

Areas at WCNOC

Corrective Action

Documents

Condition Report

(CR)

10042302, 10042589

Drawings

KD-7496

One Line Diagram

E-1F9905

Fire Hazard Analysis

PT115374

Scaffolds Blocking Spray Pattern On Aux 2000 Hallways

PT116227

Fire Permit

PT116616

Breach GLD0098 for Temp A RCP Cooling

PT116621

Combustible Materials to Support TMO 25-003-BG

WCNOC-PSA-

067

Internal Fire - Qualitative Screening, Quantitative Screening

and Quantification Notebook

Miscellaneous

WCNOC-PSA-

076

Wolf Creek Generating Station PRA Internal Fire -

Qualitative Screening, Quantitative Screening and

Quantification Notebook

ALR KC-888

Fire Protection Panel KC-008 Alarm Response

AP 10-102

Control of Combustible Materials

AP 10-103

Fire Protection Impairment Control

AP 10-104

Breach Authorization

AP 10-106

Fire Preplans

OFN KC-016

Fire Response

SYS FP-012

Operation of the CWSH Fire Protection Panel

71111.05

Procedures

WCRE-35

Boundary Matrix

Corrective Action

Documents

Condition Report

(CR)

10039173, 10039177, 10041227, 10041250, 10041364,

10042465

71111.12

Corrective Action

Documents

Resulting from

Inspection

Condition Report

(CR)

10041810

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

M-0022

P&ID Plant Service Water System (WS)

M-12EA01

Piping and Instrumentation Diagram Service Water System

M-12EA02

Piping and Instrumentation Diagram Service Water System

M-12EF01

Piping Instrumentation Diagram Essential Svc Water System

Drawings

M-12EF02

Piping and Instrumentation Diagram Essential Service Water

System

Procedures

ALR 00-008B

Serv Wtr Press HI LO

18A

Corrective Action

Documents

Condition Report

(CR)

10042383, 10043305, 10043310, 10043341, 10043602,

10043606, 10043652

Miscellaneous

ODMI 2025-02

Rod Control Logic Cabinet Power Supply Failure

ALR 00-081A

Two/More Rods at Bottom

AP 22B-001

Outage Risk Management

BD-EMG E-0

Reactor Trip or Safety Injection

EMG E-0

Reactor Trip or Safety Injection

EMG E-1

Loss of Reactor or Secondary Coolant

2A

EMG E-2

Faulted Steam Generator Isolation

EMG ES-03

SI Termination

OFN SF-011

Realignment of Dropped, Misaligned Rod(s) and Rod Control

Malfunctions

STS IC-740A

RHR Switchover to Recirc Sump Test - Train A

STS PE-154

LLRT Valve Lineup for Penetration 54

71111.13

Procedures

SYS NN-332

Deenergizing NN Buses

AN-07-009

Gothic Model for CCW Pump Room Temperature

GL-03-W

Auxiliary Building HVAC

GL-M-007

Calculate cooling loads in SR pump rooms post LOCA

Calculations

GL-M-007

Calculate Cooling Load in SR Pump Rooms Post LOCA:

1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1401,

1406

Corrective Action

Documents

Condition Report

(CR)

10042197, 10042295, 10043589

71111.15

Corrective Action

Documents

Resulting from

Condition Report

(CR)

10042627, 10043597, 10043600

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

E-13AL08

Schematic Diagram Instrumentation and Alarms (SH 3)

M-12BB01

Piping and Instrumentation Diagram Reactor Coolant System

M-12BB02

Piping and Instrumentation Diagram Reactor Coolant System

M-12BG01

Piping and Instrumentation Diagram Chemical and Volume

Control System

M-12BG02

Piping and Instrumentation Diagram Chemical and Volume

Control System

M-12BG03

Piping and Instrumentation Diagram and Volume Control

System

M-12BG05

Piping and Instrumentation Diagram Chemical and Volume

Control System

Drawings

M-12EM02

Piping and Instrumentation Diagram High Pressure Coolant

Injection System

E-012.2-00124

General Electric Component Cooling Water Pump 700 HP

1185 PRM 4000 V 1.0 SF Model 5K821167C31

W01

Miscellaneous

ODMI 2025-03

Elevated A RCP #1 Seal Leak Off Rate

ALR 00-129A

MD AFP A Trouble

AP 26C-004

Operability Determinations and Functionality Assessments

BD-EMG E-0

Reactor Trip or Safety Injection

EMG E-0

Reactor Trip or Safety Injection

EMG E-1

Loss of Reactor or Secondary Coolant

2A

EMG ES-02

Reactor Trip Response

EMG ES-04

Natural Circulation Cooldown

24A

OFN BG-009

Emergency Boration

28A

OFN KA-019

Loss of Instrument Air

16A

OFN NB-030

Loss of AC Emergency Bus NB01 (NB02)

STS AL-101

MDAFW Pump A Inservice Pump Test

STS KJ-001A

Integrated D/G and Safeguards Actuation Test - Train A

73A

SYS BG-200

Reactor Makeup Control System Normal Operation

Procedures

SYS EG-120

Component Cooling Water System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

WO 20102, 47048, 48843, 56720, 74952, 83580, 92070,

21-471822-000, 21-476639-000, 22-477654-000,

2-478391-000, 22-479779-000, 22-480431-000,

2-481688-000, 22-482296-000, 22-483479-000

Calculations

SA-90-056

Reactor Protection System/Engineered Safety Features

Actuation System Channel Error Allowances

Corrective Action

Documents

Condition Report

(CR)

10042365, 10042383, 10042915, 10042983

M-12BB03

Piping and Instrumentation Diagram Reactor Coolant System

M-12BG01

Piping and Instrumentation Diagram Chemical and Volume

Control System

Drawings

M-763-00369

Power Supplies, Phase Sense and Multiplex Control

W3

Engineering

Changes

DECP 25-002-SF

Rod Control Temporary Power Supply

M-763-00872

Westinghouse Rod Control System Corrective Maintenance

Guide

W3

ODMI 2025-03

Elevated A RCP #1 Seal Leak Off Rate

PT116615

Temp Mod for RCP A Seal Cooling - 8-inch Pen Seals

P131W1309 and P131W1310

PT116702

Breach Door 13322 to Run a Fill Hose for RCP Seal Temp.

Chiller

WCAP-15360-P

Westinghouse Rod Control System Corrective Maintenance

Guide

Miscellaneous

WCAP-17746-P

Westinghouse Setpoint Methodology as Applied to the Wolf

Creek Generating Station

AP 05-005

Design, Implementation, and Configuration Control of

Modifications

AP 21I-001

Temporary Configuration Changes

16B

OFN BB-005

RCP Malfunctions

TMO 25-003-BG

A RCP #1 Seal Injection Heat Exchanger

Procedures

TMP 25-005

Temporary Chiller for RCP A Seal Injection

0, 1

71111.18

Work Orders

WO 133185, 135106, 135110, 137150, 137153

71111.24

Corrective Action

Documents

Condition Report

(CR)

10042790, 10043792

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Resulting from

Inspection

Condition Report

(CR)

10043582, 10043625

E-13GK10A

Schematic Diagram Control Room Pressurization Fan and

Supply Dampers

M-12BG01

Piping and Instrumentation Diagram Chemical and Volume

Control System

M-12BG02

Piping and Instrumentation Diagram Chemical and Volume

Control System

M-12BG03

Piping and Instrumentation Diagram and Volume Control

System

M-12BG05

Piping and Instrumentation Diagram Chemical and Volume

Control System

M-12EF01

Piping and Instrumentation Diagram Essential SCV Water

System

M-12EM02

Piping and Instrumentation Diagram High Pressure Coolant

Injection System

Drawings

M-12GK01

Piping and Instrumentation Diagram Control Building HVAC

AP 23L-002

Heat Exchanger Program

AP 26C-004

Operability Determinations and Functionality Assessments

CKL EF-120

Essential Service Water Valve, Breaker and Switch Lineup

EMG E-0

Reactor Trip or Safety Injection

EMG E-1

Loss of Reactor or Secondary Coolant

2A

EMG ES-02

Reactor Trip Response

EMG ES-04

Natural Circulation Cooldown

24A

MPE GK-003

Control Room and Class 1E A/C Units Preventive

Maintenance Activity

MPE GK-004

GK Unit Preparation for Work

OFN BG-009

Emergency Boration

28A

STN PE-037B

ESW Train B Heat Exchanger Flow and DP Trending

26B

STS GK-001B

Control Room Emergency Vent System Train B Operability

Test

Procedures

STS GK-002B

Control Room A/C Unit Operability Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SYS BG-200

Reactor Makeup Control System Normal Operation

SYS BG-206

Boric Acid System Operation

WCRE-08

WCGS Fuse List

Work Orders

WO 89326, 102014, 102016, 102022, 128458, 132840, 132455,

340653, 15-404306-016

Miscellaneous

WCNOC-163

Mitigating System Performance Index (MSPI) Basis

Document

AP 22C-003

On-Line Nuclear Safety and Generation Risk Assessment

AP 23M-001

WCGS Maintenance Rule Program

Procedures

SYS KJ-123

Post Maintenance Run of Emergency Diesel Generator A

71151

Work Orders

WO 79662

Corrective Action

Documents

Condition Report

(CR)

10039304

E-11NK01

Class 1E 125V DC System Meter and Relay Diagram

E-11NK02

Class 1E 125V DC System Meter and Relay Diagram

Drawings

E-13AB29

Schematic Diagram Main Steam Isolation Valves Control -

Part 2

ALR 00-025C

NK01 Trouble

13A

ALR 301

24 VDC Class 1E Switchboard NK01

EMG C-0

Loss of All AC Power

46A

EMG E-0

Reactor Trip or Safety Injection

OFN NB-030

Loss of AC Emergency Bus NB01 (NB02)

OFN NK-020

Loss of Vital125 VDC Bus NK01 NK02 NK03 NK04

OFN NK-021

Loss of Vital 120 VAC Instrumentation Bus

31A

SYS GK-122

Manual CRVIS Line-Up

71152A

Procedures

SYS NN-332

Deenergizing NN Buses

18