IR 05000482/1987006

From kanterella
Jump to navigation Jump to search
Insp Rept 50-482/87-06 on 870301-31.Violations Noted:Fire Door 34031 Blocked Open & Unattended W/O Necessary Fire Impairment Permit Form Being Issued.Unresolved Item Identified
ML20206Q652
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 04/15/1987
From: Bruce Bartlett, Boardman J, Cummins J, Hunter D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20206Q630 List:
References
50-482-87-06, 50-482-87-6, NUDOCS 8704220012
Preceding documents:
Download: ML20206Q652 (9)


Text

. _ , _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

,

,.

APPENDIX B U. S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report: 50-482/87-06 LP: NPF-42 Docket: 50-482 Licensee: Wolf Creek Nuclear Operating Corporation (WCNOC)

P. O. Box 411 Burlington, Kansas 66839 Facility Name: Wolf Creek Generating Station (WCGS)

Inspection At: Wolf Creek Site, Coffey County, Burlington, Kansas Inspection Conducted: March 1-31, 1987 Inspectors: . ,. E. Cdmmins, Senior Resident Inspector, Y/ 87

/ Date /

Operations

///

km knYb ~

B. L. Bartlect, Resident Reactor Inspector, v//'//97

Dat'e '

Operations

-

x Ik h R. Boirdman, Reactor Inspector, Date peration Section, Reactor Safety Branch Approved: A w /587 D.7 . Hunter, Chief, Reactor Project

~

Date Section B, Reactor Projects Branch G

f

. - - - . - _ - - _ . . _ ._ _ . _ - - ,- . _ . _ . - . _ . - _ . . - _ - .

- , ,

Inspection Summary Inspection Conducted March 1-31, 1987 (Report 50-482/87-06)

Areas Inspected: Routine, unannounced inspection including _ plant status, operational. safety verification, monthly surveillance observation, monthly maintenance observation, onsite event followup, corrective action, and licensee event report Results: Within the seven areas inspected, one violation was identified (fire door blocked open, paragraph 4). One unresolved item is identified in paragraph ,

)

i l

l

..,1 ,

e 3 '

DETAILS Persons Contacted Principal Licensee Personnel

  • G. D. Boyer, Plant Manager 0. L. Maynard, Manager of Licensing
  • C. M. Estes, Superintendent of Operations

.

M. D. Rich, Superintendent of Maintenance

  • M. G. Williams, Superintendent of Regulatory, Quality, and Administrative Services W. J. Rudolph, QA Manager-WCGS ,
  • A. A. Freitag, Manager, Nuclear Plant Engineering-WCGS '

M. Nichols, Plant Support Superintendent

  • K. Peterson, Licensing
  • G. Pendergrass, Licensing
  • M. Lindsay, Supervisor Quality Systems C. J. Hoch, QA Technologist The NRC inspectors also contacted other members of the licensee's staff during the inspection period to discuss identified issue * Denotes those personnel in attendance at the exit meeting held on April 1, 198 . Plant Status The plant operated in Mode 1 during this inspection perio . Followup of Previously NRC Identified Items (Closed) Violation (482/8608-03): Failure to Adequately Perform TS Surveillance Requiremen This violation identified a situation where the stroke distance on two valves was adjusted improperly to meet the stroke time requirements. The NRC inspector reviewed the following documents to verify that the valve stroke distance was corrected and that no other valves had been modified in the same manner: WCGS. Internal Operations Program Deficiency 86-02, Plant Modification Request 01669, Work Request (WR) 01694-86, and Engineering Evaluation Request 86-AL-01. This violation is close r

,

  • \

. o (i 4 *

(Closed) Open Item (482/8605-02): Essential Service Water Inside Auxiliary Feedwater Syste i This open item was being.used to track the licensee's actions following the inadvertent introduction of ' essential service water into portions of the auxiliary feedwater system (AFW). The licensee flushed the AFW system and during the first refueling outage all steam generat]rs were sludge lanced. This open item is close (Closed) Violation (482/8613-02): Data Not Recorded On a Work Request (WR) As Require +:

This violation concerned a completed WR which did not have all the data ,

recorded that was required. The NRC inspector verified that the violation '

had been placed in the electrical and mechanical maintenance required reading program. Mechanical maintenance had completed the required -

reading, while electrical maintenance was nearly finished with the required reading. This violation is close . Operational Safety Verification The NRC inspectors verified that the facility is being operated safely and in conformance with regulatory requirements by direct observation of licensee facilities, tours of the facility, interviews and discussions with licensee personnel, independent verification of safety system status and limiting conditions for operations, and reviewing facility record The NRC inspectors, by observation of randomly selected activities and interview of personnel verified that physical security, radiation protection, and fire protection activities were controlle By observing accessible components for correct valve position and electrical breaker position, and by observing control room indication, the NRC inspectors confirmed the operability of the safety injection syste The NRC inspectors also visually inspected safety components for leakage, physical damage, and otner 1mpairments that could prevent them from performing their designed function Selected NRC inspector observations are discussed below:

On March 25, 1987, during a routine tour of the control room, the NRC inspector reviewed three Wolf Creek Work Request (WR) that had been written on containment isolation valves. The WRs were on Valves ~

BG HV-8105, GT HZ-6 and LF FV-96 and were written to inspect and repair, as necessary, valve internals during the next refueling outage. Retest instructions were written to perform local leak rate tests (LLRT). Upon questioning Results Engineering personnel, the NRC inspector determined that the valves had exhibited some leakage s during the last LLRT, but that the leakage was within acceptance criteria and that the maintenance was to be performed as a precautio .

,. .. c

&

The licensee stated that an 'as-found' LLRT would not be performed prior to maintenance. The 10 CFR Part 50,_ Appendix J, section II requirements state. in part, "Each valve to be tested shall be closed by normal operation and without any preliminary exercising or adjustments '. . . ." The NRC inspector informed the licensee that in his opinion Section III.c required that the valves be tested in the

'as-found' condition and that a LLRT should be performed prior to valve internal maintenance. Pending further review, this item will remain unresolved (482/8706-02).

On March 4, 1987, during a routine tour of the 2016 ft. elevation of the control building, the NRC inspector observed that TS Fire Door

,

34031~had an air' hose running through it, blocking it open and thereby preventing it from performing its design function. After checking the surrounding area and not finding any workers, the NRC inspector called the control room supervisor operator (S0). The SO

-

,

stated that'no fire impairment permit had been issued for Door 3403 '

As the NRC inspector was leaving the area, a worker was seen adjusting the air hose. . Upon questioning, the worker stated he had

i '

blocked the door open with his air hose in order to reach the only air connection on that floor and that he had not initiated an 1 impairment permit. This failure to get a fire impairment permit as required by plant procedures is an apparent violation (482/8706-01).

fc 5. Monthly Surveillance Observation The NRC inspectors observed selected portions of the performance of s surveillance testing and/or reviewed completed surveillance test procedures to verify that surveillance activities were performed in accordance with TS requirements and administrative procedures. The NRC inspectors considered the following elements while inspecting surveillance

. 11 activities:

o Testing was being accomplished by qualified personnel in accordance with an approved procedure i o The surveillance procedure conformed to TS requirements

, o Required test instrumentation was calibrated o Technical Speciffcation limiting conditions for operation (LCO) were

-

satisfied O o Test data was accurate and complete. Where appropriate, the NRC inspectors performed independent calculations of selected test data to verify their accuracy

~

.

o The performance of the surveillance procedure conformed to applicable

'

administrative procedures

,

--% ., ,.

_ d w

..

o lhe surveillance was performed within the required frequency and the test results met the required limit Surveillances witnessed and/or reviewed by the NRC inspectors are listed below:

o STS BG-001, Revision 3, " Boron Injection Flow Path Verification,"

performed on December 27, 1986 o STS BG-003, Revision 3, '"Boration System Flow Rate Verification,"

performed on October 17, 1986 No violations or deviations were identifie . Monthly Maintenance Observation The NRC inspector observed maintenance activities performed on safety-related systems and components to verify that these activities were conducted in accordance with approved procedures, Technical Specifications, and applicable industry codes and standards. The following elements were considered by the NRC inspector during the

, observation and/or review of the maintenance activities:

o LCOs were met and, where applicable, redundant components were operable o Activities complied with adequate administrative controls o Where required, adequate, approved, and up-to-date procedures were used o Craftsmen were qualified to accomplish the designated task and technical expertise (i.e., engineering, health physics, operations)

was made available when appropriate o Replacement parts and materials being used were properly certified o Required radiological controls were implemented o Fire prevention controls were implemented where appropriate o Required alignments and surveillances to verify post maintenance operability were performed o Quality control hold points and/or checklists were used when appropriate and quality control personnel observed designated work activities Selected portions of the maintenance activities accomplished on the work requests listed below were observed and related documentation reviewed by the NRC inspector:

. - . - __ -

.. -- ..-

. _. __

  • .:.

.

o WR 52341-86,." Annual Maintenance Of Para Blade Isolation Dampers" o "WR 00727-87, " Para Blade Isolation Damper GGD-019" No violations or deviations were identified.

2 Onsite Event Followup The NRC inspector performed onsite followup of a nonemergency event that occurred during this report period. The NRC inspector reviewed control

, room logs and discussed the event with cognizant personnel. The NRC

' inspector verified the licensee had responded to the event in accordance with procedures and had notified the NRC and other agencies as required in ,

,

a timely fashion. An engineered safety feature actuation that occurred F during the. report period is listed in the table below. The NRC inspector

! will review the LER for this event and will report any findings in a

, subsequent NRC inspection report.

'

Date Event Plant Status Cause 3/09/87 CRVIS* Mode 1 Spurious spike i * Control Room Ventilation Isolation System No violations or deviations were identifie . Corrective ~ Action The NRC inspector discussed with licensee personnel the corrective action aspects of licensee management systems and procedure No violations or deviations were identifie . Review of Licensee Event Report (LER)

>

'

During this inspection period, the NRC inspectors performed followup on Wolf Creek LERs. The LERs were reviewed to ensure:

o Corrective action stated in the report has been properly completed or work is in progres o Response to the event was adequat o Response to the event met license conditions, commitments, or other applicable regulatory requirement o The information contained in the report satisfied applicable reporting requirements, o Generic issues were identifie ,

._

y ;. . . .

.

The LERs discussed below were reviewed and closed:

LER 482/86-057: Unplanned Engineered Safety Features Actuation During Surveillance Testing, ihisLERreportedaneventwherean.unplannedTrainAandB-fuelbuilding ventilation isolation signal (FBVIS) and Train A control room ~ ventilation isolation signal (CRVIS).were initiated because of.the presence of a tri signal from Radiation Monitor GG RE-27. The trip signal was generated by-the simultaneous. performance of two surveillance tests and a personnel-error in removing GG RE-27 from the bypass condition. The LER was made required reading for operating personne LER-482/86-053: Delay In Establishing Required Fire Watch For Fire Protection Impairmen This LER reported an event where the shift supervisor (SS) issued an impairment control permit to establish an hourly fire watch patrol of an auxiliary feedwater alternate supply valve to compensate for the removal of the fire barrier enclosure around the valve, but failed to notify the fire watch patrol to add the area to their watch. The LER was made required reading for operating personne LER 482/86-050: TS Violation Caused By Incomplete' Closure Of Fire Doo '

This LER reported an event where an NRC inspector on a routine plant tour discovered a fire door had been blocked open and unattended. . It was later determined that contractor personnel had been holding the door open for ventilation while cleaning up a charcoal spill, but on leaving the area for shift turnover had left the door open. Discussions were held with the involved personnel and their foreman emphasized the importance of TS fire barrier In addition, TS fire doors have been posted.

j 10. Unresolved Item Unresolved items are ir.atters about which more information is required in order to ascertain whether they are acceptable items, items of noncompliance, or deviations. An unresolved item disclosed during the ~

'

inspection is discussed in paragraph 4.

i i

11. Exit Meeting i

4 The NRC inspectors met with licensee personnel to discuss the scope and j findings of this inspection on April 1,1987. The NRC inspectors also

attended entrance / exit meetings of the NRC region-based inspectors

'

identified below:

,

l l

_ _ _ _ _. _ _ ,_,_._ _._.. _ _ _ -. _ . _ __ _ _ . _ _ ..._. _ ._

. . ~ _ ~. -

..-..,.

i 9-

'

Inspection Lea Area Inspection

!

Period Inspector Inspecte Report N /02-06/87 B. Nicholas Transportation 87-08 and Solid Rad-waste Activities 03/02-06/87 J. Kelly Security 87-07 03/16-17/87' J. Boardman Corrective Action 87-06 Program

,

i i

4 i

i

-

t

. . . - , , - - . ,,- - - ..._ ,,,. - , - ..,,..-, --,_ ..., . - , ,-.. .- ..-- ,.., ...-,.. - - -- .. - ,_..-. - -- - _