IR 05000424/2020003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000424/2020003 and 05000425/2020003
ML20318A004
Person / Time
Site: Vogtle  
Issue date: 11/13/2020
From: Alan Blamey
NRC/RGN-II/DRP/RPB2
To: Gayheart C
Southern Nuclear Operating Co
References
IR 2020003
Download: ML20318A004 (27)


Text

November 13, 2020

SUBJECT:

VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 & 2 - INTEGRATED INSPECTION REPORT 05000424/2020003 AND 05000425/2020003

Dear Ms. Gayheart:

On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Vogtle Electric Generating Plant, Units 1 & 2. On October 22, 2020, the NRC inspectors discussed the results of this inspection with Mr. Drayton Pitts and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Vogtle Electric Generating Plant, Units 1 & 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Alan J. Blamey, Chief Reactor Projects Branch 2 Division of Reactor Projects

Docket Nos. 05000424 and 05000425 License Nos. NPF-68 and NPF-81

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000424 and 05000425

License Numbers:

NPF-68 and NPF-81

Report Numbers:

05000424/2020003 and 05000425/2020003

Enterprise Identifier: I-2020-003-0050

Licensee:

Southern Nuclear Operating Co., Inc.

Facility:

Vogtle Electric Generating Plant, Units 1 & 2

Location:

Waynesboro, GA

Inspection Dates:

July 1, 2020 to September 30, 2020

Inspectors:

A. Beasten, PhD, Acting Senior Resident Inspector

P. Cooper, Reactor Inspector

S. Downey, Senior Reactor Inspector

W. Pursley, Health Physicist

C. Safouri, Resident Inspector

S. Temple, Resident Inspector

Approved By:

Alan J. Blamey, Chief

Reactor Projects Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Vogtle Electric Generating Plant, Units 1

& 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71124.0

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000425/2019-003-00 LER 2019-003-00 for Vogtle Electric Generating Plant,

Unit 2, Transformer Deenergization Results in Emergency Diesel Generator and Auxiliary Feedwater Systems Starting 71153 Closed

PLANT STATUS

Unit 1 operated at or near Rated Thermal Power (RTP) for the entire inspection period.

Unit 2 operated at or near RTP until the unit was shutdown for planned refueling outage cycle 21 (2R21) on August 16, 2020. The unit was returned to RTP on September 14, 2020 and remained at or near RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin teleworking and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted. As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site.

The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 Train 'B' Emergency Diesel Generator (EDG) and associated equipment during 2A EDG maintenance outage, on July 21, 2020.
(2) Unit 2 Train 'B' Residual Heat Removal (RHR) system during Train 'A' RHR system outage, on July 29, 2020.
(3) Unit 2 Train 'A' and 'B' RHR for Shutdown Cooling alignment during lowered inventory, on August 19, 2020.
(4) Unit 1/2 Spent Fuel Pool Cooling while Unit 2 was defueled, on August 24, 2020.
(5) Restoration of Unit 2 Train 'B' of Engineered Safety Features Actuation System (ESFAS) following ESFAS testing, on September 2, 2020.

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 Train 'B' EDG system on July 27, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zones 36/37, Unit 1 Trains 'A' and 'B' Component Cooling Water Pump Rooms, on July 14, 2020.
(2) Fire Zones 144/162/164, Unit 2 Train 'B' EDG and Cable Tunnel 2T4B, on July 22, 2020.
(3) Fire Zones 140A/B/C/E, Unit 2 Containment Building, on August 20, 2020.
(4) Fire Zones 57A/81A/125B/126B/153/178/180, Unit 2 Control Building and Engineered Safety Features (ESF) Chiller Rooms, on September 2, 2020.
(5) Fire Zones 155/156/157A/157B, Unit 2 Auxiliary Feedwater (AFW) pump houses, on September 15, 2020.
(6) Fire Zones 91/92/97/98/103, Unit 1 Control Building Level A and 4.16 kV switchgear and remote shutdown rooms, on September 16, 2020.

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit 2 Train 'B' EDG Jacket Water Heat Exchanger, on August 25, 2020.

===71111.07T - Heat Sink Performance

Triennial Review (IP Section 03.02)===

(1) Unit 2: Piping Penetration Cooler (21561E7002000), Cooled by Service Water - Section 02.02b
(2) Unit 1: Component Cooling Water 'B' Heat Exchanger (11203E4002), Cooled by Service Water - Section 02.02b
(3) Unit 2: Nuclear Service Cooling Water Pump Motor Cooler (21202P4006M01),

Cooled by Service Water - Section 02.02b

(4) Unit 1: Residual Heat Removal B Heat Exchanger (11205E6002), Closed Loop Intermediate System - Section 02.02c

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors evaluated pressurized water reactor non-destructive testing by reviewing the following examinations from September 14 to September 18, 2020:

1. Liquid Penetrant Examination

a. Weld 683246-W2, Containment Spray Pump A valve replacement weld, ASME Class 2. This included a review of associated welding activities.

b. Weld 683246-W3, Containment Spray Pump A valve replacement weld, ASME Class 2. This included a review of associated welding activities.

2. Magnetic Particle Examination

a. Weld 21201-B6-002-W26, 6 Auxiliary Feedwater nozzle to shell weld, ASME Class 2

3. Ultrasonic Examination

a. Weld 21201-B6-002-W26, 6 Auxiliary Feedwater nozzle to shell weld, ASME Class 2.

b. Weld 21201-V6-002-W01, Pressurizer upper head to shell weld, ASME Class 1. This included the review of relevant indications that the licensee analytically evaluated and accepted for continued service.

c. Weld 21204-246-32-RB, 1.5 valve to pipe weld in Safety Injection Cold Leg Loop 4, ASME Class 1.

d. Weld 21204-245-34-RB, 3 reducer to branch connection weld in Safety Injection Cold Leg Loop 3, ASME Class 1

4. Visual Examination

a. Bare Metal Visual of Reactor Vessel Head (per Code Case N-729-6)b. VT-2 (System Leakage) of Reactor Coolant Pump 1 Seal Injection from Penetration 54 to Valve 006

The inspectors also evaluated the licensee's boric acid corrosion control program performance.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during the reactor shutdown from Mode 1 to Mode 4 to commence the Unit 2 Refueling Outage on August 16, 2020.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a licensed operator annual requalification exam scenario involving a faulted and ruptured Steam Generator and various transients, on September 22, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Effectiveness of lubrication program to ensure reliability and operability of safety-related equipment for Units 1 and 2, on September 23, 2020.
(2) Unit 1 Seismic Gap and Hazard Barrier Seals for Cable Tunnel Rooms 1T4A and 1T4B, on September 30, 2020.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed;

(1) Unit 2 elevated risk due to Train 'B' Nuclear Service Cooling Water (NSCW) being inoperable during seismic restraint modifications, on July 15, 2020.
(2) Unit 2 elevated risk due to Train 'A' EDG major outage with use of Risk Informed Completion Time, on July 20, 2020.
(3) Unit 2 high risk activity for new fuel storage in the Spent Fuel Pool, on August 6, 2020.
(4) Unit 2 elevated shutdown risk, Yellow, for core cooling and Reactor Coolant System (RCS) inventory due to lowered inventory in the RCS, and for Electrical DC Power due to 2D batteries being out of service during lowered inventory, on August 19, 2020.
(5) Unit 2 high risk activity for fuel offloading during 2R21 Refueling Outage, on August 21, 2020.
(6) Unit 1 elevated risk due to swapping from Train 'A' Stator Cooling Water (SCW) Pump to Train 'B' SCW pump for troubleshooting, on September 24, 2020.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (9 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2 Train 'B' RHR Operable but Degraded Non-conforming due to oil loss, on July 28, 2020.
(2) Unit 2 Main Feedwater Regulating Valve solenoid valves exceeding Environmental Qualification qualified life, on August 4, 2020.
(3) Unit 1 Train 'A' RHR Pump Motor Cooler Pressure Relief Valve, 1PSV11748, exceeding testing requirements, on August 11, 2020.
(4) Unit 1 Train 'B' NSCW pump motor cooling outlet spool flange surface outside of procedure limits, on September 14, 2020.
(5) Unit 1 Train 'A' ESF Chiller compressor oil temperature found high, on September 15, 2020.
(6) Part 21 Evaluation for Framatome Letter LTR19061 (D26 Relays Only), on September 16, 2020.
(7) Unit 2 Electrical Containment Penetration #64 leaking by, on September 17, 2020.
(8) Unit 1 Plant Ventilation Radiation Monitor, 1-RE-12442, functionality challenges while 1-RE-12444 was out of service, on September 17, 2020.
(9) Unit 1 Train 'A' EDG broken fuel rail hold-down bolt, on September 21, 2020.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 2 Solid State Protection System (SSPS) Bridging Strategy, on August 27, 2020.
(2) Unit 2 Single Point Vulnerabilities (SPVs) reduction from Main Steam Isolation Valve (MSIV) control circuits, on September 17, 2020.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (8 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1)

===14980A-2, Unit 2 Train 'A' EDG operability run, following extended maintenance outage, on July 27, 2020.

(2) Functional Test following Unit 2 Train 'A' RHR system outage, on July 29, 2020.
(3) Unit 2 Train 'A' and 'B' SSPS General Warning Monitor Circuit and Power Supplies functional testing after Modifications, on August 26, 2020.
(4) Leak checks following Unit 2 Train 'B' EDG Jacket Water Heat Exchanger inspection, on August 28, 2020.
(5) Work Order (WO) SNC1115784, for replacement activities on Unit 1 Loop 4 Delta T instrument card, on September 2, 2020.
(6) Unit 2 Main Generator Protective Relay Replacement Functional Test, on September 24, 2020.
(7) Operation of Unit 1 Train 'B' NSCW Pump 2 following planned maintenance, on September 29, 2020.
(8) Functional Test for Train 'A' MSIV following reduction of SPVs from control circuits, on September 30, 2020.

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01)===

(1) The inspectors evaluated Unit 2 refueling outage (2R21) activities from August 16, 2020 to September 11, 2020.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1)

===28914-C, Unit 1 Group 'A' Pressurizer Heater Capacity Test, on July 31, 2020.

(2)14721C-2, Unit 2 Emergency Core Cooling System Subsystem Flow Balance and Check valve Refueling Inservice Test, on August 19, 2020.

(3)14667-2, Unit 2 Train 'B' Diesel Generator and ESFAS Test, on September 1, 2020.

(4)14244-2, Unit 2 Main Turbine Safety Injection / P-14 or P-4 Final Trip Device Actuation Test, on September 11, 2020.

Inservice Testing (IP Section 03.01)===

(1) Unit 2 Train 'B' Motor Driven AFW Pump Inservice Test and Response Time Test, on July 21, 2020.

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Containment Penetration No. 80 Containment Service Air Supply Line Local Leak Rate Test, on August 12, 2020.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Licensed Operator Requalification Training exam scenario involving a Reactor Coolant Pump seal failure and various system malfunctions, on September 21,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated radiological protection-related instructions to plant workers.

Contamination and Radioactive Material Control (IP Section 03.03) (3 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) Observed workers exiting the RCA at Unit 2 during a refueling outage.
(2) Observed licensee surveys of potentially contaminated material leaving the RCA during the Unit 2 refueling outage.
(3) Evaluated reasons for differences in personnel contamination monitoring equipment count times between plant RCA exit and the Unit 2 personnel hatch.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (5 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) Unit 2 Reactor Coolant Pump Motor Removal under RWP #20-2200. involved work in area with potential for airborne radioactivity.
(2) Unit 2 Reactor Coolant Pump Seal Removals under RWP #20-2203 involving a breach of the RCS system and potential for high contamination levels and potential alpha level II controls.
(3) Unit 2 Reactor Coolant Pump Impeller Removal under RWP #20-2203 involving high potential airborne risks, expected dose rates up to 7 Rem per hour and large dose rate gradients.
(4) U2 RP entry into Unit 2 Regenerative Heat Exchanger Room for Pre-Job Survey under RWP #20-2108 involving RP surveys in Locked High Radiation Areas with unknown dose rates prior to entry.
(5) Decon of Unit 2 Reactor Coolant Pump Housing Flange under RWP #20-2109 involving highly contaminated surfaces.

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) High Radiation Area controls during the Unit 2 Reactor Coolant Pump Impeller Removal
(2) Very High Radiation Area controls for the Unit 2 Spent Fuel Pool Transfer Canal
(3) Unit 2 Chemical Volume Control System Letdown Heat Exchanger Room.

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS07: High Pressure Injection Systems (IP Section 02.06)===

(1) Unit 1 (July 1, 2019 - June 30, 2020)
(2) Unit 2 (July 1, 2019 - June 30, 2020)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (July 1, 2019 - June 30, 2020)
(2) Unit 2 (July 1, 2019 - June 30, 2020)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2019 - June 30, 2020)
(2) Unit 2 (July 1, 2019 - June 30, 2020)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) 09/30/2019 to 06/01/2020

===71153 - Followup of Events and Notices of Enforcement Discretion

Event Report (IP Section 03.02)===

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000425/2019-003-00, Transformer deenergization results in Emergency Diesel Generator and Auxiliary Feedwater Systems Starting (ADAMS Accession No.

ML19338C617). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements.

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71124.01 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Licensee Identified Violation of 10CFR 20.1501(a)(1) which requires in part, surveys necessary to evaluate the magnitude and extent of radiation levels. In addition, 10CFR20.1902 requires posting of areas as a High Radiation Area (HRA) where dose rates exceed 100 mrem in one hour at 30 centimeters. Contrary to these requirements, on September 1, 2020, following a primary resin sluice on Unit 2, a down-posting survey was performed that failed to fully evaluate the magnitude and extent of radiation levels and failed to identify that HRA conditions still existed. Specifically, room 2-AB-86-Mezzanine which contained a portion of the resin line was not surveyed. On September 18, during a routine RP survey, dose rates as high as 8000 mrem per hour contact and 400 mrem per hour at 30 centimeters were discovered on this portion of the resin line, however the room was no longer posted in accordance with 10CFR1902.

Significance/Severity: Green.

Corrective Action References: CR10739998

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 22, 2020, the inspectors presented the integrated inspection results to Mr.

Drayton Pitts and other members of the licensee staff.

  • On July 17, 2020, the inspectors presented the Triennial Heat Sink Inspection results to Drayton Pitts, Site Vice President and other members of the licensee staff.
  • On September 1, 2020, the inspectors presented the RP Routine Baseline Inspection 2020003 Exit inspection results to Drayton Pitts, Site Vice President and other members of the licensee staff.
  • On September 18, 2020, the inspectors presented the Baseline ISI Exit Meeting inspection results to Drayton Pitts, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Drawings

1X4DB130

P&I Diagram - Spent Fuel Cooling & Purification

System - System No. 1213

50.0

71111.04

Drawings

2X4DB121

P&I Diagram - Safety Injection System - System No.

204

50.0

71111.04

Drawings

2X4DB122

P&I Diagram - Residual Heat Removal - System No.

205

54.0

71111.04

Drawings

2X4DB130

P&I Diagram - Spent Fuel Cooling & Purification

System - System No. 1213

2.0

71111.04

Drawings

2X4DB170-2

P&I Diagram Diesel Generator System Train B

System No. 2403

45.0

71111.04

Miscellaneous

10032-C

Shutdown Defense-In-Depth Assessment

08/24/2020

71111.04

Procedures

11145-2

Diesel Generator Alignment

14.1

71111.04

Procedures

NMP-OS-010

Protected Train/Division and Protected Equipment

Program

8.1

71111.04

Procedures

NMP-OS-010-003

Vogtle Protected Equipment Logs

11.0

71111.05

Corrective Action

Documents

10574691, 10732376

71111.05

Fire Plans

2736-1

Zone 36 - Auxiliary Building Level A Fire Fighting

Preplan

5.0

71111.05

Fire Plans

2737-1

Zone 37 - Auxiliary Building Level A Fire Fighting

Preplan

5.0

71111.05

Fire Plans

2757A-1

Zone 57A - Control Building - Levels B, A, 1, 2, and 3

Fire Fighting Preplan

4.2

71111.05

Fire Plans

2781A-1

Zone 81A - Control Building - Levels B, A, 1, 2, and 3

Fire Fighting Preplan

5.0

71111.05

Fire Plans

2791-1

Zone 91 - Control Building Level A Fire Fighting

Preplan

4.1

71111.05

Fire Plans

2792-1

Zone 92 - Control Building Level A Fire Fighting

Preplan

3.1

71111.05

Fire Plans

2797-1

Zone 97 - Control Building - Level A Fire Fighting

Preplan

71111.05

Fire Plans

2798-1

Zone 98 - Control Building - Level A Fire Fighting

4.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Preplan

71111.05

Fire Plans

2803-1

Zone 103 - Control Building - Level A Fire Fighting

PrePlan

3.0

71111.05

Fire Plans

2825B-1

Zone 125 B Control Building Level 3 Fire Fighting

Preplan

5.3

71111.05

Fire Plans

2826B-1

Zone 126B - Control Building - Level 3 Fire Fighting

Preplan

3.2

71111.05

Fire Plans

2840A-2

Zone 140A - Containment Building - Levels A, B, 1, 2

and 3 Fire Fighting Preplan

3.1

71111.05

Fire Plans

2840B-2

Zone 140B - Containment Building - Levels A, B, 1, 2

and 3 Fire Fighting Preplan

4.1

71111.05

Fire Plans

2840C-2

Zone 140C - Containment Building - Levels A, B, 1, 2

and 3 Fire Fighting Preplan

2.1

71111.05

Fire Plans

2840E-2

Zone 140E - Containment Building - Levels A, B, 1, 2

and 3 Fire Fighting Preplan

1.1

71111.05

Fire Plans

2844-2

Zone 144 - Diesel Generator Building - Electrical

Tunnel - Train B - Fire Fighting Preplan

2.2

71111.05

Fire Plans

2853-2

Zone 153 - Control Building - Level B Fire Fighting

Preplan

0.2

71111.05

Fire Plans

2855-2

Zone 155 - Auxiliary Feedwater Pumphouse - Train B

Fire Fighting Preplan

0.2

71111.05

Fire Plans

2856-2

Zone 156 - Auxiliary Feedwater Pumphouse Fire

Fighting Preplan

0.2

71111.05

Fire Plans

2857A-2

Zone 157A - Auxiliary Feedwater Pumphouse - Train

C Fire Fighting Preplan

0.2

71111.05

Fire Plans

2857B-2

Zone 157B - Auxiliary Feedwater Pumphouse - Train

C Fire Fighting Preplan

0.2

71111.05

Fire Plans

2862-2

Zone 162 - Diesel Generator Building Fire Fighting

Preplan

1.1

71111.05

Fire Plans

2864-2

Zone 164 - Diesel Generator Building - Train B DFO

Day Tank Fire Fighting Plan

0.2

71111.05

Fire Plans

2878-2

Zone 178 Control Building Level 3 Fire Fighting

Preplan

1.1

71111.05

Fire Plans

2880-2

Zone 180 Control Building Level 3 Fire Fighting

0.2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Preplan

71111.05

Fire Plans

NMP-ES-035-007

Fleet Fire Watch Instruction

5.0

71111.05

Procedures

2040-C

Fire Protection Functionality and LCO Requirements

46.3

71111.05

Work Orders

SNC1114249,

SNC782278,

SNC902691, SNC993922

71111.07A

Procedures

83395-C

Heat Exchanger Testing/Maintenance Program

7.10

71111.07A

Procedures

NMP-ES-012

Heat Exchanger Program

2.0

71111.07A

Work Orders

SNC1013636,

SNC820593

71111.08P

Corrective Action

Documents

Condition Reports (by CR

  1. )

CR10613570, CR10631016, CR10636903,

CR10729805, CR10729936, CR10730672,

CR10730754, CR10733292

71111.08P

Engineering

Evaluations

Corrosion Assessment

Number 1213-2011-009

Boric Acid Corrosion Assessment for Train A Spent

Fuel Pool Heat Exchanger

08/14/2020

71111.08P

Engineering

Evaluations

LTR-SDA-19-018-P

Vogtle Unit 2 Pressurizer top Head to Upper Shell

Weld ASME Section XI Evaluation of As-Found

Indications

Revision 0

71111.08P

Engineering

Evaluations

SNC1115524

Evaluation of V2R21 Reactor Head Inspection

Results

09/03/2020

71111.08P

Miscellaneous

SG-CDMP-20-18

Steam Generator Degradation Review for Vogtle Unit

Cycle 21

Revision 0

71111.08P

NDE Reports

S20V2V045

Visual Examination Report for Vessel Closure Head

Exterior

08/30/2020

71111.08P

Procedures

NMP-ES-019-001

Boric Acid Corrosion Control Program

Implementation

Version 11.1

71111.08P

Procedures

NMP-ES-019-004

Boric Acid Corrosion Control Program - Corrosion

Assessment

Version 5.1

71111.08P

Procedures

NMP-ES-024-202

Visual Examination (VT-2)

Version 7.0

71111.08P

Procedures

NMP-ES-024-208

Visual Examination of Reactor Vessel Head

Penetrations and Base Material

Version 6.3

71111.08P

Procedures

NMP-ES-024-401

Magnetic Particle Examination

Version 12.0

71111.08P

Procedures

NMP-ES-024-501

PDI Generic Procedure for Ultrasonic Examinatiokn

of Austenitic Pipe Welds (Appendix VIII)

Version 7.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08P

Procedures

NMP-ES-024-516

Manual Ultrasonic Examination of Pressure Vessel

Welds (Non-Appendix VIII)

Version 6.0

71111.11Q Procedures

2004-2

Power Operation (Mode 1)

4.1

71111.11Q Procedures

2005-C

Reactor Shutdown to Hot Standby (Mode 2 to Mode

3)

71111.11Q Procedures

2006RFO-2

Unit Cooldown to Cold Shutdown for Refueling

1.7

71111.12

Corrective Action

Documents

23064, 162028, 162032,

395948, 503291, 802581,

841494, 10313228,

10313317, 10315786,

10315787, 10407211,

10407213, 10645149,

10658620, 10659181,

10686716

71111.12

Corrective Action

Documents

Resulting from

Inspection

10658261

71111.12

Drawings

AX2D94V030

Waterstops & Waterproofing General Arrangement

Plan

71111.12

Drawings

AX2D94V031

Waterstops & Waterproofing Sections and Details

Sheet 1

71111.12

Drawings

AX2D94V033

Waterstops & Waterproofing Sections and Details

Sheet 3

71111.12

Procedures

20411-C

Control of Lubricants

16.3, 17,

18.1

71111.12

Procedures

NMP-ES-021

Structural Monitoring Program for the Maintenance

Rule

11.0

71111.12

Procedures

NMP-ES-027

Maintenance Rule Program

10.2

71111.12

Procedures

NMP-ES-074-006

Fleet Lubrication Instruction

4.0

71111.12

Work Orders

SNC1033792,

SNC1057746

71111.13

Corrective Action

Documents

10725636

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.13

Corrective Action

Documents

Resulting from

Inspection

10722710

71111.13

Miscellaneous

Phoenix Risk Profile

07/15/2020

71111.13

Miscellaneous

Protecting Equipment Logs

07/15/2020

71111.13

Miscellaneous

Phoenix Risk Model

07/21/2020

71111.13

Miscellaneous

Plan of the Day

07/20/2020

71111.13

Miscellaneous

V2R21 Defense in Depth Assessment Final Report

71111.13

Miscellaneous

Phoenix Risk Model

07/20/2020

71111.13

Miscellaneous

Plan of the Day

08/06/2020

71111.13

Miscellaneous

10032-C

Shutdown Defense-In-Depth Assessment (Mode 4, 5,

6, 0)

08/21/2020

71111.13

Miscellaneous

VNP-1-20-003

Degraded SCW Pumps ODMI

71111.13

Procedures

10032-C

Outage Risk Assessment Monitoring

71111.13

Procedures

13419-C

Diesel Generator RICT Support

10.3

71111.13

Procedures

NMP-AD-002

Conduct of Problem Solving and Troubleshooting

13.5

71111.13

Procedures

NMP-AD-002-F04

Troubleshooting Log

1.1

71111.13

Procedures

NMP-DP-001-F01

Operational Risk Awareness Form 1 Risk Activity

Evaluation Worksheet

1.0

71111.13

Procedures

NMP-GM-031-003

Risk Management Actions for 10 CFR 50.65(a)(4)

and the Risk Informed Completion Time Program

8.0

71111.13

Procedures

NMP-MA-009

Foreign Material Exclusion Program

15.0

71111.13

Procedures

NMP-MA-009-001

Foreign Material Exclusion Program Requirements

10.0

71111.13

Procedures

NMP-OM-002

Shutdown Risk Management

6.0

71111.13

Procedures

NMP-OS-003

Operational Decision Making Issue Evaluation

Process

10.0

71111.13

Procedures

NMP-OS-010

Protected Train/Division and Protected Equipment

Program

8.1

71111.13

Procedures

NMP-RE-011

Special Nuclear Material Movement

1.0

71111.13

Work Orders

SNC963072

71111.15

Calculations

X4CPS.0075.183

Qualified Life (QL) Extension for ASCO Solenoid

Valves

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Corrective Action

Documents

10714605, 10727375,

10739502, 277403,

10691621, 10693484,

10727332, 10727518,

277066, 277582,

265306, 10646853,

10728167, 10708633,

10704418, 10731746,

10720064, 10732422

71111.15

Engineering

Evaluations

2B RHR leak rate calculation

71111.15

Engineering

Evaluations

2B RHR Motor - Oil Level Trend

71111.15

Miscellaneous

1-2020-3

Standing Order: Actions Required if overpressure

condition (pipe rupture) occurs on NSCW A to RHR A

pump motor cooler due to a failure of the relief valve

1PSV11748 to lift

1.0

71111.15

Miscellaneous

AX4AJ04-20000

Installation, Operation, & Maintenance Manual ESF

Chillers

9.0

71111.15

Miscellaneous

MIS-17-009

Vogtle Electric Generating Plant Fourth 10-Year

Interval Inservice Testing Program

11.0

71111.15

Miscellaneous

MIS-17-027

Vogtle Electric Generating Plant Unit 1 Fourth 10-

Year Interval Valve Inservice Testing Basis

Document

2.0

71111.15

Miscellaneous

SO 2-2020-4

Standing Order - 2B RHR Oil Leak Monitoring Plan

08/01/2020

71111.15

Procedures

11881-2

Unit 2 Auxiliary Building Rounds

64.0

71111.15

Procedures

24965-C

Containment Electrical Penetration Local Leak Rate

Test and Charging Instructions

71111.15

Procedures

34316-C

Operation of DRMS Plant Vent Effluent Monitor (RE-

2442)

71111.15

Procedures

GEN-87

Operator Lubricant Addition List

6.0

71111.15

Procedures

NMP-AD-012

Operability Determinations and Functionality

Assessments

13.3

71111.15

Procedures

NMP-AD-012-GL04

Mission Times

1.1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Procedures

NMP-EP-305-GL03

VEGP Equipment Important to the EP Function

6.2

71111.15

Procedures

NMP-ES-013

Inservice Testing Program

8.1

71111.15

Procedures

NMP-ES-013-006

IST Ten Year Interval Update

2.1

71111.15

Procedures

NMP-ES-013-010

IST Relief Valve Program Development and

Maintenance

1.0

71111.15

Procedures

NMP-ES-016

Environmental Qualification Program

11.1

71111.15

Work Orders

SNC1096401,

SNC1096402,

SNC1096403,

SNC1096404

71111.18

Engineering

Changes

SNC106213450.59

50.59 Evaluation of Eliminate SPVs from MSIV

control circuits for Normally Energized MDR relays

and micro switches

71111.18

Engineering

Changes

SNC1062134COMPACTS Risk Mitigation plan for elimination of SPVs from

MSIV control circuits for Normally Energized MDR

relays and micro switches

71111.18

Engineering

Changes

SNC1062134DCP

Eliminate SPVs from MSIV control circuits for

Normally Energized MDR relays and micro switches

71111.18

Engineering

Changes

SNC1062134WKCOMP

Implementing Work Order for elimination of SPVs

from MSIV control circuits for Normally Energized

MDR relays and micro switches

71111.18

Engineering

Changes

SNC95902550.59

CFR 50.59 Screening: U2 SSPS Bridging

Strategy: Low Margin, Increase UVTA Coil Ckt

Voltage

0.0

71111.18

Engineering

Changes

SNC959025AD

Applicability Determination: U2 SSPS Bridging

Strategy: Low Margin, Increase UVTA Ckt Voltage

1.0

71111.18

Engineering

Changes

SNC959025DCP

U2 SSPS Bridging Strategy

71111.18

Engineering

Changes

SNC959025FFP6

Detailed Fire Protection Program Change Evaluation:

U2 SSPS Bridging Strategy

0.0

71111.18

Engineering

Changes

SNC959025FPP5

Fire Protection Program Impact Screening: U2 SSPS

Bridging Strategy

0.0

71111.18

Engineering

Evaluations

SNC1062134RISK

Risk Assessment Form for elimination of SPVs from

MSIV control circuits for Normally Energized MDR

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

relays and micro switches

71111.18

Miscellaneous

EQ3663

Seismic Qualification Data Summary / Seismic and

Dynamic Qualification Summary

1.0

71111.18

Miscellaneous

EQ3666

Seismic Qualification Data Summary / Seismic and

Dynamic Qualification Summary

1.0

71111.18

Miscellaneous

PWROG-14063-P

SSPS Conceptual General Warning Monitor Circuit

Summary Report

71111.18

Miscellaneous

SNC959025RISK

Design Change/Modification - Risk Assessment

Form: SNC959025

0.0

71111.19

Corrective Action

Documents

10726268, 10730390,

10735813, 10736030,

10736032, 10735143

71111.19

Miscellaneous

DCP SNC959025

Unit 2 SSPS General Warning Monitor Circuit

(GWMC) Site Acceptance Test

1.0

71111.19

Procedures

11885A-2

Diesel Generator 2A Operating Log

5.3

71111.19

Procedures

13150B-1

Train B Nuclear Service Cooling Water System

71111.19

Procedures

14420-2

Solid State Protection System Train A Operability

Test

2.1

71111.19

Procedures

14980A-2

Diesel Generator 2A Operability Test

31.1

71111.19

Procedures

2408-C

7300 Circuit Board Removal, Inspection, Cleaning,

and Reinstallation

44.2

71111.19

Procedures

24813-1

Delta T/T Avg Loop 4 Protection Channel IV 1T-441

Channel Operational Test and Channel Calibration

71111.19

Work Orders

SNC1056311,

SNC1056316,

SNC1060825,

SNC872956DCP,

SNC1070289,

SNC1085621,

SNC1091321,

SNC1091322,

SNC1115784,

SNC928745, SNC931262

71111.22

Corrective Action

10637850, 10722762,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

10729784, 10731967

71111.22

Drawings

1X3D-AA-E01A

One Line Diagram - 480V Switchgear 1NB01 - 1-

1805-S3-B01

15.0

71111.22

Drawings

1X3D-AA-F13A

One Line Diagram - 480V Pressurizer Heater Panels

- 1NBPC, 1NBPB1, 1NBPB2, 1NBPB3

7.0

71111.22

Miscellaneous

NUREG-0737

Clarification of TMI Action Plan Requirements

11/1990

71111.22

Procedures

13430-1

480V AC Non 1E Electrical Distribution System

16.2

71111.22

Procedures

244-2

Main Turbine SI/P-14 or P-4 Final Trip Device

Actuation Test

71111.22

Procedures

14380-2

Containment Penetration No. 80 Containment

Service Air Supply Line Local Leak Rate Test

71111.22

Procedures

14545B-2

Motor Driven Auxiliary Feedwater Pump B Operability

Test

1.2

71111.22

Procedures

14721C-2

ECCS Subsystem Flow Balance and Checkvalve

Refueling Inservice Test

71111.22

Procedures

14807B-2

Train B Motor Driven Auxiliary Feedwater Pump /

Check Valve Inservice and Response Time Test

5.1

71111.22

Procedures

18031-1

Loss of Class 1E Elect Systems

1.2

71111.22

Procedures

19011-1

ES - 1.1 SI Termination

1.1

71111.22

Procedures

28914-C

Pressurizer Heater Capacity Test

71124.01

ALARA Plans

RWP 20-2203

20-2203 Remove and Replace RCP#1 Pump

08/03/2020

71124.01

Corrective Action

Documents

10733187

Key to LHRA lock 02 was lost in containment

08/25/2020

71124.01

Corrective Action

Documents

Resulting from

Inspection

10734162

Relocation of dosimetry due to potential gradient

dose rates not evaluated in accordance with RP

procedural requirements.

08/31/2020

71124.01

Corrective Action

Documents

Resulting from

Inspection

10734865

ALARA plan for the RCP pump replacement did not

discuss contingencies for the pump binding as it did

in 1998

08/31/20

71124.01

Corrective Action

Documents

Resulting from

10734866

Permanent High Radiation Area postings in U2

containment have not been Updated

08/31/20

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

71124.01

Corrective Action

Documents

Resulting from

Inspection

10734869

RP supervisory oversight required for high risk work

may be more effective in central monitoring than at

the job when telemetry and video capabilities are

available.

08/31/20

71124.01

Corrective Action

Documents

Resulting from

Inspection

10734871

Organizational knowledge gap in the appropriate

criteria for relocation of dosimetry since the NISPs

were issued.

08/31/20

71124.01

Procedures

NM-HP-306

Radiological Job Coverage

Version 1.0

71124.01

Procedures

NMP-HP-108

Issuance, Use, and Collection of Personnel

Dosimetry

Version 2.7

71124.01

Procedures

NMP-HP-108-002

Use of EDE (Effective Dose Equivalent)

Methodologies

Version 3.1

71124.01

Procedures

NMP-HP-204

ALARA Planning and Job Review

Version 5.5

71124.01

Procedures

NMP-HP-300

Radiation and Contamination Surveys

Version 5.4

71124.01

Radiation

Surveys

28197

HI_STORM SURFACE DOSE RATES (C) MPC #489

08/17/2019

71124.01

Radiation

Surveys

28198

HI_STORM SURFACE DOSE RATES (C) MPC #489

08/17/2019

71124.01

Radiation

Surveys

28388

HI_STORM SURFACE DOSE RATES (C) MPC #490

08/26/2019

71124.01

Radiation

Surveys

28389

HI_STORM SURFACE DOSE RATES (C) MPC #490

08/26/2019

71124.01

Radiation

Surveys

28946

HI_STORM SURFACE DOSE RATES (C) MPC #544

09/14/2019

71124.01

Radiation

Surveys

28947

HI_STORM SURFACE DOSE RATES (C) MPC #539

09/21/2019

71124.01

Radiation

Surveys

237531

Plant Vogtle Quadrant 4 Elevation 197

08/16/2020

71124.01

Radiation

Surveys

237538

Plant Vogtle Level A Lower Overview (2RXAL)

08/16/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.01

Radiation

Surveys

237856

Plant Vogtle Level A Lower Overview

08/16/2020

71124.01

Radiation

Surveys

238058

Plant Vogtle RCP Motor (2RXAI15)

08/23/2020

71124.01

Radiation

Surveys

238069

RCP #1 Shroud (rev#2) (2RXB5)

08/23/2020

71124.01

Radiation

Surveys

238070

RCP #1 Seal Plate (2RXB9)

08/23/2020

71124.01

Radiation

Surveys

238113

Plant Vogtle Regenerative Heat Exchanger Room

08/24/2020

71124.01

Radiation

Surveys

238263

Reactor Coolant Pump Impeller (1RXA-19)

08/27/2020

71124.01

Radiation

Surveys

2H19

Vogtle Boundary Report from Environmental

Laboratory

07/12/2019 -

2/31/2019

71124.01

Radiation Work

Permits (RWPs)

20-0148

Unit 1 Remove and Replace Pump on RCP#1 and All

Associated Work in Unit 2 Containment

Revision 0

71124.01

Radiation Work

Permits (RWPs)

20-2003

2R21 Refueling Outage Work Activities to Include

CMs/PMs, Surveillance, Calibration and Misc/Support

Work Activities in High Radiation Areas not Covered

Under Other RWPs.

Revision 0

71124.01

Radiation Work

Permits (RWPs)

20-2109

Decon Activities in Locked High Radiation Areas in

U2 CNMT

Revision 0

71124.01

Radiation Work

Permits (RWPs)

20-2202

Remove and Replace RCP #1 Pump to Include All

Associated Work for Assemby and Reassembly in

Unit 2 Containment

Revision 0

71124.01

Radiation Work

Permits (RWPs)

20-2202

Remove and Replace RCP #1 Pump to Include All

Associated Work for Assemby and Reassembly in

Unit 2 Containment

71124.01

Radiation Work

Permits (RWPs)

20-2203

RP Surveys and Job Coverage In Locked High

Radiation Areas in U2 Containment

Revision 0

71124.01

Radiation Work

Permits (RWPs)

20-2505

Under Rx Vessel Work Including DMIMS, Cavity

Sump CM/PM, Liner Plate Inspection,/Repair and All

Associated Work

Revision 0

71124.01

Self-

NMP-HP-305

Vogtle Alpha Plant Charactgerization Study

04/24/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Assessments

71151

Corrective Action

Documents

10730772

Individual Received Unanticipated Dose Rate Alarm

08/16/2020

71151

Corrective Action

Documents

Resulting from

Inspection

10741335, 278373

71151

Miscellaneous

Access Control Alarms

Report

Access Control Alarms Report

01/16/2019

to

08/21/2020

71151

Procedures

MSPI-VOGTLE

NRC Mitigating System Performance Index (MSPI)

Basis Document

71151

Procedures

MSPI-VOGTLE

NRC Mitigating System Performance Index (MSPI)

Basis Document

71151

Procedures

NMP-ES-076

Mitigating System Performance Index Program

(MSPI)

3.1

71151

Procedures

NMP-ES-076-001

Mitigating System Performance Index Implementation

Instruction

4.1

71153

Corrective Action

Documents

10724196, 10650853,

10653959, 10653949,

276893, 256995,

1057750, 1054522

71153

Drawings

AX3D-AA-A03A

Vogtle - Wilson - Master One Line Diagram

20.0

71153

Miscellaneous

Plant Wilson Services Agreement Between Georgia

Power Company and Southern Nuclear Operating

Company, Inc.

71153

Miscellaneous

NUMARC 93-01

Nuclear Energy Institute - Industry Guideline for

Monitoring the Effectiveness of Maintenance at

Nuclear Power Plants

4A

71153

Miscellaneous

RG 1.160

Monitoring the Effectiveness of Maintenance at

Nuclear Power Plant

71153

Procedures

13418A-2

Standby Auxiliary Transformer Unit Two Train A

Operations

6.2

71153

Procedures

13418A-2

Standby Auxiliary Transformer Unit Two Train A

7.1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Operations

71153

Procedures

230-2

Offsite AC Circuit Verification and Capacity/Capability

Evaluation

71153

Procedures

NMP-GM-021-003

Plant Vogtle 1-2 Switchyard Access and Maintenance

Controls

2.0

71153

Procedures

NMP-GM-021-003

Plant Vogtle 1-2 Switchyard Access and Maintenance

Controls

1.1

71153

Procedures

NMP-OS-010-003

Vogtle Protected Equipment Logs

11.0

71153

Procedures

NMP-OS-010-003

Vogtle Protected Equipment Logs

10.0