IR 05000414/1986021

From kanterella
Jump to navigation Jump to search
Insp Rept 50-414/86-21 on 860429-0502.No Violations or Deviations Noted.Major Areas Inspected:Maint Activities, Preoperational Test Results,Precritical Testing & Previously Identified Inspector Followup Item
ML20197J798
Person / Time
Site: Catawba Duke Energy icon.png
Issue date: 05/13/1986
From: Jape F, Larry Nicholson, Matt Thomas
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20197J786 List:
References
50-414-86-21, NUDOCS 8605200174
Download: ML20197J798 (4)


Text

,

[9 trugjo NUCLEAR REGULATORY COMMISSION A

UNITED STATES

.[

REGION 11 n

g, j

101 MARIETTA STREET.N.W.

\\*.../

+

Report No.: 50-414/86-21-Licensee: Duke Power Company 422 South Church Street Charlotte, NC 28242 Docket No.: 50-414 License No.:

NPF-48 Facility Name: Catawba Unit 2 Inspection Conducted: April 29 - May 2, 1986 w,,_

ne4_,

8-/8-[d Inspectors:

C

M. Thoma's fCfw{k Date Signed n

S-/3-ff L. NicholsoW Date Signed Approved by:

/

F. Jape, Section Chief (/

/

Date Signed

, Test Programs Section, Engineering Branch

'

Division of Reactor Safety

-

,

SUMMARY Scope:

This routine, unannounced inspection - involved reviewing the areas of-maintenance activities, preoperational test results, precritical testing and a previously identified inspector-followup, item.

Results: No violations or deviations were identified.

.

s.

06052% h PDR G

__-_

--

.

-

.

REPORT DETAILS 1.

Persons Contacted Licensee Employees

  • J. W. Cox, Technical Services Superintendent t
  • C. L. Hartzell, Ccmpliance/ Compliance Engineer
  • J. A. Kammer, Performance / Unit 2 Test Engineer P. G. LeRoy, Compliance / Licensing Engineer
  • F. P. Schiffley, II, Compliance / Licensing Engineer
  • G. Smith, Maintenance Superintendent
  • W.

L. Turbyfill, IAE/ Coordinator i

Other licensee employees contacted included test coordinators, engineers, l

technicians, operators, security office members and office personnel.

'

NRC Resident Inspectors s.

  • P. H. Skinner, Senior Resident Inspector
  • P. K. VanDoorn, Senior Resident Inspector
  • M. Lesser, Resident Inspector I
  • Attended exit interview 2.

Exit Interview The inspection scope and findings were summarized on May 2, 1986, with those persons indicated in paragraph 1 above. The inspectors described the areas inspected and discussed the inspection findings. No dissenting comments were received from the. licensee.

The licensee did not identi fy as proprietary any of the materials provided to or reviewed by the inspectors during this inspection.

3.

Licensee Action on Previous Enforcement Matters This subject was not addressed in the inspection.

4.

Unresolved Items l

Unresolved items were not identified during the inspection.

i

,

i -

- -- - -

-

-

.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _. _ _ _.

~- - -.

.

-

-

.

-

.

5.

Independent Inspection - Maintenance (62702)

Maintenance activities associated with the #2 Turbine Driven Auxiliary Feedwater Pump were observed during the inspection period. Inadequate pump discharge flow detected while performing PT/2/A/4250/03C, Auxiliary Feedwater Pump #2 Performance Test, resulted in the disassembly and inspection of valves 2CA-20 and 2CA-181 per Work Requests 4971 PRF and 4980 PRF, respectively. The low flow condition required this maintenance to be performed in accordance with action item a.

of Catawba Technical'

Specification 3.7.1.2 as discussed in the resident inspector report (414/86-22). The inspectors witnessed portions of the valve maintenance to verify that proper administrative, material and cleanliness controls were utilized.

Appropriate system isolations were obtained and operational personnel were aware of the maintenance activity.

The licensee stated that acceptable discharge flow was obtained subsequent to cleaning and reassembly of the above valves.

No violations or deviations were identified in the areas inspected.

6.

'Preoperational Test Results Verification (70329)

In Attachment 2 of DPC's status letter for fuel loading (dated January 24, 1986), all of the preoperational (preop) tests that were not expected to be complete by fuel load were listed.

Justifications and the modes of operation where the test would be completed was also listed. The testing to be completed before initial criticality was reviewed and discussed with licensee personnel.

Preop test TP/2/A/1600/068, Steam Generator Steam Line Pressure Control Functional Test, was in progress during this inspection.

Preop tests TP/2/B/1200/09, Boron Thermal Regeneration; and TP/2/B/1350/17E, 6.9 KV Auxiliary Power Fast / Delay Transfer, will not be completed prior to initial criticality as stated in the letter.

The licensee stated that justification for not completing these two tests will be addressed in a revision letter to the NRC. The inspectors verified that other tests listed in Attachment 2 which were to be completed by initial criticality had been completed.

No violations or deviations were identified in the areas inspected.

7.

Precritical Test Procedure Review / Witness (72564, 72302)

The inspectors reviewed precritical test TP/2/A/2600/07, Rod Cluster Control Assembly Drop Time Test.

The procedure was reviewed to veri' that:

FSAR commitments have been included,

-

-

Rod drop time acceptance criteria is as specified in the Technical Specification, Correct prerequisites were identified,

-

-

..

.

..

....

..

..

.

'

Drop testing of each rod is performed with no flow and full flow in

-

both the cold and hot plant conditions.

The inspectors witnessed portions of both TP/2/A/2600/07 and TP/2/B/2600/06, Full Length Control Rod Drive Mechanism Timing Test to verify that:

-

- Appropriate revisions of the procedures were available and in use by test personnel, Test prerequisites were met,

-

Personnel involved in the tests were briefed prior to beginning the

-

tests,

-

Proper plant systems were in service,

-

The tests were performed in accordance with requirements,

-

Adequate coordination among personnel involved in the test, Test data were collected and recorded in the proper manner.

-

No violations or~ deviations were identified in the areas inspected.

8.

Followup on Previously Identified Inspection Findings (92701)

(Closed) Inspector Followup Item 414/86-14-01, concerning guidance for correcting in process procedure documentation errors.

Station Directive 4.2.1, Development, Approval, and Use of. Station Procedures, has been revised (Rev. 21) to provide specific guidance for correcting mistakes after the procedure is in use. This includes prohibiting the use of " white out" to correct mistakes. This item is considered closed.

-

b I

.a