IR 05000261/1981017

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-261/81-17 on 810608-09.Noncompliance Noted: Whole Body Dose Limit Exceeded for Contract Worker Marking Steam Generator B Tube Sheet.No Notice of Violation Issued
ML14176A650
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 07/09/1981
From: Hosey C, Wray J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14176A649 List:
References
50-261-81-17, NUDOCS 8109090361
Download: ML14176A650 (7)


Text

tp 8 REG(1

UNITED STATES RE YUCLEAR REGULATORY COMMISSIi

REGION II

101 MARIETTA ST., N.W., SUITE 3100 ATLANTA, GEORGIA 30303 Report No. 50-261/81-17 Licensee:

Carolina Power and Light Company 411 Fayetteville Street Raleigh, NC 27602 Facility Name:

H. B. Robinson Docket No. 50-261 License No. DPR-23 Inspection at H. B. Robinson Site near Hartsville, South Carolina Inspector:

JDate Signed Approved by: C4,__Z C. M. Hosey, Acting ection Chief Date Signed Technical Inspection Branch Engineering and Technical Inspection Division SUMMARY Inspection on June 8-9, 1981 Areas Inspected This special, unannounced inspection involved 12 inspector-hours on site reviewing the events surrounding an overexposure of a contract worke Results In the areas inspected, two violations were identified (exceeding quarterly whole body dose limit, paragraph 5.e; failure to follow procedures, paragraphs 5.a, 5.c, and 5.d).

Both violations relate to an overexposure event which was reported by the licensee in a letter to the Director, Office of Inspection and Enforcement, dated June 9, 198 The event is an additional example of the inadequate external exposure control program identified in IE Report 50-261/

81-1 Therefore, no Notice of Violation is enclosed herewit PDR ADOCK 05000261 G

PDR

REPORT DETAILS Persons Contacted Licensee Employees

  • R. B. Starkey, Jr., General Manager
  • D. S. Crocker, Manager-Environmental and Radiation Control
  • B. MacCready, E&RC Supervisor J. Pettigout, Senior ALARA Specialist W. Ritchie, RC&T Foreman Other licensee employees contacted included four technician Other Organizations V. Burke, Senior Engineer - Westinghouse E. Boyce, Site Coordinator - Institute for Resource Management, In NRC Resident Inspector
  • S, Weise, Resident Inspector,
  • Attended exit interview Exit Interview The inspection scope and findings were summarized on June 9, 1981, with those persons indicated in paragraph 1 above. The General Manager informed the inspector that the response to the overexposure event will be included in the response to NRC's letter of May 12, 1981. The inspector agreed that no further written action would be required if the response is determined to be adequat The inspector also discussed the factors listed in paragraph 9 which are believed to have contributed to the overexposur. Licensee Action on Previous Inspection Findings Not inspecte.

Unresolved Items Unresolved items were not identified during this inspectio. Overexposure Incident On May 30, 1981, a contract worker notified the Health Physics Department that he would be entering the containment building and peforming platform work on steam generator B. The individual was

issued a full-face respirator and multiple thermoluminescent dosimeters (TLDs)

for his head, chest and gonad areas as required for platform work by health physics procedure HP-12, Steam Generator Inspection and Maintenance. An air supplied suit is required for entries into the steam generator while only a full-face respirator is required for platform work. Dose control restricted his allowable exposure to 400 mrem, the normal limit assigned for work not involving entry into the steam generator. The health physics control point at the containment building entrance verified that the individual was wearing the proper protective clothing and personnel monitoring devices prior to entering containmen They also verified that sufficient health physics personnel were inside the containment building to provide job.coverage as required by procedures. At approximately 8:45 a.m., the contract worker entered the containment building on' Special Radiation Work Permit (SRWP)

530-9 to mark tubes in steam generator B for eddy current testing. SRWP 530-9 was written for steam generator C with the appro priate radiological survey information for that steam generato The worker should have been listed on SRWP 530-8 which was written for work on B steam generator. Health physics procedure HP-7, Special Radiation Work Permits, states that only workers listed on the SRWP are authorized to perform work under that SRW Technical Specification 6.11 states that procedures involving personnel radiation exposure shall be adhered to for all operations. The inspector stated that an individual listed on and performing work under the wrong SRWP was failure to follow procedure HP-7 in violation of Technical Specifica tion 6.11 (81-10-03). There were approximately five individuals, in addition to two health physics techn-icians, in containment at this time. The two HP techni cians were providing coverage.of an entry by one individual into steam generator C. The remaining four individuals did not require continuous health physics coverage.: One of the HP technicians was assigned by the licensee to act as rover, covering jobs requiring intermittent HP coverage and assisting, as was the situation at C steam generator, special jobs when appropriat The technician responsible for provi ding roving health physics. coverage informed the inspector that he was not aware that work was planned for B steam generator nor that a worker had entered the building in order to work on. B steam generato The inspector reviewed the minutes of the daily plan-of-the-day meeting which indicated that site management was aware that marking tubes in B steam generator was scheduled for May 30. In addition, health physics personnel in dose control, respiratory protection and at the contain ment building access control point were aware that a worker was entering the containment to work on B steam generator. The inspector stated that a system should be devised to ensure that the health physics technician in the containment building responsible for ensuring each worker is provided health physics coverage is aware of all work performed in the buildin c. The entrance to the B steam generator area was posted with a sign which read "contact HP prior to entry."

SRWPs 530-8 and 530-9 emphasized the requirement to obey all postings and to contact HP prior to starting work at the steam generators. Technical Specification 6.13 states that each individual or group of individuals entering a high radiation area shall be provided with a dose rate survey instrument. Health physics procedure HP-7 states that during outages continuous health physics coverage can be substituted for the requirement specified in Technical Specification 6.1 The worker admitted to entering the B steam generator platform area without contacting health physics and without a survey instrumen The inspector stated that not following the requirements of the SRWP was another example of failure to follow pro cedure HP-7 in violation of Technical Specification 6.11 (81-10-03).

d. At approximately 9:30 a.m., the roving HP technician was relieved and a turnover of activities in the containment building was conducted with his relief. No mention of work in B steam generator was mad Upon assuming the watch, the HP technician toured the building and discovered the worker marking tubes in B steam generator. The tech nician stopped work, read the worker's pocket dosimeter on his chest which indicated 260 mrem and observed that his exposure limit was 400 mrem. The worker stated that he had only one more tube to mark. The technician left the area to continue the tour and permitted the worker to complete his work without ensuring that health physics coverage was provided. The inspector stated that not providing health physics coverage for work on B steam.generator after becoming aware that work was being performed on the platform in a high radiation area without a survey instrument was another example of failure to follow procedure HP-7 in violation of Technical Specification 6.11 (81-10-03).

e. Within approximately 15 minutes, the HP technician confronted the worker a second time and read his pocket dosimeter. It indicated. 370 mrem. Because this value was near the worker's limit of 400 mrem, the technician instructed the worker to leave the buildin Subsequent processing of the worker's head, chest and gonad TLDs indicated doses of 2807 mrem, 1092 mrem and 163 mrem, respectivel Based upon a previous quarterly whole body exposure of 302 mrem, the individual was assigned a whole body dose of 3.109 rem for the second calendar quarter of 198 CFR 20.101(b) requires licensees to restrict the total occupational dose to the whole body of each individual in a restricted area to 3 rems during any calendar quarter. The inspector stated that an individual receiving a whole body dose of 3.109 rems in the second calendar quarter of 1981 was in. violation of 10 CFR 20.101(b)

(81-10-03).

4 Coincidental Circumstances As previously stated, there were approximately five workers, in addition to two health physics technicians between 8:45 and 9:30 on May 3 Two HP technicians were providing health physics coverage to a worker making an entry into C steam generato Three workers were painters not working in a high radiation area and, therefore, did not require continuous health physics coverage. The last worker was an engineering technician inspecting the portable 1000 cfm HEPA filter units used on each steam generator. This technician informed the inspector that he had encountered a worker in the B steam generator bay twice during his tours. At both times, health physics coverage was not being provided. The engineering technician stated that he had observed the worker with his head inside the steam generator channel head marking tubes, but acknowledged not comprehending the significance of this activity nor the absence of a qualified HP technicia However, he did instruct the worker that when idle, to wait in a low dose rate are Siubsequent interviews with the worker indicated that he mistook the engi n eering technician as a HP technician. Although he admitted not contacting HP prior to his initial entry into the B steam generator platform area, the worker assumed that a health physics technician had arrived to cover his jo The licensee has modified its containment building health physics coverage program to require HP technicians to wear red arm bands as a visual aid in identifying members of the Health Physics Departmen The inspector reviewed the licensee's program for computing stay times inside steam generator channel head A licensee representative stated that prior to steam generator entry, the. HP technician covering the job is required to phone dose control outsi-de containment where the worker's exposure history is reviewed and a stay time is calculated using the formula specified in HP-1 For platform work, dose control reviews a worker's exposure history and assigns a dose limit of 400 mrem which is written on the worker's protective clothing prior to containment building entry. When health physics became aware that this worker was at B steam generator, it appeared, based on the issuance of a full-face respirator, an exposure limit of 400 mrem written on his protective clothing and discussions with the worker, that only platform work was being performed. Health physics had no reason to expect an overexposure since the worker's chest worn pocket dosimeter did not exceed 400 mre (The pocket dosimeter is worn on the chest during platform work because this is the area of the body which would appear to receive the maximum'dose if the individual does not enter the generator.)

Based on reenactment of the worker's activities on the mock-up and cbmparison of exposure results and.survey data, it was concluded that multiple channel head entries were mad The licensee estimated that the worker had to have been inside the generator approximately 15 minutes to receive a dose to the head of 2807 mrems based on survey data.. Interviews with the contractor responsible for the steam generator work revealed a misinterpretation of what constitutes a steam generator entr The licensee

maintains that any part of the body breaking the imaginary plane of the

.steam generator channel head manway is considered an entry. The contractor stated that he considered an entry that which involves the entire body entering the channel head are It appeared that for this reason, the worker informed health physics that he would be performing platform work and not making any entries. The inspector reviewed records subsequent to this event that indicated personnel on site had been reinstructed in what con stitutes a steam generator entry and how tube marking can result in steam generator entrie. Pre-incident Activities The inspector reviewed records of training given to the overexposed indi vidua The worker required a second test before successfully passing the requirements for unescorted access throughout the plan The individual had previously worked for the contractor as a steam generator jumper and had worked three or four times before at the Robinson facility. The inspector was informed by contractor and licensee representatives that they had no previous radiological concerns with regard to this worke The inspector reviewed the worker's NRC Form 4. It indicated an exposure of 85 mrem received between April 1 and May 15, 198 Licensee dosimetry records indicate that the. worker received 231 mrem since arrival onsite

.

May 14, 1981 and prior to entering containment at approximately 8:45 a.m. on May 30, 198 His combined previous quarterly whole body exposure of 316 mrem when combined with 2807 mrem recieved the morning of May 30 exceeds the

.quarterly dose limit of three rems specified in 10 CFR 10.101(b).

Records indicated that the worker was given special training on the steam generator mock-up by an experienced contractor senior enginee This

  • training consisted of proper dress requirements, nozzle cover installation,.

eddy current fixture, mechanical plugging operation and tube sheet markin The inspector had no further questions concerning worker trainin.

Post-incident Activities Upon recognition that a worker had been overexposured during.steam generator work, the licensee restricted the individual from further work at the plan In addition, the licensee stopped all work in the containment building an began training site personnel on the contributing factors of this event and actions each worker needed to take to prevent recurrence. Modifications to the.health physics containment building coverage program were made. Health physics technicians in containment began wearing red arm bands to facilitate

.recognition by workers so that the worker can procure health physics coverage prior to starting work. Training sessions were also conducted to clarify that an entry into a steam generator means any part of the body breaking the imaginary plane of the manway opening. In addition, an indi

.vidual was assigned to the steam generator contractor to ensure that a

health physics technician accompanies workers into high radiation areas inside the containment building requiring continuous health physics coverag The inspector had no further comment.

Conclusions The inspector concluded.that the major contributing factor to the over exposure of the contract worker marking the B steam generator tube sheet was the worker's disregard for the requirements of the appropriate SRWP; In addition, the following concerns were expressed.to licensee management: lack of knowledge by responsible HP technician in the containment building of all activity under his purview; b. permission by health physics technician to perform work on steam generator platform without HP coverage; apparently no requirement for workers to read, initial and comply with all requirements of SRWP or RWP; lack of knowledge of HP personnel on tube sheet marking activities and the possibility that such activities could involve steam generator entries; e. misunderstandings of definition of steam generator entry; f. consideration that posting is adequate personnel access control to high radiation.areas within the containment building; and placement of pocket dosimeter on chest during.marking operations.