AECM-83-0586, Updated RO 83-053/1:on 830601,fire-rated Penetrations Opened to Implement Design Change Packages.Hourly Fire Watches Established.Work Tasks Expected to Be Completed by 831101

From kanterella
Jump to navigation Jump to search
Updated RO 83-053/1:on 830601,fire-rated Penetrations Opened to Implement Design Change Packages.Hourly Fire Watches Established.Work Tasks Expected to Be Completed by 831101
ML20080H417
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 09/15/1983
From: Dale L
MISSISSIPPI POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
AECM-83-0586, AECM-83-586, RO-83-053-1, RO-83-53-1, NUDOCS 8309210290
Download: ML20080H417 (3)


Text

'

MISSISSIPPI POWER & LIGHT COMPANY Helping Build Mississippi EmikhihbliddB P. O. B O X 16 4 O . J A C K S O N . M I S S I S S iff 9205 September 15, 1983 8 4 g*

NUCLEAR PRODUCTION DEPARTMENT U. S. Nuclear Regulatory Ccmmission Region II 101 Marietta St., N.W., Suite 2900 Atlanta, Georgia 30303 Attention: Mr. J. P. O'Reilly, Regional Administrator

Dear Mr. O'Reilly:

SUBJECT:

Grand Gulf Nuclear Station Unit 1 Docket No. 50-416 License No. NPF-13 File 0260/L-835.0 Special Report 83-053/1 -

Update Report - Fire Rated Penetrations Opened to Implement Design Change Packages AECM-83/0586 This is an update to a previous report submitted July 8, 1983, for the event described below. The purpose of this update is to provide a revised estimated completion date.

Beginning on June 1, 1983, the fire rated penetrations listed on the attached page were opened to implement design change packages and restored on the dates listed. Fourly fire watches were established within one (1) hour and will be maintained for the duration of the planned maintenance activities in accordance with Technical Specification 6.9.2.

This condition has no affect on the health and safety of the public and does not constitute a threat to plant safety. The remaining work tasks are now expected to be complete by November 1, 1983.

Yours truly,

/b kYk'-

k L. F. Dale Manager of Nuclear Services EBS/SHH: sap Attachment cc: (See Next Page)

D DO OOO 6 PDR $b' O Member Middle South Utilities System f

r  ;..

i

- AECM-83/0586 MICOlCalPPI POWER Q LIGHT COMPANY Mr. J. B. Richard (w/a) cc:

Mr. . R. B. McGehee ('w/o)

Mr. T. B. Conner (w/o)

Mr. G. B. Taylor (w/o)

Mr. Richard C. DeYoung, Director (w/a)

Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Document Control Desk (w/a)

U. S. Nuclear Regulatory Commission Washington, D. C. 20555 4

4 i

r  :~.

Attachment to AECM-83/0586

' Page 1 of 1 Beginning on June 1, 1983, the following fire rated penetrations were opened to implement design change packages and restored on the dates listed. The remaining work tasks are expected to be completed by November 1, 1983.

PENETRATIONS INCIDENT REPORT # RESTORATION DATE CE-36G 83-06-05 CE-20E 83-06-04 08-25-83 CE-87E 83-06-04 08-25-83 CE-74E 83-06-04 08-25-83 '

CE-200D 83-06-04 CABLE TRAY COVER DTGE 43-45 83-06-02 08-23-83 FIRE DAMS LA59-LO9 in U720 83-06-04 08-25-83 LA18-LO4 in U739 83-06-04 08-25-83 LA59-L01 in U739 83-06-04 LA10-LO59 in U720 83-06-04 08-25-83 LA13-LO3 in U739 83-06-04 08-25-83 LA12-LO3 in U739 83-06-04 08-25-83