MONTHYEAR3F0505-01, April 2005 Monthly Operating Report for Crystal River Unit 32005-05-12012 May 2005 April 2005 Monthly Operating Report for Crystal River Unit 3 3F0405-01, March 2005 Monthly Operating Report for Crystal River Nuclear Plant2005-04-0808 April 2005 March 2005 Monthly Operating Report for Crystal River Nuclear Plant 3F0305-01, February 2005 Monthly Operating Report for Crystal River Unit 32005-03-10010 March 2005 February 2005 Monthly Operating Report for Crystal River Unit 3 3F0205-02, January 2005 Monthly Operating Report for Crystal River Unit 32005-02-0909 February 2005 January 2005 Monthly Operating Report for Crystal River Unit 3 3F0105-01, December 2004 Monthly Operating Report for Crystal River Unit 32005-01-11011 January 2005 December 2004 Monthly Operating Report for Crystal River Unit 3 3F1204-01, November 2004 Monthly Operating Report for Crystal River Unit 32004-12-0909 December 2004 November 2004 Monthly Operating Report for Crystal River Unit 3 3F1104-01, October 2004 Monthly Operating Report for Crystal River Unit 32004-11-0909 November 2004 October 2004 Monthly Operating Report for Crystal River Unit 3 3F1004-01, September 2004 Monthly Operating Report for Crystal River Unit 32004-10-13013 October 2004 September 2004 Monthly Operating Report for Crystal River Unit 3 3F0904-01, August 2004 Monthly Operating Report for Crystal River Unit 32004-09-0909 September 2004 August 2004 Monthly Operating Report for Crystal River Unit 3 3F0804-01, July 2004 Monthly Operating Report for Crystal River Unit 32004-08-10010 August 2004 July 2004 Monthly Operating Report for Crystal River Unit 3 3F0704-01, June 2004 Monthly Operating Report for Crystal River Unit 32004-07-14014 July 2004 June 2004 Monthly Operating Report for Crystal River Unit 3 3F0604-01, May 2004 Monthly Operating Report for Crystal River Unit 32004-06-14014 June 2004 May 2004 Monthly Operating Report for Crystal River Unit 3 3F0504-01, April 2004 Monthly Operating Report for Crystal River, Unit 32004-05-12012 May 2004 April 2004 Monthly Operating Report for Crystal River, Unit 3 3F0404-01, March 2004 Monthly Operating Report for Crystal River Unit 32004-04-0707 April 2004 March 2004 Monthly Operating Report for Crystal River Unit 3 3F0304-01, February 2004 Monthly Operating Report for Crystal River Unit 32004-03-10010 March 2004 February 2004 Monthly Operating Report for Crystal River Unit 3 3F0204-01, January 2004 Monthly Operating Report for Crystal River, Unit 32004-02-11011 February 2004 January 2004 Monthly Operating Report for Crystal River, Unit 3 3F0104-01, December 2003 Monthly Operating Report for Crystal River Unit 32004-01-13013 January 2004 December 2003 Monthly Operating Report for Crystal River Unit 3 3F1203-01, November 2003 Monthly Operating Report for Crystal River, Unit 32003-12-0909 December 2003 November 2003 Monthly Operating Report for Crystal River, Unit 3 3F1103-01, October 2003 Monthly Operating Report for Crystal River Unit 32003-11-11011 November 2003 October 2003 Monthly Operating Report for Crystal River Unit 3 3F1003-01, September 2003 Monthly Operating Report for Crystal River, Unit 32003-10-0909 October 2003 September 2003 Monthly Operating Report for Crystal River, Unit 3 3F0903-01, August 2003 Monthly Operating Report for Crystal River, Unit 32003-09-0909 September 2003 August 2003 Monthly Operating Report for Crystal River, Unit 3 3F0803-01, July 2003 Monthly Operating Report for Crystal River, Unit 32003-08-0606 August 2003 July 2003 Monthly Operating Report for Crystal River, Unit 3 3F0703-01, June 2003 Monthly Operating Report for Crystal River, Unit 32003-07-0909 July 2003 June 2003 Monthly Operating Report for Crystal River, Unit 3 3F0603-01, May 2003 Monthly Operating Report for Crystal River Unit 32003-06-11011 June 2003 May 2003 Monthly Operating Report for Crystal River Unit 3 3F0503-01, April 2003 Monthly Operating Report for Crystal River Unit 32003-05-12012 May 2003 April 2003 Monthly Operating Report for Crystal River Unit 3 3F0403-01, March 2003 Monthly Operating Report for Crystal River Unit 32003-04-10010 April 2003 March 2003 Monthly Operating Report for Crystal River Unit 3 3F0303-01, February 2003 Monthly Operating Report for Crystal River Unit 32003-03-13013 March 2003 February 2003 Monthly Operating Report for Crystal River Unit 3 3F0203-01, January 2003 Monthly Operating Report for Crystal River, Unit 32003-02-11011 February 2003 January 2003 Monthly Operating Report for Crystal River, Unit 3 3F0103-01, December 2002 Monthly Operating Report for Crystal River Unit 32003-01-0808 January 2003 December 2002 Monthly Operating Report for Crystal River Unit 3 3F1202-01, November 2002 Monthly Operating Report for Crystal River Unit 32002-12-10010 December 2002 November 2002 Monthly Operating Report for Crystal River Unit 3 3F1102-01, October 2002 Monthly Operating Report for Crystal River Unit 32002-11-13013 November 2002 October 2002 Monthly Operating Report for Crystal River Unit 3 3F1002-01, September 2002 Monthly Operating Report for Crystal River Unit 32002-10-10010 October 2002 September 2002 Monthly Operating Report for Crystal River Unit 3 3F0902-02, August 2002 Monthly Operating Report for Crystal River Unit 32002-09-11011 September 2002 August 2002 Monthly Operating Report for Crystal River Unit 3 3F0802-02, July 2002 Monthly Operating Report for Crystal River Unit 32002-08-0808 August 2002 July 2002 Monthly Operating Report for Crystal River Unit 3 3F0702-02, June 2002 Monthly Operating Report for Crystal River Unit 32002-07-0909 July 2002 June 2002 Monthly Operating Report for Crystal River Unit 3 3F0502-02, April 2002 Monthly Operating Report for Crystal River Unit 32002-05-13013 May 2002 April 2002 Monthly Operating Report for Crystal River Unit 3 3F0402-02, March 2002 Monthly Operating Report for Crystal River Unit 32002-04-0808 April 2002 March 2002 Monthly Operating Report for Crystal River Unit 3 3F0302-02, February 2002 Monthly Operating Report for Crystal River, Unit 32002-03-12012 March 2002 February 2002 Monthly Operating Report for Crystal River, Unit 3 3F0202-02, January 2002 Monthly Operating Report for Crystal River Unit 32002-02-12012 February 2002 January 2002 Monthly Operating Report for Crystal River Unit 3 ML0203604382002-01-10010 January 2002 December 2001 Monthly Operating Report for Crystal River, Unit 3 2005-05-12
[Table view] |
Text
Cn Progress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating license No. DPR-72 Ref: ITS 5.7.1.2 April 8,2005 3F0405-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - March 2005 Monthly Operating Report
Dear Sir:
Florida Power Corporation, doing business as Progress Energy Florida, Inc., hereby submits the Crystal River Unit 3 (CR-3) March 2005 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.
If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
Sincerely, J. A. Franke Plant General Manager JAF/ff Attachment xc: Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Progress Energy Florida. Inc.
,'I-Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL34428
APPENDIX A OPERATING DATA REPORT DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE Aprili 2005 COMPLETED BY J. E. Lane 1'y TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD (Month/Year): March 2005 MONTH YEAR TO DATE CUMULATIVE 1 DESIGN ELECTRICAL RATING (MWe-Net) 860 2 MAXIMUM DEPENDABLE CAPACITY (Mwe-Net) 838 3 NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 2,160.0 176,844.3 4 NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 2,160.0 174,472.6 5 UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 6 NET ELECTRICAL ENERGY GENERATED (MWH) 640,285 1,859,540 137,011,850
. t, ., ' Jr APPENDIX B UNIT SHUTDOWNS DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE April 1, 2005 COMPLETED BY J. E. Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD: March 2005 No. Date Type Duration Reason Method of Cause / Corrective Actions ;. :ur F: Forced (Hours) (1) Shutting S: Scheduled Down (2) Comments None
SUMMARY
Crystal River Unit 3 operated the entire month without an outage.
(1)Reason: (2) Method A-EQUIPMENT FAILURE (Explain) I-MANUAL B-MAINTENANCE OR TEST 2-MANUALTRIP ISCRAM C-REFUEUNG 3-AUTO TRIP I SCRAM D-REGULATORY RESTRICTION 4-CONTINUATION E-OPERATOR TRAINING / UCENSE EXAMINATION 5-OTHER (Explahi)
F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)
H-OTHER (Explain)