3F1104-01, October 2004 Monthly Operating Report for Crystal River Unit 3

From kanterella
Jump to navigation Jump to search
October 2004 Monthly Operating Report for Crystal River Unit 3
ML043230496
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 11/09/2004
From: Franke J
Progress Energy Florida
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
3F1104-01
Download: ML043230496 (3)


Text

co3 Progress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: ITS 5.7.1.2 November 9, 2004 3F1 104-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Crystal River Unit 3 - October 2004 Monthly Operating Report

Dear Sir:

Florida Power Corporation, doing business as Progress Energy Florida, Inc., hereby submits the Crystal River Unit 3 (CR-3) October 2004 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.

If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.

JAF/ff Attachment xc:

Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Progress Energy Florida, Inc.

Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428 L

APPENDIX A OPERATING DATA REPORT DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE 50-302 FLCRP-3 November 1, 2004 J. E. L7ne9 8x (352) 795-6486 x3698 REPORTING PERIOD (Month/Year):

October 2004 MONTH YEAR TO DATE CUMULATIVE 1

DESIGN ELECTRICAL RATING (MWe-Net) 2 MAXIMUM DEPENDABLE CAPACITY (MWe-Net) 3 NUMBER OF HOURS REACTOR WAS CRITICAL 4

NUMBER OF HOURS THE GENERATOR WAS ON LINE 5

UNIT RESERVE SHUTDOWN HOURS 6

NET ELECTRICAL ENERGY GENERATED (MWH) 860 838 745.0 745.0 0.0 628796 7149.0 7121.0 0.0 6045501 173220.3 170848.6 0.0 133894503

APPENDIX B UNIT SHUTDOWNS DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE November 1, 2004 COMPLETED BY J. E. Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD:

October2004 No.

Date Type Duration Reason Method of Cause / Corrective Actions F: Forced (Hours)

(1)

Shutting S: Scheduled Down (2)

Comments

SUMMARY

Crystal River Unit 3 operated the entire month without an outage.

(1) Reason:

A-EOUIPMENT FAILURE (Explain)

B-MAINTENANCE OR TEST C-REFUELING D-REGULATORY RESTRICTION E-OPERATOR TRAINING I LICENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)

H-OTHER (Explain)

(2) Method I MANUAL 2-MANUAL TRIP / SCRAM 3-AUTO TRIP / SCRAM 4-CONTINUATION 5-OTHER (Explain)