October 2002 Monthly Operating Report for Crystal River Unit 3
ML023250189
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 11/13/2002
From: Franke J
Florida Power Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
3F1102-01, ITS 5.7.1.2
Download: ML023250189 (3)


Text

t Florida Power A Progress Energy Company Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: ITS 5.7.1.2 November 13, 2002 3F1102-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Crystal River Unit 3 - Monthly Operating Report

Dear Sir:

Florida Power Corporation hereby submits the Crystal River Unit 3 (CR-3) October 2002 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.

If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.

Sincerely, A. Franke Plant General Manager JAF/ff Attachment xc:

Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Crystal River Nuclear Plant 15760 W Power Line Street Crystal River. FL 34428

REPORTING PERIOD (MonthlYear):

October 2002 MONTH YEAR TO DATE DESIGN ELECTRICAL RATING (MWe-Net)

MAXIMUM DEPENDABLE CAPACITY (Mwe-Net) 3 NUMBER OF HOURS REACTOR WAS CRITICAL 4

NUMBER OF HOURS THE GENERATOR WAS ON LINE 5

UNIT RESERVE SHUTDOWN HOURS 6

NET ELECTRICAL ENERGY GENERATED (MWH) 1 2

825 834 CUMULATIVE 745.0 745.0 0.0 629,388 7,277.0 7,269.4 0.0 6,121,710 156,684 154,392 0

120,090,973 APPENDIX A OPERATING DATA REPORT DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE November 1,2002 COMPLETED BY J E Lane________

TELEPHONE (352) 795-6486 x3698 i

APPENDIX B UNIT SHUTDOWNS DOCKET NO.

50-302 UNIT NAME FLCRP-3 DATE November 1, 2002 COMPLETED BY J E Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD:

October 2002

SUMMARY

Crystal River Unit 3 operated the entire month without an outage or significant downpower.

(1) Reason:

A-EQUIPMENT FAILURE (Explain)

B-MAINTENANCE OR TEST C-REFUELING D-REGULATORY RESTRICTION E-OPERATOR TRAINING ! LICENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)

H-OTHER (Explain)

(2) Method 1-MANUAL 2-MANUAL TRIP/ SCRAM 3-AUTO TRIP / SCRAM 4-CONTINUATION 5-OTHER (Explain)

No.

Date Type Duration Reason Method of Cause / Corrective Actions --z F: Forced (Hours)

(1)

Shutting S: Scheduled Down (2)

Comments None