3F0103-01, December 2002 Monthly Operating Report for Crystal River Unit 3
| ML030150593 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 01/08/2003 |
| From: | Franke J Progress Energy Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 3F0103-01 | |
| Download: ML030150593 (3) | |
Text
. Progress Energy Docket No. 50-302 Operating License No. DPR-72 Ref: ITS 5.7.1.2 January 8, 2003 3F0103-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Monthly Operating Report
Dear Sir:
Florida Power Corporation hereby submits the Crystal River Unit 3 (CR-3) December 2002 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.
If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
Sincerely, J. A. Franke Plant General Manager JAF/ff Attachment xc: Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Progress Energy Florida, Inc.
Crystal River Nuclear Plant 15760 W. Powerline Street Crystal River, FL 34428
APPENDIX A OPERATING DATA REPORT DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE January2. 2003 COMPLETED BY J. E. Lanei 0GY
)
TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD (MonghYear):
December 2002 MONTH YEAR TO DATE CUMULATIVE I
DESIGN ELECTRICAL RATING (MWe-Net) 825 2
MAXIMUM DEPENDABLE CAPACITY (Mwe-Net) 834 3
NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 8,707.9 158,115 4
NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 8,692.4 155,815 5
UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0
6 NET ELECTRICAL ENERGY GENERATED (MWH) 634,766 7,300,308 121,269,571
.0
,I APPENDIX B UNIT SHUTDOWNS DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE January 2, 2003 COMPLETED BY J. E. Lane TELEPHONE (352) 795.-64 x898 REPORTING PERIOD:
December 2002 No.
Date Type Duration Reason Method of Cause I Corrective Actions F: Forced (Hours)
(1)
Shutting S: Scheduled Down (2)
Comments None
SUMMARY
Crystal River Unit 3 operated the entire month without an outage.
(1) Reason:
A-EQUIPMENT FAILURE (Explain)
S-MAINTENANCE OR TEST C-REFUEUNG D-REGULATORY RESTRICTION E-OPERATOR TRAINING I UCENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)
H-OTHER (Explai)
(2) Method 1-MANUAL 2-MANUAL TRIP I SCRAM S-AUTO TRIP I SCRAM 4-CONTINUATION
-OThER (Explan)