3F0403-01, March 2003 Monthly Operating Report for Crystal River Unit 3
| ML031080418 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 04/10/2003 |
| From: | Franke J Progress Energy Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 3F0403-01 | |
| Download: ML031080418 (3) | |
Text
Progress Energy Docket No. 50-302 Operating license No DPR-72 Ref: ITS 5.7.1.2 April 10, 2003 3F0403-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Monthly Operating Report
Dear Sir:
Progress Energy Florida, Inc. hereby submits the Crystal River 2003 Monthly Operating Report in accordance with CR-3 Specification 5.7.1.2.
Unit 3 (CR-3) March Improved Technical If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
Sincerely, Plant General Manager JAF/ff Attachment xc:
Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Progress Energy Florida, Inc Crystal River Nuclear Plant 15760 W Powerline Street Crystal River, FL 34428
CD-4
APPENDIX A OPERATING DATA REPORT DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50-302 FLCRP-3 April 1, 2003 J E Lane W
b (352) 795-6486 x3698 REPORTING PERIOD (MonthlYear):
March 2003 MONTH YEAR TO DATE CUMULATIVE 1
DESIGN ELECTRICAL RATING (MWe-Net) 2 MAXIMUM DEPENDABLE CAPACITY (Mwe-Net) 3 NUMBER OF HOURS REACTOR WAS CRITICAL 4
NUMBER OF HOURS THE GENERATOR WAS ON LINE 5
UNIT RESERVE SHUTDOWN HOURS 6
NET ELECTRICAL ENERGY GENERATED (MWH) 860 834 744.0 744.0 0.0 639,946 2,160.0 2,160.0 0.0 1,848,651 160,275 157,975 0
123,118,222
C APPENDIX B UNIT SHUTDOWNS
(
DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE April 1, 2003 COMPLETED BY J E Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD:
March 2003 No.
Date Type Duration Reason Method of Cause / Corrective Actions F: Forced (Hours)
(1)
Shutting S: Scheduled Down (2)
Comments None
SUMMARY
Crystal River Unit 3 operated the entire month without an outage.
(1) Reason:
A-EQUIPMENT FAILURE (Explain) 8-MAINTENANCE OR TEST C-REFUELING D-REGULATORY RESTRICTION E-OPERATOR TRAINING / LICENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)
H-OTHER (ExplaIn)
(2) Method 1-MANUAL 2-MANUAL TRIP / SCRAM 3-AUTO TRIP / SCRAM 4-CONTINUATION 5-OTHER (Explain)