3F0902-02, August 2002 Monthly Operating Report for Crystal River Unit 3
| ML022660036 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 09/11/2002 |
| From: | Franke J Florida Power Corp |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 3F0902-02, ITS 5.7.1.2 | |
| Download: ML022660036 (3) | |
Text
Florida Power A Progress Energy Company Crystal River Nuclear Plant Docket No. 50-302 Operating License No DPR-72 Ref: ITS 5.7.1.2 September 11, 2002 3F0902-02 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Monthly Operating Report
Dear Sir:
Florida Power Corporation hereby submits the Crystal River Unit 3 (CR-3) August 2002 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.
If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
i
- ely, J
Franke lant General Manager JAF/ff Attachment xc:
Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Crystal River Nuclear Plant 15760 W Power Line Street Crystal River, FL 34428
APPENDIX A OPERATING DATA REPORT DOCKET NO.
50-302 UNIT NAME FLCRP-3 DATE September 3, 2002 COMPLETED BY J E. Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD (MonthlYear):
August 2002 MONTH DESIGN ELECTRICAL RATING (MWe-Net)
MAXIMUM DEPENDABLE CAPACITY (Mwe-Net)
NUMBER OF HOURS REACTOR WAS CRITICAL NUMBER OF HOURS THE GENERATOR WAS ON LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED (MWH) 1 2
3 4
5 6
YEAR TO DATE 825 834 CUMULATIVE 744.0 744.0 0.0 622,296 5,812.0 5,804.4 0.0 4,887,247 155,219 152,927 0
118,856,510
. 3 APPENDIX B UNIT SHUTDOWNS DOCKET NO.
50-302 UNIT NAME FLCRP-3 DATE September 3, 2002 COMPLETED BY J E Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD:
August 2002 No.
Date Type Duration Reason Method of Cause / Corrective Actions F: Forced (Hours)
(1)
Shutting S: Scheduled Down (2)
Comments None
SUMMARY
Crystal River Unit 3 operated at full power for the entire month.
(1) Reason:
A-EQUIPMENT FAILURE (Explain)
B-MAINTENANCE OR TEST C-REFUEUNG D-REGULATORY RESTRICTION E-OPERATOR TRAINING I LICENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)
H-OTHER (Explain)
(2) Method I-MANUAL 2-MANUAL TRIP ISCRAM 3-AUTO TRIP I SCRAM 4-CONTINUATION S-OTHER (Explain)