MONTHYEARML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 ML23131A3282023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220052022-08-24024 August 2022 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022005 and 05000316/2022005) ML22130A1722022-05-11011 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000315/20210062022-03-0202 March 2022 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021006 and 05000316/2021006) ML21309A3322021-11-0505 November 2021 Notification of Nrc Fire Protection Team Inspection Request for Information IR 05000315/20210052021-09-0101 September 2021 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021005 and 05000316/2021005) ML21146A2862021-05-26026 May 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Donald C. Cook Nuclear Plant ML21068A3512021-03-0909 March 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2021002; 05000316/2021002 IR 05000315/20200062021-03-0404 March 2021 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020006 and 05000316/2020006) ML21012A0592021-01-12012 January 2021 Information Request for the Cyber-Seruity Full Implementation Inspection, Notification to Perform Inspection 05000315/2021401; 05000316/2021401 IR 05000315/20200112020-09-17017 September 2020 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2020011; 05000316/2020011 IR 05000315/20200052020-09-0101 September 2020 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020005 and 05000316/2020005) ML20133J9722020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000315/20200202020-04-10010 April 2020 Units 1 and 2 - Information Request for NRC Triennial Evaluation of Changes, Tests, and Experiments (50.59) Baseline Inspection 05000315/2020020 and 05000316/2020020 IR 05000315/20190062020-03-0303 March 2020 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2019006 and 05000316/2019006) ML20016A3842020-01-16016 January 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000315/20204102019-11-19019 November 2019 Information Request for the Cyber Security Full Implementation Inspection, Notification to Perform Inspection 05000315/2020410; 05000316/2020410 IR 05000315/20190052019-08-28028 August 2019 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2019005 and 05000316/2019005) ML19192A1552019-07-11011 July 2019 Ltr. 07/11/19 Donald C. Cook Nuclear Power Plant, Unit 2 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2019004; 05000316/2019004 (DRS-M.Holmberg) ML19128A3482019-05-0808 May 2019 Ltr. 05/08/19 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000315/2019012; 05000316/2019012 (DRS-A.Shaikh) ML19078A3732019-03-19019 March 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspection at the Donald C. Cook Nuclear Power Plant, Units 1 and 2 IR 05000315/20180062019-03-0404 March 2019 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2018006 and 05000316/2018006) ML19037A3842019-02-0404 February 2019 Ltr. 02/04/19 Donald C. Cook Nuclear Power Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2019001; 05000316/2019001 (DRS-E.Fernandez) IR 05000315/20180052018-08-28028 August 2018 Updated Inspection Plan for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2018005 and 05000316/2018005) IR 05000315/20170062018-03-0202 March 2018 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2017006; 05000316/2017006) ML18058B6192018-02-27027 February 2018 Inspection Plan for Donald C. Cook, Unit 2, for Inservice Inspection Activities; Inspection Report 05000316/2018002 (DRS-L.Smith) IR 05000315/20170052017-08-28028 August 2017 Updated Inspection Plan for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2017005; 05000316/2017005) ML17076A3592017-03-17017 March 2017 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000315/2017002; 05000316/2017002 (Lnr) IR 05000315/20160062017-03-0101 March 2017 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2016006; 05000316/2016006) IR 05000315/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2016005; 05000316/2016005) ML16211A0322016-07-28028 July 2016 Request for Inforamtion for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000316/2016010 IR 05000315/20150062016-03-0202 March 2016 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2(Report 05000315/2015006 and 05000316/2015006) ML16013A1832016-01-12012 January 2016 Notification of NRC Inspection and Request for Information (Jen) IR 05000315/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2015005; 05000316/2015005) IR 05000315/20140012015-03-0404 March 2015 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2, (Report 05000315/2014001 and 05000316/2014001) ML14317A5892014-11-13013 November 2014 Notification of NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection 05000315/2015002; 05000316/2015002 ML14245A2562014-09-0202 September 2014 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 IR 05000316/20130012014-03-0404 March 2014 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Unit 1 and 2 (Report 05000351/2013001; 05000316/2013001) ML14024A4762014-01-23023 January 2014 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000315-14-007 ML13246A2272013-09-0303 September 2013 2013 Donald C. Cook Mid-Cycle Letter Combined IR 05000315/20120012013-03-0404 March 2013 Annual Assessment Letter for D.C. Cook Nuclear Power Plant, Units 1 and 2, (Report 05000315/2012001 and 05000316/2012001) ML13032A5182013-02-0101 February 2013 IR 05000315-13-009 & 05000316-13-009, on 05/28-29/2013, 05/29-31/2013, 06/10-14/2013, & 06/24-28/2013, Donald C. Cook, Units 1 & 2- Notification to Perform a Triennial Fire Protection Baseline Inspection While Transition to 10 CFR 50.48(C). ML12248A3012012-09-0404 September 2012 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant Units 1 and 2 ML12235A2462012-08-21021 August 2012 IR 05000315-12-005 & 05000316-12-005, 11/26-30/2012, D.C. Cook Nuclear Power Plant, Units 1 & 2 - Notification of an NRC Triennial Heat Sink Performance & Review of Implementation of Industry Initiative to Control Degradation of Underground IR 05000315/20110072012-03-0505 March 2012 Annual Assessment Letter for D.C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2011007 and 05000316/2011007) 2023-08-30
[Table view] Category:Letter
MONTHYEARIR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 ML24004A1582024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0039 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report ML23159A0192023-06-13013 June 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report ML23131A3282023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 AEP-NRC-2023-19, Annual Radioactive Effluent Release Report2023-04-30030 April 2023 Annual Radioactive Effluent Release Report ML23117A0062023-04-27027 April 2023 Review of the Spring 2022 Steam Generator Tube Inspections Report ML23114A1142023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2023-23, Annual Report of Individual Monitoring for 20222023-04-24024 April 2023 Annual Report of Individual Monitoring for 2022 AEP-NRC-2023-24, Notification of Ph Non-Compliance for Turbine Room Sump2023-04-12012 April 2023 Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-20, Annual Report of Property Insurance2023-04-0303 April 2023 Annual Report of Property Insurance AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion AEP-NRC-2023-11, Form OAR-1, Owner'S Activity Report2023-01-31031 January 2023 Form OAR-1, Owner'S Activity Report IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 AEP-NRC-2023-02, Request for Approval of Change Regarding Neutron Flux Instrumentation2023-01-26026 January 2023 Request for Approval of Change Regarding Neutron Flux Instrumentation ML22363A5622023-01-0404 January 2023 Relief Request ISIR-5-06 Related to ASME Code Case N-729-6 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in ML22340A1392022-11-30030 November 2022 Submittal of Revision 31 to Updated Final Safety Analysis Report and 10CFR50.71(e) Updated and Related Site Change Reports IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2022-61, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-062022-10-24024 October 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-06 2024-01-08
[Table view] |
Text
March 2, 2006 Mr. M. Nazar Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106
SUBJECT:
ANNUAL ASSESSMENT LETTER - D. C. COOK NUCLEAR PLANT, UNITS 1 AND 2 (REPORT 05000315/2006001; 05000316/2006001)
Dear Mr. Nazar:
On February 8, 2006, the NRC staff completed its performance review of the D. C. Cook Nuclear Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2005. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.
Overall, the D. C. Cook Nuclear Plant, Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process baseline inspections at your facility.
While plant performance for the most recent quarter is within the Licensee Response column of the Action Matrix, there was a safety significant Performance Indicator affecting the first two quarters of the assessment cycle for Unit 2. Specifically, there was one White PI in the Scrams with Loss of Normal Heat Removal area of the Initiating Events cornerstone that returned to Green after the second quarter of calendar year 2005.
M. Nazar Additionally, on November 23, 2005, the staff issued two Severity Level III violations of 10 CFR 50.9 and one Severity Level III violation of 10 CFR 55.25 with a $60,000 civil penalty in accordance with the NRCs Enforcement Policy. The violations were associated with providing incomplete and inaccurate information with regard to applications for new, renewed, or amended reactor operator licenses; providing incomplete and inaccurate information in an August 2, 2004, letter that described your corrective actions for a previous Severity Level III violation; and the failure to provide timely information with regard to a change in medical status of licensed reactor operators. The violations remain open pending further NRC review of your corrective actions.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through September 30, 2007. In addition to the program defined inspection activities, additional oversight activities will be conducted for the reactor vessel head replacement, scheduled for the Fall refueling outage in 2006. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Christine Lipa at 630-829-9619 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Satorius, Director Division of Reactor Projects Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74
Enclosure:
D. C. Cook Nuclear Plant Inspection/Activity Plan See Attached Distribution
M. Nazar Additionally, on November 23, 2005, the staff issued two Severity Level III violations of 10 CFR 50.9 and one Severity Level III violation of 10 CFR 55.25 with a $60,000 civil penalty in accordance with the NRCs Enforcement Policy. The violations were associated with providing incomplete and inaccurate information with regard to applications for new, renewed, or amended reactor operator licenses; providing incomplete and inaccurate information in an August 2, 2004, letter that described your corrective actions for a previous Severity Level III violation; and the failure to provide timely information with regard to a change in medical status of licensed reactor operators. The violations remain open pending further NRC review of your corrective actions.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through September 30, 2007. In addition to the program defined inspection activities, additional oversight activities will be conducted for the reactor vessel head replacement, scheduled for the Fall refueling outage in 2006. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Christine Lipa at 630-829-9619 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Satorius, Director Division of Reactor Projects Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74
Enclosure:
D. C. Cook Nuclear Plant Inspection/Activity Plan See Attached Distribution DOCUMENT NAME:G:\Branch TSS\ALL EOC\EOC CY2005\EOC Letters For CY 2005\cook.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME EDuncan for MSatorius CLipa:dtp DATE 03/01/06 03/01/06 OFFICIAL RECORD COPY
M. Nazar cc w/encl: J. Jensen, Site Vice President L. Weber, Plant Manager G. White, Michigan Public Service Commission L. Brandon, Michigan Department of Environmental Quality -
Waste and Hazardous Materials Division Emergency Management Division MI Department of State Police D. Lochbaum, Union of Concerned Scientists Berrien County Board Chairman Berrien County Coordinator Berrien County Sheriff EMA Coordinator, Berrien County Emergency Management Agency Mayor of Benton Harbor City Manager of Benton Harbor Mayor of St. Joseph City Manager of St. Joseph Mayor of Bridgman City Manager of Bridgman Mayor of Buchanan City Manager of Buchanan President, Village of Stevensville President, Village of Berrien Springs President, Village of Shoreham INPO
M. Nazar ADAMS Distribution:
HKN PST DWW RidsNrrDirslpab JLC1 GEG KGO RML2 SRI Cook DRPIII DRSIII PLB1 JRK1 ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)
Page 1 of 2 D.C. Cook 03/01/2006 16:02:50 Inspection / Activity Plan Report 22 03/01/2006 - 09/30/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71111.11 - LIC OPERATOR REQUAL PROGRAM EVALUATION 2 1, 2 IP 7111111B Licensed Operator Requalification Program 03/06/2006 03/10/2006 Baseline Inspections ISI - D.C. COOK UNIT 2 ISI INSPECTION 2 1 IP 7111108P Inservice Inspection Activities - PWR 03/27/2006 04/21/2006 Baseline Inspections 7112102 - ALARA (OUTAGE) 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 04/03/2006 04/07/2006 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 04/03/2006 04/07/2006 Baseline Inspections IP 71114 - EP NON-EXERCISE BASELINE 1 1, 2 IP 7111402 Alert and Notification System Testing 04/17/2006 04/21/2006 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 04/17/2006 04/21/2006 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 04/17/2006 04/21/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 04/17/2006 04/21/2006 Baseline Inspections MOD/5059 - MODIFICATION/50.59 INSPECTION 2 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 05/08/2006 05/26/2006 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 05/08/2006 05/26/2006 Baseline Inspections PI&R - PI&R BIENNIAL 3 1, 2 IP 71152B Identification and Resolution of Problems 07/24/2006 08/18/2006 Baseline Inspections MAINT - MAINTENANCE EFFECTIVENESS 1 1, 2 IP 7111112B Maintenance Effectiveness 07/17/2006 07/21/2006 Baseline Inspections ISI - D.C. COOK U1 ISI & RPV HD FAB/MOD INSP 3 1 IP 71007 Reactor Vessel Head Replacement Inspection 09/04/2006 11/03/2006 Other Routine 1 IP 7111102 Evaluation of Changes, Tests, or Experiments 09/04/2006 11/03/2006 Baseline Inspections 1 IP 7111117B Permanent Plant Modifications 09/11/2006 11/03/2006 Baseline Inspections 1 IP 7111108P Inservice Inspection Activities - PWR 10/09/2006 11/03/2006 Baseline Inspections 7112101 - RAD ACCESS AND OUTAGE ALARA 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/25/2006 09/29/2006 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 09/25/2006 09/29/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 09/25/2006 09/29/2006 Baseline Inspections 7112202 - TRANSPORTATION & RADWASTE 1 1, 2 IP 7112202 Radioactive Material Processing and Transportation 10/30/2006 11/03/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 10/30/2006 11/03/2006 Baseline Inspections 71122.01 - RADIOLOGICAL EFFLUENTS 1 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 01/08/2007 01/12/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 01/08/2007 01/12/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 D.C. Cook 03/01/2006 16:02:50 Inspection / Activity Plan Report 22 03/01/2006 - 09/30/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type CDBI - COMPONENT DESIGN BASES INSPECTION 5 1, 2 IP 7111121 Component Design Bases Inspection 01/22/2007 02/23/2007 Baseline Inspections FY 2007 - D. C. COOK INIT PREP 02/2007 3 1 W90152 OL - INITIAL EXAM - D.C. COOK - FEB/MAR 2007 02/26/2007 03/02/2007 Not Applicable FY 2007 - D. C. COOK INIT EXAM 03/2007 3 1 W90152 OL - INITIAL EXAM - D.C. COOK - FEB/MAR 2007 03/19/2007 03/30/2007 Not Applicable 71121.02 - POST OUTAGE ALARA 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/26/2007 03/30/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/26/2007 03/30/2007 Baseline Inspections 71122.03 - REMP & RAD MTL CONTROL 1 1, 2 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 06/11/2007 06/15/2007 Baseline Inspections HEATSINK - HEAT SINK INSPECTION 1 1, 2 IP 7111107B Heat Sink Performance 07/09/2007 07/13/2007 Baseline Inspections 71121.01 - RADIOLOGICAL ACCESS CONTROL 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/24/2007 09/28/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 09/24/2007 09/28/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.