August 28, 2017
SUBJECT:
UPDATED INSPECTION PLAN FOR DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 (REPORT 05000315/2017005; 05000316/2017005)
Dear Mr. Gebbie:
The enclosed inspection plan lists the inspections scheduled through June 30, 2019 for Donald C. Cook Nuclear Power Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.
This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Please contact me at 630-829-9827 with any questions you have regarding this letter.
Sincerely,
/RA/
Billy Dickson, Chief Branch 2 Division of Reactor Projects
Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 Enclosure:
Inspection Plan
cc: Distribution via LISTSERV