ML20016A384

From kanterella
Jump to navigation Jump to search
Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information
ML20016A384
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 01/16/2020
From: David Reeser
Operations Branch III
To: Gebbie J
Indiana Michigan Power Co
References
Download: ML20016A384 (5)


Text

January 16, 2020 Mr. Joel P. Gebbie Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106

SUBJECT:

DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2NOTIFICATION OF AN NRC BIENNIAL LICENSED OPERATOR REQUALIFICATION PROGRAM INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Gebbie:

In a telephone conversation on January 16, 2020, between Mr. D. Reeser, Operations Engineer, the U.S. Nuclear Regulatory Commission (NRC) lead inspector for this inspection, and Mr. C. Peak, Licensed Operator Requalification Training Supervisor, final arrangements were made for the NRC to inspect the licensed operator requalification program at the Donald C. Cook Nuclear Power Plant, Units 1 and 2. The inspection is planned for the week of March 2, 2020, which coincides with your regularly scheduled requalification examination cycle.

The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations and annual operating tests as necessary to support the NRC's inspection program needs. In order to minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a request for documents needed for the inspection.

Please furnish the items listed in the first group of the attached enclosure, needed to support our in-office inspection activities, to the NRC by February 21, 2020. Please have the items listed in the second group of the attached enclosure available for the inspectors during the onsite portion of the inspection activities. Mr. Peak has been advised of this request.

Thank you for your cooperation in this matter. If there are any questions regarding either the inspection, or the material requested in the enclosure, please contact me at 630-829-9859 or via e-mail at david.reeser@nrc.gov.

J. Gebbie This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.

This letter and its enclosure will be available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

David W. Reeser, Operations Engineer Operations Branch Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74

Enclosure:

Requested Information to Support Licensed Operator Requalification Program and Licensed Operator Performance Inspection (IP 71111.11) cc: Distribution via LISTSERV

J. Gebbie Letter to Joel P. Gebbie from David W. Reeser dated January 16, 2020.

SUBJECT:

DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2NOTIFICATION OF AN NRC BIENNIAL LICENSED OPERATOR REQUALIFICATION PROGRAM INSPECTION AND REQUEST FOR INFORMATION DISTRIBUTION:

Jessie Quichocho Omar Lopez-Santiago RidsNrrDorlLpl3 RidsNrrPMDCCook Resource RidsNrrDroIrib Resource Darrell Roberts John Giessner Jamnes Cameron Allan Barker DRPIII DRSIII Ikeda Betts Colleen Schmidt ADAMS Accession Number: ML20016A384 OFFICE RIII NAME DReeser:jw DATE 01/16/20 OFFICIAL RECORD COPY

REQUESTED INFORMATION TO SUPPORT LICENSED OPERATOR REQUALIFICATION PROGRAM AND LICENSED OPERATOR PERFORMANCE INSPECTION (IP 71111.11)

Please provide the following information on a CD/DVD, if possible, by February 21, 2020.

1. One complete version of a biennial requalification written examination administered during the training cycle.
2. Ten (10) job performance measures (JPMs) and four (4) simulator scenarios associated with an annual requalification operating test required by Title 10 of the Code of Federal Regulations, Part 55.59(a)(2). The JPMs and scenarios to be reviewed should include those that will be observed during the onsite portion of this inspection, with any remaining JPMs and scenarios selected from other weeks within the same training cycle.
3. Complete versions of the reference materials used to develop the administered written examinations and operating tests. (Refer to ES-201, Attachment 3, Reference Material Guidelines for Initial Licensing Examinations, for additional examples and clarification.).
4. Spreadsheets and/or test outlines which show the usage of written examination questions, JPMs, and simulator scenarios.
5. A list (or lists) of licensee-identified issues associated with licensed operator errors or other licensed operator performance problems which have occurred in the actual plant/main control room since the last biennial requalification program inspection, their associated corrective actions, and if these issues were incorporated into requalification training. (These issues are likely documented in condition/problem identification reports, licensee-conducted audits and assessments, and in industry operating experience reports, etc.).
6. Facility licensee procedures that describe, and discuss the implementation of, licensed operator requalification training and examination, including examination security procedures.
7. Facility licensee procedures that describe maintenance and testing of the facility licensees control room simulator.
8. A schedule of the licensees examination activities during the on-site inspection week.

Please have the following information available for U.S. Nuclear Regulatory Commission (NRC) review on March 2, 2020.

1. Licensed operator pass/fail statistics for any NRC-required requalification examinations that have been completed.
2. An overall schedule of the facility licensees requalification program since the last biennial inspection (cycle weeks, training topics, etc.).
3. A list and descriptions of any examination security problems since the last biennial inspection (likely documented in training department condition/problem identification reports).

Enclosure

REQUESTED INFORMATION TO SUPPORT LICENSED OPERATOR REQUALIFICATION PROGRAM AND LICENSED OPERATOR PERFORMANCE INSPECTION (IP 71111.11)

4. Records for licensed operator requalification training attendance, licensed operator performance in requalification, licensed operator remedial training, individual licensed operator medical records, and records for maintaining an active license and license re-activation.
5. Simulator testing, maintenance, modification, and performance records.

Simulator corrective action records, including lists of open/closed simulator deficiencies, and corrective actions taken.

2