Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000315/2017002; 05000316/2017002 (Lnr)
ML17076A359
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 03/17/2017
From: Lionel Rodriguez
NRC/RGN-III/DRS/EB2
To: Gebbie J
Indiana Michigan Power Co
References
IR 2017002
Download: ML17076A359 (9)


See also: IR 05000315/2017002

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

March 17, 2017

Mr. Joel P. Gebbie

Senior VP and Chief Nuclear Officer

Indiana Michigan Power Company

Nuclear Generation Group

One Cook Place

Bridgman, MI 49106

SUBJECT: DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NOTIFICATION

OF AN NRC TRIENNIAL HEAT SINK PERFORMANCE INSPECTION AND

REQUEST FOR INFORMATION; INSPECTION REPORT 05000315/2017002;

05000316/2017002

Dear Mr. Gebbie:

On June 19, 2017, the U.S. Nuclear Regulatory Commission (NRC) will begin the onsite portion

of the Triennial Heat Sink Performance Inspection at your Donald C. Cook Nuclear Power Plant,

Units 1 and 2. This inspection will be performed in accordance with NRC baseline Inspection

Procedure 71111.07.

In order to minimize the impact that the inspection has on the site and to ensure a productive

inspection, we have enclosed a request for documents needed for the inspection. The

documents have been divided into three groups.

The first group lists information necessary for our initial inspection scoping activities.

This information should be available to the lead inspector no later than May 5, 2017.

By May 12, 2017, the inspector will communicate the initial selected set of approximately

2-3 risk significant heat exchangers.

The second group is needed to support our in-office preparation activities. This set of

documents, including the calculations associated with the selected heat exchangers,

should be available at the Regional Office no later than June 5, 2017. This information

should be separated for each selected component, especially if provided electronically

(e.g., folder with component name that includes calculations, condition reports,

maintenance history, etc.). During the in-office preparation activities, the inspector may

identify additional information needed to support the inspection.

The last group includes the additional information above as well as plant specific

reference material. This information should be available onsite to the inspector on

June 19, 2017. It is also requested that corrective action documents and/or questions

developed during the inspection be provided to the inspector as the documents are

generated.

J. Gebbie -2-

All requested documents are to be for the time period from the onsite inspection period back

to the documents that were provided in response to the previous Heat Sink Performance

Inspection. If no activities were accomplished in that time period, then the request applies to

the last applicable document in the previous time period. It is important that these documents

be as complete as possible, in order to minimize the number of documents requested during the

preparation week or during the onsite inspection.

The lead inspector for this inspection is Mr. Lionel Rodriguez. We understand that our

licensing contact for this inspection is Mr. Michael B. Ellett of your organization. If there are

any questions about the inspection or the material requested in the enclosure, please contact

the lead inspector at 630-829-9609 or via e-mail at Lionel.Rodriguez@nrc.gov.

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,

a request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget Control Number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Lionel Rodriguez, Reactor Inspector

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-315; 50-316

License Nos. DPR-58; DPR-74

Enclosure:

Triennial Heat Sink Performance Inspection

Document Request

cc: Distribution via LISTSERV

J. Gebbie -3-

Letter to Joel P. Gebbie from Lionel Rodriguez dated March 17, 2017

SUBJECT: DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NOTIFICATION

OF AN NRC TRIENNIAL HEAT SINK PERFORMANCE INSPECTION AND

REQUEST FOR INFORMATION; INSPECTION REPORT 05000315/2017002;

05000316/2017002

DISTRIBUTION:

Jeremy Bowen

RidsNrrDorlLpl3-1 Resource

RidsNrrPMDCCook Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

ADAMS Accession Number ML17076A359

OFFICE RIII RIII RIII RIII

NAME LRodriguez:cl

DATE 03/17/17

OFFICIAL RECORD COPY

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Inspection Report: 05000315/2017002; 05000316/2017002

Inspection Dates: June 19 - 23, 2017

Inspection Procedure: IP 71111.07, Heat Sink Performance

Lead Inspector: Lionel Rodriguez

630-829-9609

Lionel.Rodriguez@nrc.gov

Please provide the information electronically in pdf files, Excel, or other searchable formats,

preferably on some portable electronic media (e.g., CD-ROM, DVD). The portable electronic

media should contain descriptive names, and be indexed and hyperlinked to facilitate ease of

use. Information in lists should contain enough information to be easily understood by

someone who has knowledge of light water reactor technology.

I. Information Requested By May 5, 2017

1. List of the Generic Letter (GL) 89-13, Service Water System Problems Affecting

Safety-Related Equipment, heat exchangers in order of risk significance.

2. Copy of heat exchanger performance trending data tracked for each GL 89-13 heat

exchanger.

3. List of Corrective Action Program (CAP) documents (with a short description)

associated with GL 89-13 heat exchangers, heat sinks, silting, corrosion, fouling,

aging, or heat exchanger testing, ultimate heat sink (UHS), and safety-related

service and closed cooling water systems for the previous 3 years or since the last

CAP document list was sent to the U.S. Nuclear Regulatory Commission for the

previous heat sink performance inspection. The list should include all CAP

documents not on the last CAP document list.

4. Copy of any self-assessment done on any of GL 89-13 heat exchangers, UHS, and

safety-related service and closed cooling water systems since the last heat sink

performance inspection.

5. Last two System Health Report(s) and maintenance rule system notebooks for all the

GL 89-13 heat exchangers, UHS, and safety-related service and closed cooling

water systems.

6. List of engineering-related operator workarounds (with a short description)

associated with GL 89-13 heat exchangers. The requested documents are to be for

the time period from the onsite inspection period back to the documents that were

provided in response to the previous heat sink performance inspection.

Enclosure

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

7. List of permanent and temporary modifications (with a short description) associated

with GL 89-13 heat exchangers, UHS, and safety-related service and closed cooling

water systems. The requested documents are to be for the time period from the

onsite inspection period back to the documents that were provided in response to the

previous heat sink performance inspection.

8. Electronic copies of the current Final Safety Analysis Report, Technical

Specifications, Technical Specifications Basis, and Technical Report Manual.

9. List of enhancements and/or commitments made during license renewal for

GL 89-13 heat exchangers, UHS, and safety-related service and closed cooling

water systems (as applicable).

II. Information Requested By June 5, 2017

1. Copies of the GL 89-13 responses.

2. Copies of procedures developed to implement the recommendations of GL 89-13

(e.g., the GL 89-13 Heat Exchanger Program description).

3. Copies of the selected CAP documents.

4. For the specific heat exchangers selected:

a. Copy of system description and design basis document for the heat exchangers

(as applicable).

b. Provide a list of calculations (with a short description) which currently apply to

each heat exchanger.

c. Provide the calculations or evaluations that:

i. establish the limiting design basis heat load required to be removed by

each of these heat exchangers;

ii. demonstrate the heat exchangers capacity to remove the limiting heat load;

iii. correlate surveillance testing and/or inspection results from these heat

exchangers with design basis heat removal capability (e.g., basis for

surveillance test and/or inspection acceptance criteria);

iv. evaluate the potential for water hammer in each heat exchanger or

associated piping; and

v. evaluate excessive tube vibration in each heat exchanger.

d. Copy of any operability determinations or other documentation of degradation

associated with the heat exchangers or the systems that support the operation

for the selected heat exchangers.

e. Copy of the design specification, heat exchanger data sheets, and vendor

documents including component drawings applicable for the selected heat

exchangers.

2

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

f. Copies of normal, abnormal, and emergency operating procedures associated

with the selected heat exchangers.

g. Copies of the Aging Management Programs (AMP) and the implementing

procedures that manage aging of the selected heat exchangers (as applicable).

5. For the UHS and the safety-related service and closed cooling water systems (or

equivalent):

a. Copy of system description and design basis document (as applicable).

b. Copy of any operability determinations or other documentation of degradation

associated with the UHS and the safety-related service and closed cooling water

systems.

c. Copy of the document (e.g., Updated Final Safety Analysis Report or Technical

Requirements Manual) that states the maximum cooling water system inlet

temperature limit that still allows full licensed power operation of the nuclear

reactor.

d. Copy of system description and design basis document (as applicable).

e. Copy of the construction code and Design Specification.

f. Copies of normal, abnormal, and emergency operating procedures associated

with the UHS and safety-related service and closed cooling water systems

including procedures for loss of these systems.

g. Copies of CAP documents associated with waterhammer or hydraulic transients

in the safety-related service and closed cooling water systems since the last Heat

Sink Inspection.

h. If available, provide an electronic copy of piping and instrumentation diagrams for

the service and closed cooling water systems, including the intake structure.

i. Provide a list of calculations (with a short description), which currently apply to

the UHS and safety-related service and closed cooling water systems.

j. Provide a list of instruments (with a short description) associated with automatic

or alarm functions for the UHS and safety-related service and closed cooling

water systems.

k. Provide a list of any design change (with a short description) performed on the

UHS and safety-related service and closed cooling water systems since the last

heat sink performance inspection.

l. Copies of the AMPs and the implementing procedures that manage aging of the

UHS (including the intake structure) and the safety-related service and closed

cooling water systems (as applicable).

6. A schedule of all inspections, cleanings, maintenance, or testing of any

safety-related plant heat exchanger to be performed during the onsite portion of

the inspection.

3

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

III. Information Requested to be Available on First Day of Inspection, June 19, 2017

1. For the specific heat exchangers selected.

a. Copy of the calculation which correlates surveillance testing results from these

heat exchangers with design basis heat removal capability (e.g., basis for

surveillance test acceptance criteria).

b. Copies of the two most recent completed tests and evaluation data confirming

thermal performance for those heat exchangers which are performance tested.

c. Documentation and procedures that identify the types, accuracy, and location of

any special instrumentation used for the two most recently completed thermal

performance tests for the heat exchangers (e.g., high accuracy ultrasonic flow

instruments or temperature instruments). Include calibration records for the

instruments used during these tests.

d. Information regarding any alarms which monitor on-line performance.

e. Copy of the document describing the inspection results of each heat exchanger.

The requested documents are to be for the time period from the onsite inspection

period back to the documents that were provided in response to the previous

heat sink performance inspection.

f. The cleaning and inspection maintenance schedule for each heat exchanger for

the next 5 years.

g. Copy of the calculation which establishes the limiting (maximum) design basis

heat load which is required to be removed by each of these heat exchangers.

h. Copy of the operating procedure that ensures that the maximum cooling water

system inlet temperature limit is not exceeded.

i. Copy of the calculations or documents which evaluate the potential for water

hammer in each heat exchanger or associated piping.

j. Copy of the calculations that evaluate excessive tube vibration in each heat

exchanger and the documents that describe the controls that prevent heat

exchanger degradation due to excessive flow induced vibration during operation.

k. Copy of the periodic flow testing at or near maximum design flow. The requested

documents are to be for the time period from the onsite inspection period back to

the documents that were provided in response to the previous heat sink

performance inspection.

l. Copy of the document which identifies the current number of tubes in service for

each heat exchanger and the supporting calculation which establishes the

maximum number of tubes which can be plugged in each heat exchanger.

m. Copy of the document establishing the repair criteria (plugging limit) for degraded

tubes which are identified in each heat exchanger.

4

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

n. Copies of the documents that verify the structural integrity of the heat exchanger

(e.g. eddy current summary sheets, ultrasonic testing results, and visual

inspection results).

o. Copies of those documents that describe the methods taken to control water

chemistry in the heat exchangers, including those credited by any AMPs (as

applicable).

p. Copies of any credited AMP monitoring/inspection results for the selected heat

exchangers (as applicable). The requested documents are to be for any

completed monitoring/inspection in the time period from the onsite inspection

period back to the documents that were provided in response to the previous

heat sink performance inspection.

2. For the review of the operation of the safety-related service water system (or

equivalent) and the UHS:

a. Copies of any design change performed on the UHS. The requested documents

are to be for the time period from the onsite inspection period back to the

documents that were provided in response to the previous heat sink performance

inspection.

b. Copies of any design change performed on the safety-related service water

system. The requested documents are to be for the time period from the onsite

inspection period back to the documents that were provided in response to the

previous heat sink performance inspection.

c. Copies of procedures for a loss of UHS.

d. Copies of procedures for a loss of service water system.

e. Inspections and/or maintenance related to preventing macrofouling (e.g., silt,

dead mussel shells, or debris) and biotic fouling (e.g., fish, algae, grass, or kelp).

The requested documents are to be for the time period from the onsite inspection

period back to the documents that were provided in response to the previous

heat sink performance inspection.

f. Copies of documents associated with the monitoring of pump performance for

potential strong-pump vs. weak-pump interaction.

3. For the review associated with the system walkdown of the safety-related service

and closed cooling water systems:

a. Copies of the testing, inspection, or monitoring program procedures for buried or

inaccessible piping and the associated results. The requested documents are to

be for the time period from the onsite inspection period back to the documents

that were provided in response to the previous heat sink performance inspection.

b. Copies of the ultrasonic test results and/or visual inspections that verify the

structural integrity of the piping.

5

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

c. Copies of the procedures to monitor, assess, and disposition active thru wall pipe

leaks, including structural evaluations and/or planned corrective actions.

d. History of any thru wall pipe leak on the system. The requested documents are

to be for the time period from the onsite inspection period back to the documents

that were provided in response to the previous heat sink performance inspection.

e. Historical trend data for make-up to the safety-related closed cooling water

system. The requested documents are to be for the time period from the onsite

inspection period back to the documents that were provided in response to the

previous heat sink performance inspection.

f. Copies of the documents associated with the periodic inspection program used to

detect protective coating failure, corrosion, erosion, and aging.

g. Copies of the IST vibration monitoring results and operational history for deep

draft vertical pumps, if applicable. The requested documents are to be for the

time period from the onsite inspection period back to the documents that were

provided in response to the previous heat sink performance inspection.

h. Copies of any credited AMP monitoring/inspection results for the safety-related

service and closed cooling water systems, and the UHS (as applicable). The

requested documents are to be for any completed monitoring/inspection in the

time period from the onsite inspection period back to the documents that were

provided in response to the previous heat sink performance inspection.

If the information requested above will not be available, please contact Lionel Rodriguez as

soon as possible at 630-829-9609 or e-mail Lionel.Rodriguez@nrc.gov.