IR 05000317/1986023

From kanterella
Jump to navigation Jump to search
Insp Rept 50-317/86-23 on 861117-21.No Violations Identified.Major Areas Inspected:Licensee Action on Previous Insp Findings & Insp of Inservice Insp Activities,Including Observations of Ultrasonic & Eddy Current Exams in Progress
ML20207J624
Person / Time
Site: Calvert Cliffs Constellation icon.png
Issue date: 12/22/1986
From: Mcbrearty R, Strosnider J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20207J602 List:
References
50-317-86-23, NUDOCS 8701080541
Download: ML20207J624 (6)


Text

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report N /86-23 Docket N License No. DPR-53 Licensee: Baltimore Gas and Electric Company P. O. Box 1475 Baltimore, Maryland 21203 Facility Name: Calvert Cliffs Nuclear Power Plant, Unit 1 Inspection At: King of Prussia, Pennsylvania and Lusby, Maryland Inspection Conducted: November 17 - 21, 1986 Inspector: h 7h ' M ft./f,/9}d R. A. Mc Brearty, Reactor Ejigineer date'

h ////2[85 Approvedby: J. R. Strosnider, Chief, Materials and date Processes Section, EB, DRS Inspection Summary: Inspection on November 17 - 21, 1986 Report No. 50-317/86-2 Areas Inspected: A routine, unannounced inspection of licensee actions on previous inspection findings and inspection of inservice inspection (ISI)

activities was performed. The inspection included review of the ISI program, observations of ultrasonic and eddy current examinations in progress, review of NDE procedures and review of ISI dat Results: No violations were identifie kDy20 42 862230 0 OCK 0500o337 PDR

_ _

.

.

DETAILS Persons Contacted Baltimore Gas & Electric Company S. Bauxbaum, ET Level III

  • M. Bowman, General Supervisor, Technical Services Engineering
  • J. Carroll, General Supervisor, Quality Assurance
  • L. Larragoite, Licensing Engineer, NESD
  • J. Lemons, Manager, Nuclear Operations Department
  • W. Lippold, Manager, Nuclear Engineering Services J. Pence, NDE Level III
  • C. Quimby, Quality Assurance Auditor

, *B. Rudell, Senior Engineer, Performance Engineering

  • L. Russell, Manager Nuclear Maintenance
  • A. Thornton, General Supervisor Plants & Projects Engineering
  • A. Zimmerman, Quality Assurance Engineer
NDE Technologies T. Byers, ET Data Analyst - Level III Zetech W. Gray, ET Data Analyst - Level IIA U.S. Nuclear Regulatory Commission i

T. Foley, Senior Resident Inspector

  • L. Tripp, Chief, Projects Section 3A
  • Denotes those present at the exit meetin . Licensee Action on Previous Inspection Findings i

(Closed) Violation (317/84-06-01): Failure to perform acceptance NDE in accordance with the applicable ASME Code Section. Fourteen Unit 1 pipe l to penetration welds were re-examined ultrasonically by Southwest Research

'

Institute personnel to meet acceptance requirements of ASME Section III Division 1, Subsection NE, Class MC Components, 1977 Edition through Winter 1977 Addenda. The inspector reviewed ultrasonic examination procedure 800-90, Revision 2, Deviation 1, data sheets associated with the fourteen welds, customer notification forms and indication resolution sheets which document the evaluation and disposition of examination i i

results. The inspector's review indicated that the licensee's commitments were met and the welds were acceptable per ASME Section II i

, Based on the above this item is closed.

i i

l I

, , _ _ _ _ _ _ _ _ _ _ _ _ _ _ . .--,,,m, _ . _ _

, . . _ , , _ _ _ . _ _ _ _ _ _ _ _ . , _

.

.

(Closed) Unresolved Item (317/85-11-01): UT couplant not traceable to certification record. The licensee has v'erified that the glycerine used as an ultrasonic couplant at Calvert Cliffs was, in all cases, USP 99.5%

grade glycerine. The licensee's Chemistry Laboratory has determined that USP 99.5% grade glycerine limits are below licensee contaminant level rejection limits and, therefore, that grade glycerine is acceptable for use as an ultrasonic couplant on a generic basi Based on the above this item is close . Inservice Inspection (ISI) Program Review The inspector reviewed the licensee's ISI program to ascertain that ASME code and regulatory requirements are met, and that related ISI activities are properly controlled by the license The current outage is the last scheduled refueling outage in the first ten year inspection interval, and the examinations scheduled for comple-tion during the outage will complete the program requirements for the interva The inspector found that administrative procedures are in place, and that the program format provides for adequately tracking the various aspects of the program, and for determining examination status during the interva Nondestructive examination implementing procedures are prepared by the licensee's ISI vendor, and are approved by the licensee prior to us The ISI staff is adequate for the work load and is comprised of technically competent individual No violations were identifie . Review of ISI Implementing Procedures The following nondestructive examination procedures were reviewed by the inspector with regard to technical adequacy, and to ascertain compliance with applicable ASME Code and regulatory requirement *

SwRI-NDT-300-1, Revision 26, " Dry Powder Magnetic Particle Exami-nation" SwRI-NDT-600-3, Revision 62 " Manual Ultrasonic Examination of Pres-sure Piping Welds"

SwRI-NDT-700-11, Revision 1, " Mechanized Ultrasonic Inside Surface Examination of Ferritic Vessels Greater than 2.5 Inches in Thickness" SwRI-NDT-700-11, Revision 2, " Mechanical Ultrasonic Inside Surface Examination of Ferritic Vessels Greater Than 2 Inches in Thickness"

_ - .

.

. .

The inspector's review indicated that the above listed procedures meet

- applicable code and regulatory requirements, and are technically acceptable for their intended us No violations were identifie . Observations of NDE In Progress Ultrasonic Examination The inspector observed the mechanical ultrasonic examination of the following reactor pressure vessel (RPV) welds:

Middle Shell longitudinal weld 2-203A

Middle Shell to Lower Shell circumferential weld 9-203 The inspector's observations were made to ascertain compliance with the implementing NDE procedure and with applicable code and regulatory requirement The inspector found that the examinations were performed by qualified examination personnel in accordance with the applicable NDE

procedure, and in accordance with the appropriate scan plan as listed in the RPV examination program pla No violations were identifie Eddy Current Examination of Steam Generator Tubes i The inspector observed the eddy current examination of tubes in steam generators 11 and 12 to ascertain compliance with the facility Technical Specification. The inspector's observations included examination of the following tubes:

Steam Generator No. 11 R0W LINE f

97 67 98 68 97 71 97 73 97 75

!

{

.

.

5 Steam Generator No. 12 R0W LINE 128 78 128 82 127 83 127 81 127 79 The examinations which were observed by the inspector were performed by Zetech Corporation personnel qualified to ET Level IIA and ET Level I using the MIZ-18 syste The system incorporates a computer controlled eddy current probe which does not require the use of templates for tube identification, therefore reducing radiation exposure to equipment installer Additionally, an in-line calibration standard was used to facilitate initial system calibration and subsequent calibration check No violations were identifie . Review of ISI Data The inspector observed the review of ISI data to ascertain compliance with ASME Code and regulatory requirements, and that the evaluations were performed by qualified individual Ultrasonic examination data consisted of video tape recordings of the ultrasonic instrument display and strip chart recordings made during each weld examination. Additionally, data were simultaneously collected with the Ultrasonic Data Recording and Processing System (UDRPS). At present the UDRPS is not permitted by the ASME code because it does not incorpo-rate the use of a distance amplitude correction curve (DAC) for system calibration. System calibration is performed using the examination material to establish a noise level. The licensee used the system for informational purposes, and to provide baseline data for future RPV weld examinations in the event that the code permits its use. The information collected by UDRPS was from the ultrasonic transducer array from which SWRI gathered the official data. The effectiveness of the UDRPS system was dependent upon synchronization cf the two collection methods, and this was controlled largely by SWRI personnel, therefore cooperation of the SWRI group and the licensee personnel operating UDRPS was necessar The inspector found that the two groups worked closely together and lines of communication were maintained to provide the necessary coordinatio The Inspector visited the off site location where eddy current examination data were being interpreted independently by a Zetech Level IIA data analyst, and by an NDE Technologies Level III data analyst. The inspector interviewed the analysts with regard to system calibration techniques,

d t

.

.

various aspects of the MIZ-18 system and the effect of copper on the eddy current examir.: tion results. The inspector was advised that copper produces a characteristic eddy current signal that is readily recognize The inspector was further informed that copper was not detected in the Calvert Cliffs Unit I steam generator tubes. In the event that copper is present the MIZ-18 system is capable of mixing frequencies to eliminate or minimize the copper signal to display underlying defect signal The eddy current data analysis was done by qualified individuals using equipment that was identical to the equipment with which the data were collecte No violations were identifie . Exit Meeting The inspector met with licensee representatives (denoted in paragraph 1)

at the conclusion of the inspection on November 21, 1986. The inspector summarized the purpose and the scope of the inspection and the finding At no time during the inspection was material provided by the inspector to the licensee.