ML20245F259
| ML20245F259 | |
| Person / Time | |
|---|---|
| Site: | Calvert Cliffs |
| Issue date: | 06/16/1989 |
| From: | Roy Mathew NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML20245F253 | List: |
| References | |
| 50-317-89-12, 50-318-89-12, IEB-85-003, IEB-85-3, NUDOCS 8906280074 | |
| Download: ML20245F259 (14) | |
See also: IR 05000317/1989012
Text
7-
y
nyg y
- ----
-
w
,
s*
.4l
e
,
,
( ., ;
- 1
'
r
,
,
i
1
- U.S. NUCLEAR REGULATORY COMMISSION-
. REGION I
.
- 50-317/89-12
- Report lNo; 50-318/89-12
.
50-317
Docket No._~50-318'
,
DpR-53'
License No. DPR-69
, Licensee:
3altimore Gas' and Electric Company
,
P.O. Box 1475
Baltimore.-Maryland 21203-
Facility,Name: 'Calvert Cliffs Units 1 & 2-
Inspection At:
Lusby, Maryland ~
Inspection Conducted: May 1-5, 1989
' In spect' ors :
-
6
G
f
Roy p'..-Mathew,. Reactor Engineer
date
,
-Approved by:
- Io / 7
'C. J Anderson,. Chief, Plant Systems Section
date
Insp6ttion' Summary:
Inspection o'n May 1-5, 1989-(Combined Insp'ection Report
Nos.-50-317/89-12 and 50-318/89-12)
Areas Inspected: A special announced inspection was performed to review the
>
corrective actions that resulted from IE Bulletin _85-03 regarding improper
-limit switch and torque switch settings in motor operatored valves. This
inspection reviewed the licensee's engineering and maintenance' activities to
assure the operational readiness of the motor operated valves.
- Results: The licensee had not addressed all the significant aspects of the
bulletin. Two violations were identified regarding:
(1)lackofprocedures
for-setting the limit switches and providing stem lubrication; and, (2) the
"as-left" Torque switch settings were different from the specified settings in
the setpoint file. Three items remained unresolved at the end of the
inspection.
8906280074 890616
9
gDR
ADOCK 05000317
L__n
-_- - _ _ _ _ - _ _ _ _ - _ _ _
_ _ _ _
e
4
. ;
.
,
,
>
.
DETAILS
1.0 Persons Contacted
1.1 Daltimore Gas and Electric Company
- G. Bell, Engineer, Licensing
- R. Booin, AGS, Electrical Maintenance
- R. Branch, Senior Engineer, Environmental Qualification
S. Cowne, Senior Engineer, Licensing
R. E. Denton, Manager, Quality Assurance and Services Department
i
- M. J. Gahan III, Principal Engineer, Calvert Cliffs
- J. D. Hayden, Engineer, Mechanical Maintenance
P. Hebrank, Engineer, Electrical Modifications
- J. Jerald, Supervisor, Maintenance Training
T. Koneath, Mechanical Engineering Unit
B. Nelson, Training, Electrical and Instrumentation
- D. E. Nickerson, AGS, Mechanical Maintenance
- K. Nietman, General Supervisor, Nuclear Training
- W. H. Robinson, Project Manager, MOV Program
l
S. Rosenbach, Mechanical Engineering Unit
'
- L. Russell, Manager, Calvert Cliffs
- M. W. Taylor, Engineer
- A. Thornton, General Supervisor, Plant and Project Engineering
- L. L. Wackbaugh, General Supervisor, Electrical and Controls
1.2 United States Nuclear Regulatory Commission
j
- H. Eichenholz, Senior Resident Inspector
V. Pritchett, Resident Inspector
- Present at the exit meeting on May 5, 1989.
2.0 Purpose
The purpose of this inspection was to review the licensee's actions taken
in response to IE Bulletin 85-03 regarding motor operated valve (MOV)
common mode failures during plant transients due to improper switch
settings and to review the licensee's program to assure the operational
readiness of the motor operated valves covered under this bulletin.
3.0 Background
l
On June 9, 1985, the Davis-Besse Plant experienced a complete loss of
main and auxiliary feedwater whf ch was caused, in part, by MOV failures.
l
This event resulted in IE Bulletin 85-03 that promulgated NRC requirements
to as:ure the operational readiness of MOVs in the high pressure coolant
'
injection, core spray and emergency feedwater systems. The bulletin
specified that licensees take the following actions.
'l
l
i
m_su_-_-______m___
_ _ _
__
__
l
<
i
'
3
l
'
4
1
(a) Review and document the design basis for the operation of each
valve, including the maximum differential pressure expected during
normal and abnormal operation.
!
(b) .Using the above data, establish the correct switch settings for
torque, torque bypass, position limit and overload for each valve
and perform modifications as needed.
.
(c) Individual valves should be demonstrated to be operable by testing
the valve at the maximum differential pressure based on the
performance requirements.
In the absence of differential pressure
testing, a justification should be provided.
(d) Prepare and revise procedures to ensure that correct switch settings
are determined'and maintained throughout the life of the plant.
(e) Submit a schedule to accomplish the above program including a final
submittal with the results of (b) through (d).
Item (a) was reviewed by the NRC office of Nuclear Reactor Regulation
(NRR). The scope of this inspection was to review items (b) through (d).
4.0 Baltimore Gas and Electric Company response to IE Bulletin 85-03
4.1 Status of Commitments
In a letter dated May 15, 1986 (Ref. 1, Attachment-1), the licensee
provided their schedule for Item (e) of Bulletin 85-03, which requested
a written report within 180 days of the date of this bulletin.
The
licensee completed documentation on May 15, 1986 of the maximum
differential pressure expected across MOVs during normal and abnormal
operation. Of the systems identified in the bulletin, only the High
Pressure Safety Injection (HPSI) system motor operated valves are
subject to the bulletin concerns.
The motor operated valves identi-
fied for Calvert Cliffs 1&2 for IEB 85-03 consideration are listed in
attachment 3 to this report.
In the same letter, the licensee committed
to complete item (b) of the bulletir by July 15, 1986, item (c) by
December 1, 1986 for Unit I and June 1, 1987 for Unit 2, and item (d)
by July 1, 1987.
An NRC letter to the licensee dated July 29, 1987 (Ref. 2, Attachment-1)
requested additional information regarding the licensee's response
dated May 15,1986 (Ref.1, Attachment-1). The licensee responded to
this letter on September 21, 1987.
The NRC requested a written report within 60 days on completion of
the program.
In a letter dated January 28, 1988 (Ref. 4, Attachment 1),
the licensee completed the final response to IE Bulletin 85-03.
_
, _ - -
. _
._
,_ -
-____ __-
_ .
__
. - - _ _ _ _ _ _ _ .
__
- _ - _ - _
'4
.
.
.
,
'
- '
4
4.2 Switch Settings
Item (b) of the bulletin requires that correct switch settings
for torque, torque bypass, position limit and overload for each
value be' established. These items are addressed below.
Open. Torque Switch and Open Bypass Limit Switch
This switch is normally used to limit the mechanical thrust applied
to the valve in the open direction. This switch is usually bypassed
during the initial valve unseating which is-the most challenging
portion of the open stroke.
Failure to set this switch to the required
valve, or, not bypassing this switch in the initial opening stroke,
can cause valve failure.
At Calvert Cliffs Units 1&2, the torque switch is initially bypassed
during the unseating of the valve. The MOV will then " ride on" the
torque switch until the open limit switch contact opens. The licensee
has elected to set the open torque switch to a conservative value
based on the limitations of the actuator assembly and the valve
operator manufacturer's (Limitorque) recommendations.
Close Torque Switch and Close Torque Bypass Limit Switch
The close torque switch bypass acts in a similar manner to the open
torque switch bypass.
This torque switch is bypassed during the
lightest duty portion of the stroke, the beginning of the closing
stroke. This torque switch should be set to assure that valve closure
is not prevented by the torque switch.
At Calvert Cliffs Units 1 and 2, the close torque switch bypass switch
is set to a percentage of the valve travel from the backseat position.
For the remainder of the valve stroke, the torque switch is used in
the control circuit, in series, with the close limit switch.
The licensee does not torque seat the subject MOVs in the closed
direction. However, the torque switch acts as a secondary control
device during the closing cycle. The limiting requirement of the
close torque switch is at the end of the closure stroke when the
thrust requirements are the highest.
If the valve demands more thrust
due to mechanical friction or binding of the valve during the valve
travel between the open and close limits, the torque switch will trip
the motor depending on the torque settings. The torque switch is set
to protect the motor as well as to assure valve operability during a
design bases accident. The licensee obtained Limitorque recommenda-
tions on required torque settings and the supporting data sheets.
The torque switch trip set point was calculated based on the most
limiting closure thrust requirement including the thrust needed to
'
overcome the differential pressure across the valve.
_
_ _ _ _ _ _ - . _ _ _ . _ . . _ . . . - - _
.-
- - - - -
s ,
ll
s
'
,
A
L
,
.
,
QE
4
'
5
>
Open Limit Switch /Close Limit' Switch
L
Normal industry practiceLis.to seat valves under torque switch control
L
"and backseat valves under limit switch control. This is to assure
tight seating during closure and to provide a positive stop of the
~
_
operator during valve opening.
At Calvert Cliffs Units 1 and 2, the licensee.uses limit switch control
-for both opening-and clos.ing,of valves. -The.open li_mit-switch provides
the control function for determining the upper limit of the valve
stem' travel in'the open direction and stops motor. rotation by opening
~
'the circuit. The setting of this switch must assure adequate valve
opening and should prevent backseating.
Valve backseats normally
provide'a.se'al that is redundant to the valve packing in order to'
allow valve packing replacement without the need to drain'down the
process system. Using the motor power to backseat can and has, caused .
valve stem shearing and stem thread twisting.
Therefore, it is-
.
important to set the open limit switch away from the backseat with
enough margin to allow for motor deenergization and inertia.
The close-limit switch is usually used with the close torque switch
in series for over torque protection.
For high speed operators,
where torque switches cannot react in sufficient time,' the close
limit switch'deenergizes the motor and the remaining inertia force
is used to seat the valve.
At.Calvert Cliffs Units 1 and 2, the licensee has set both th'e open
and close limitLswitches to position valves a sufficient distance from
the backseat / seat to deenergize.the motor. The remaining inertia
forces are used to open/close the valve. The inspector noticed that
i
the. licensee is relying on the electrician's expertise to' set the
.
' limit switches.
Since the limit switch is the primary control for
opening / closing.the valve, the valve will operate per the limit switch
setting, unless, there is a. mechanical failure of the valve which
demands excessive thrust causing the' torque switch.to operate.
Incorrect limit switch settings could lead to damage to the valve,
valve operator and related components. See section 4.4 for a further
discussion of this issue.
Another related concern regarding limit switch control for controlling
valve closure is the influence of wear on the valve seat. The motor
will get a signal to shut off the limit switch at a definite point
during the closing stroke based on the limit switch setpoint.
If the
valve seat suffers erosion or other wear, the inertia force available
after the motor shuts off may not be sufficient to fully seat the
valve. The inspector noted that the licensee does not perform
surveillance checks or leak rate tests to assure proper closing of
the bulletin valves.
This is an unresolved item pending NRC review
of the licensee action to assure proper setting of the close limit
switch considering the influence of seatwear on valve closure for
valves that are closed using the limit switches.
50-317/89-12-03;
50-318/89-12-03.
,
.
-
k
'
'
A
I
.J
-
s ,;
,
.
%
6'
,
Open/Close In'dication
' A red lightlindicates a valve open signal. This light is taken from
,s
- the close rotor limit. switch'which is set'-to actuate very close to-
the:end of valve closure. A green: light provides a valve closed
signal'.and is taken' from the open rotor limit switch actuation. The'
. greenLlight will turn off.when the MOV is in the full open position,
andethe red light-will turn off when the MOV is in the full closed--
position.- Whon both lights are'on,;the valve is in.an intermediate
- position.
At Calvert Cliffs Units 1 and 2, the licensee uses a 2 roter limit
switch assembly for; controlling M0V operation. ;The torque bypass
switch and' the indication light signals are taken fm. the' same rotors.
Any adjustment to the torque bypass switch will. affect the indica-
tion.
In a'similar.' manner. limit switch adjustment to get the correct
,
indication will-change the bypass switch' settings. Operators rely on
- the indication lights to' determine the valve status. .Any change.in:
.
limit switch' setting can influence MOV stroke time testing as well'as
valve position dependent interlocks and permissives. .This is an
unresolved item pending h,* review of the licensee's' actions to assure
.
that changes'to bypass switch settings do not' adversely affect' indica-
tion and' limit switch settings.
(50-317/89 .12-04; 50-318/89-12-04).
Thermal Overload Relay
1
.
Thermal overload relays are used to protect motor winding insulation
i;
. from' breakdown during overload conditions.
Devices used consist of
heaters at-the motor control center which trip a heat sensitive relay,.
the ' contacts of which either. interrupt current to the contactor closure
or.open the coil (which stops the motor) or initiate an overload alarm,
-or both. Where thermal overload rela /s stop operator. motor rotation
on' tripping, the heaters must either be sized to prevent inadvertently
stopping the motor or the overload relays must be. bypassed.when motor-
operation is important to safety.
They should also_ba sized to' protect
the motor windings from thermal damage.
Regulatory Guide 1.106, thermal
. overload protection for electric motors on motor operated valves .
provides guidelines on the design criteria for thermal ' overloads.
Designs that are being used at this time to el'rinate the threat of-
inadvertent motor trips include:
(1) removing the heaters or relay
contacts from use; (2) using the relay contacts for alarm only; (3)
bypassing the relay contacts during all oper., ting modes except when
a valve is being exercised for testing; (4) Lypassing the relay
'
contacts only during the presence of an automatic safety actuation
signal; and, (5) oversizing the thermal overloads.
I.
E__ _
-- -
.
_-
_
-
_
_--
--
- - -
{f
e1 o . ,.
.
H
w
1.,
At1Calvert Cliffs Units 1- and-2, the licensee utilizes the following
!
. general criteria for sizing the overload relays that are used in the
control circuit of all bulletin valves to protect the motor- without-
-compromising'the safety function.
1.
.A minimum of twenty minutes trip time.at fu'11 load current.
{
2.
'A ' maximum' of fifteen seconds and minimum off two: seconds trip
'!
E
time at locked rotor current. This allows at least 2 seconds
1
to unseat the valve and a maximum-of fifteen seconds to operate-
!
c
the valve under locked rotor condition.
During the review of the overload heater calculations, the inspector
obser_ved 'that the licensee sized the overload relays to trip between
1
a band of approximately 4.5 seconds minimum to a 15 seconds maximum
.{
locked rotor current' range.
Limitorque requires its motor manufacturers
to provide a minimum of 10-15 seconds allowable stall- time. According
j
to Limitorque,10 seconds locked rotor time for overload selection
gives the highest degree of motor protection, even though, 15 seconds-
locked rotor t,ime is considered adequate protection for the motor.
I
The licensee 3 elected the overload relay such that motor protection
j
and availability of the MOV is not compromised.
During the field
'
walkdown,:the inspector verified thermal overloads for four HPSI valves
for Unit 1.
The installation agreed with the required ratings
established.in the calculation.
The licensee determined that control room indication is not provided
to identify tripped overload relays. The licensee is reviewing this
- 3
issue to determine the need for- control room indication of tripped
j
f
4.3 Demonstration of Operability
~
i
This involves demonstrating the valve to be operable by testing the
!
valve under maximum differential pressure (AP) after changing the
'
individual valve settings, as appropriate; based on the design bases.
In the absence of testing with full differential pressure across-the
!
valve, a justification.is to be provided. The use of a Limitorque/
l
M0 PATS data base to set the torque switches for a particular type'of
!
valve is considered an acceptable alternative to differential
l
pressure testing, provided this type of valve has sufficient test
data to establish similarity.
'
The inspector noted that the licensee has not used signature tracing
)
methods to determine ti:.e traces of motor current, torque and limit
'
switch actuations and axial motion of the worm gear.
Lacking this
information the licensee cannot determine the actual available. thrust
,
developed by the motor at the maximum design bases differential pressure.
(
However, the licensee uses Limitorque information to calculate the
stem thrust and the required torque settings to seat and unseat the
valve.
'l
_ - _ - _
_ - _ _ _ _ _ - - - _ .
. _
- --
--
_ _ - .
_
. ,_ -
l :x
J
.:
..;
,
.-
8
'
'The MOVs subject to the requirements of the bulletinLwere. tested at .
the maximum Ap and at full flow for both units. .The' valves:were stroke.
tested using the "asLfound" switch settings' with.the maximum differential
^ pressure.(Ap). Additionally, the Unit 1 MOVs were tested lat a-reduced"
- voltage
- of.432 volts- (minimum 480V. bus voltage allowed by: tech specifi-
,
cations). . Unit;1; completed the differential pressure test twice:and
the.second test-for Unit 2.is' scheduled.for this outage. The. full
Ap- test-is scheduled every refueling outage. The inspector: verified'
the-test records. ' All MOVs operated properly'in both the~ open and-
shut directions with the maximum design bases differential pressure-
across the valve. -In five cases the HPSI system was not capable of-
producing maximum. design Ap.
(1310 psid'vs. 1313 psid required).
.For these. cases, the. difference in Ap was minimal. -'During the test,
the licensee took opening / closing time and starting and. running current'
to establish'the operability of the MOVs.
No changes'to the switch settings were required as a result of the
'
testing. However, some torque switch settings were changed, either
to increase the conservatism'in the settings or, to standardize settings
on similar MOVs in order to assist in long-term valve trending.
The'
'
inspector noted that the licensee performs a quarterly valve operability-
verification test consisting of valve cycling to provide additional
confidenceLof valve operability. The list of the bulletin' valves'and
their torque and thrust values are shown in attachment 3.
!
4.4 Maintenance and_ Procedures
1q
The bulletin requires that licensees prepare or revi.se procedures to
1
ensure that correct switch settings are maintained throughout the
life of the plant and also'to ensure that' applicable industry
recommendations 'are considered' in the preparation of the procedure.
~
The inspector reviewed the procedures and documents listed in Attach-
l
ments 1 and 2.
The licensee had revised existing-procedures for
maintaining the limit and torque switch settings.. The procedure
i
addressed the details on installing torque switches with the spring
pack in'the relaxed condition.
However, procedures were not provided
.
to specify the greasing levels and acceptable level / quantity of
,
grease for the-limit ~ switch gear assembly.
!
A walkdown was conducted to assess the adequacy of MOV maintenance and
to verify torque switch and limit switch settings. As Unit 1 was
.)
operating at full power, access to these valves was lir;ted.
However,
the inspector inspected three valves (MOV 653, 654 and 655) in the
HPSI system. The torque and the limit switch contacts appeared to be
set correctly, aligned, clean, and free from corrosion and pitting.
The inspector verified the control wiring to be in conformance with
the licensee documents listed in Attachment 2.
4
I
-_
- _ _ _ _
.
'
,
9
During the' procedure review, the inspector noted that no specific
criteria were provided to specify limit switch and bypass switch
settings to cut off the motor circuit.
Industry practice is to use
either the stem measurement or the hand wheel movement method to get
the desired limit switch setting.
Industry analysis indicated'that
the lack of information of proper limit switch settings and torque
switches was one of the causes of failures of MOVs.
During the walkdown, the inspector noted that '.he 2MOV653, 654 and
<
655 valve stems were without a trace of lubric tion. No procedural
'
requirements exist for SMB-00 and SMB-3 M0V actuators to specify the
frequency of inspections or to specify the criteria for stem lubrication
>
of the actuators to assure proper MOV operation.
I dustry experience
indicates that a lack of adequate lubrication of valve stem leads to
premature tripping of the operator because of excessive torque require-
l
ments. The above two examples constitute a violation of Baltimore
Gas and Electric Company Technical Specification, section 6.8.1, in
that no procedures were provided for these important maintenance
activities that can affect the performance of safety related
equipment (50-317/89-12-01; 50-318/89-12-01).
!
During the review of the test records, the inspector noted that at
>
the last refueling outage, several MOVs in Unit 1 exhibited potential
lubrication deficiencies for the main gear box assemoly (such as
potential degradation of grease and using different grease).
Pre-
ventive maintenance records, PM 2-52-MR8 thru 15 for the last outage
for Unit 2 indicated discoloration of the grease.
This is an indica-
'
tion of potential grease degradation.
During the current Unit 2
outage, tSe licensee stated that ten out of 12 Bulletin valves
exhibited similar lubrication deficiencies.
'
This issue of potential lubrication deficiencies for the main gear
box assembly is an unresolved item pending the licensee establishing
C
clear acceptance criteria for the lubricant, licensee determination
of the acceptability of the main gear box lubricant; and the
licensee's actions to correct unacceptable lubricant conditions
(50-317/89-12-02; 50-318/89-12-02).
During the walkdown, the inspector noticed that the torque switch
settings were nonconservatively set at 1.0 for both opening and
closing valve 2MOV653. The setpoint file manual and the licensee's
final response to the Bulletin specifies 1.5 for both opening and
closing the valve. This discrepancy was brought to the attention of
the licensee during the inspection and at the exit meeting.
The Baltimore Gas and Electric Company Quality i.ssurance policy,
Revision 19, Section 18.5 requires that activities affecting quality
I
shall be prescribed by procedures and shall be accomplished in
'
accordance with these procedures.
This finding constitutes a
violation of 10 CFR 50 Appendix B Criterion V, failure to follow
!
procedures (50-317/89-12-05; 50-318/89-12-05).
'
l
i
_ , , _ . _ _ _ _ _ _ - - - - - - .
- - - - - - - ' - - - -
_ _ _ _ - - - _
-
.
- ,..F
.
10
-
The inspector reviewed the licensee's training program.
The mainte-
nance personnel have attended the Limitorque training presented by
power safety international and also undergo in-house training. The
training consists of operation, disassembly and assembly of MOV,
setting torque and limit switches and hands on training. .Since the
licensee'did not have any diagnostic equipment, technicians are not
trained in this area.
The inspector interviewed an electrician who
was responsible for the MOV maintenance. He was determined to be
knowledgeable in the maintenance aspects of MOVs.
The inspector
observed that the existing training requalification interval is three
years.
'The inspector reviewed the post maintenance testing of MOVs.
The
licensee is currently timing the valve stroke and monitoring the
current reading to establish the operability of MOVs after minor and
mid-level maintenance.
Following major maintenance, full op stroke
{
testing is performed to establish MOV operability.
The licensee is
currently reviewing their valve testing program to determine if there
is a need for full Ap stroke testing after mid-level maintenance.
5.0 Conclusions
The licensee has not addressed all of the significant aspects of the bulletin.
A deficiency was noted during the walkdown regarding a torque switch setting.
Maintenance procedures were not provided to specify the limit switch settings.
Maintenance deficiencies were observed in the lubrication area.
Surveillance,
i
preventive, and post maintenance procedures were not descriptive.
During the. inspection, the inspector observed that the licensee lacked
dedicated MOV maintenance personnel to address the MOV program. They now
have a dedicated project manager to oversee the program. The licensee
stated that they are in the process of implementing an extensive plan that
!
should address concerns regarding the existing MOV maintenance' program.
!
!
The inspector concluded that since all the bulletin valves were tested
with full differential pressure across the valve, there is reasonable
assurance that these valves can perform thcir safety function.
Based on
the review of the licensee's LER's and PM's, no MOV failures were observed
during the past two years.
6.0 Unresolved Items
Unresolved items are matters fce which more information is required in
j
order to ascertain whether they are acceptable, violations, or deviations.
j
Three unresolved items are discussed in sections 4.2 and 4.4 of this report.
i
7.0 Exit Interview
l
At the conclusion of the inspection on May 5, 1989, the inspectors met
i
with the licensee representatives, denoted in section 1.0.
The inspector
{
summarized the scope and findings of the inspection at that time,
No
{
written material was given to the licensee during this inspection.
l
_- _ - - . _.
-- _ - - _ -
.
.
..
,
o,
'
Attachment -1
REFERENCES
'1.
. Letter from Mr. J. A. Tiernan (BG&E) to Dr. T. E. Murley (NRC), dated May
15, 1986.
i
2.
Letter from Mr. E. C. Wenzinger (NRC) to Mr. J. A.' Tiernan (BG&E), dated
i
July 29,1987, Request for Additional Information
i
3.
Letter from Mr. J. A. Tiernan (BG&E) to NRC Document Control Desk dated
September 1, 1987
4.
Letter from Mr. J. A. Tiernan (BG&E) to NRC Document Control Desk dated
January 28, 1988.
PROCEDURES
Procedure No. FTE-41, Rev 6. Insulation Resistance Testing
Calvert Cliffs Instruction 2051, Rev 0 - Setpoint Control Procedure
STP No. 066-2 Rev 0 - Quarterly Valve Operability Verification - Shutdown
GEN-19, Rev 5 - Disassembly and assembly of limitorque actuators SMB-0, SMB-1,
SMB-2 and SMB-3
065-1, Rev 32 - Quarterly Valve Operability Verification.
GNE-18, Rev 1 - Instruction and Maintenance of timitorque Actuator SMB-00
FTE-47, Rev 6 - Functional Test Procedures - Electrical Motor Operated Valve
Test Procedure
Quality Assurance Policy Rev 19
STP No. 0-103-1 (Unit 1) - Surveillance Test Procedure - HPSI MOV Maximum
Differential Pressure
l
STP No. 0-103-2 (Unit 2) - Surveillance Test Procedure - HPSI MOV Maximum
Differential Pressure
l
4
i
_ _ _ _ _ _ _ _ _ _ . . _ - - - - - - - - - - _ - - - - - - - - -
-
- _ _ - - _ _ _ _ _ _
_-
j.
. ' .
-
,
,
' '
Attachment-2
Documents Reviewed
STP-066-1 - Maximum Differential Pressure Test Record
Maintenance Order No. 206-294-277A - Perform Testing on SI MOV
Manual. #14 - Set poi:1t file for MOV torque switch settings
Calculation No. E-81-1 - Overload heater selection
Bechtel File No. 1475/2703 - MOV overload relay calculations
BG&E Drawing No. 61-014B Shet 4 Rev 23 - Relay Settings, MCC 104R
BG&E Drawing No. 61-0148 Sht 48, Rev 25 - Relay setting, MCC 114R
BG&E Drawing No. 63-014-B, Sht 4, Rev 24 - Relay settings, MCC 204R
BG&E Drawing No. 063-014B, Sht 48, Rev 22 - Relay settings, MCC 214R
BG&E Drawing No., 61-076-8 Sht 23, Rev 10 - Reactor Safeguards MOVs 616, 626;.
636, 646
i
BG&E, Drawing No. 61-0768,
Sht 22, Rev 10 - Reactor Safeguards MOVs 615, 625,
'635, 645, 617, 627, 637 and 547
BG&E, Drawing No. 61-076-B, Reactor Safeguards MOV 656 Sht 21, Rev 7
'
BG&E, Drawing No. 61-076-B, Sht 19, Rev 10 - Reactor Safeguards, MOVs 653,
!
654, 655
BG&E, Drawing No. 63-076-B, Sht 23A, Rev 0 - Reactor Safeguards MOVs 616, 626,
636, 646
Motor Operated Valve Safety Data
PM No. 1-52-E-2R-3, Safety Injection MOVs
FCR No. 89-10 - Limitorque Motor Operators
PM No. 1-52-M-R-16, 18 - SI, 1-MOV-653, 654
PM No. 2-52-M-R-8 thru 18 and 21 - Safety Injection MOVs
PM No. 1-52-E-2R-6 - Preventive Maintenance for Valves 653, 654, 658, 659,
660, 662
PM No. 1-52-E-2R-7 - Preventive Maintenance for Valves 665, 656, 663
l
PM No. 2-52-E-2R-6 - Preventive Maintenance Safety Injection MOVs
i
__ - _ _ _ _
-
e.
,:...
.
..
.
g.
g
,
x
'
Attachment-2
Documents Reviewed (Continued)
LERs
LER 79-11/3L, 2 LER 7787
LER 79-44/3L, 1 LER 8416
LER 77-87/3L, 1 LER 7911
LER 80-01/3L
l
l
i.
L_ -- - - - - -
M
sg
~
- '
. en
E ' '
-
- 5
.
\\ \\
mui
oqt
333333332424333333332424
crt
'
.
-
-
'
eoe
-
an
- .i
-
)
t
int
.
.e
e
ga
.Ms
.
.
-
.
n
u
g
t
.e
mu
\\\\\\\\h\\\\4 - % - %\\
\\ \\
\\
k
k
ro
oq
1111II111212111i1111121E
P
it o
cr
sf s
.,
.eo
.
-
- -
'
a
e i
t
tth
-
l
st
e
ye
D
btr
g
o
.nt
- : -
.
.
-
l
dPf
eA
mis
555555557070555555557070
l
otu
000000002121000000002121
u
h
d
car
999999998787999999998787
F esl e
eeh
777777779494777777999494
gill
RST
-
2
2
.
2
2
t al uu
L
~
atbFd
ua( e
-
'
h
dot
h
L
- * *
5*
.* * :
1
5 - '
1-
. 5
+ +
5
c
e
sec
A
555755555052555525555052
t
tt evs
NC
i
ss
l
I
111111111312111111111312
w
eayas
-
S
Tl tVi
F
- -
5
-
5
/ i
e
d gl 12
55.5555555052555555555052
5
u
ani
/ 0
T
111111111312111111111312
q
+ ibtt
r
e
sraii
'.
~
-
ons
uarnn
5555
5 -
5
5
5
5
T e o 5 j d e, U U
T
272755750502555525005252
pl/ d
SC
= OCTA
0,
-
E
212121211212111111221212
5=
=
T
-
- ~
. _
T0C*
+
.
-
/
&
.5
_
5
5
5
5
5
5
020555750202555555005252
/ O
T :
122121121212111111111212
' -
s
. --
L
.e
00000000000050505000500' 0
gr
T
424231311311222221212411
i u
e
EAT
333333333333333333333333
ss
g
T
O
111111111111111111111111
n
ps
a
ee
e
t
'3
.
.
^
L
psnr
u
555555443333555555443333
A
OoiP wo
T
999999991111999999991111
N
l
o
N
a
222222223333222222223333
I
o C s gl t
E
C
1. -11111111111111111111111
F
t
enf s
M
S
-
ori
a
H
I
-
-
5
dt ushl
C
S
555555443333555555443333
/
e
sot
A
A
99P999991111999999991111
T
snsli g
T
B0
222222223333222222223333
loeeC wn
T
111111111111111111111111
pr
i
A
-
-
-
COpeer
'
= =llvru
ad
C
V . V
V
V
l a
FN
VVVVVVVVI VIVVVVVVVVVIVIV
0CAV
VU
IIIIIIII OIOIIIIIIIIIOI DI
DT
LLLLLLLLPTPTLLLLLLLLPTPT
~
-
.
e
n
~
-
-
v
lvh o
e
gi
.
111111111111111111111111
.l
ait
R
666666662424666666662424:
ca
d ta c
- : : : : : : : : : : : : : : : : : : : : : :
nV me
e
G
-
u
avnej
R
888888886565838888886565
P
F nel oh n
-
I
333333333333333333333333
oraitI
.
O
A
eitVt
A
-
'
T
lvt s
any
L
annl
R
'
-
E
al woo i t
E
-
e
P
000000000005000000000000
D
V ooisef
000000000000000000000002
sDtI ra
P
777777777774777777777777
T
nI
a
aS
ER
111111111113111111111111
S
g
pl n
p m oi s e
V
-
E
i
L
.
-
T
sousaer
A
555555555
5
555555555
5
eoPI rvum
V
222222222020222222222020
DL
Tl se
000000000106000000000406
=
ast
000000000001000000000001
= ves
M
- - - - - - - - - - - - - - - - - - - - - - - -
V
ry
F
FVI
Vl PS
-
-
V
VI O
Il
000000000000000000000000
D
DLP
TA
000000000000000000000000
555555559995555555559995
e
R
11111111
111111111
1
uq
'
r
c
R
o
i
5
222222224646222222224646
O
. t
t
T
ti
a
A
cmBrR
.
R
aiMo
s.
777777778888777777778888
L
f LSt r
b
555555555555555555555555
P
u
oa
666666666666666666666666
O
ne
Me
I
444444444444444444444444
ar
G
n
L
3333333332 s.3333333333333
E
Ha
=
i
D
V
=
M
PPPPPPPPP' ",PPPPPPPP9PPPP
L
=L
M
g
A
L
PR
n
E .
-
V
MA
it
V
L
LLLLLLLLAAAALLLLLLLLAAAA
AI
GGGGGGGGGGGGGGGGGGGGGGGG
.
ra
V
- '
t
.
- M
VVVVVVVVVVVVVVVYVVVVVVVV
c
n
y
s
isrl
iN
e
eae
uA eb eeh md
.
nL pot zcio
D
676767673456676767673456
aE yl ainrM
122233445555112233445555
MVTGGSiP
I
S66666666666666666666666
E
=
P
VVVVVVVVVVVVVVVVVVVVVVVV
V
= = ==
=
M
OOOOOOOOOOOOOOOOOOOOOOOO
L
L
O
MMMMMMMMMMMMMMMMMMMMMMMM
A
LA
O
'
.
.
-
C
I11III1I11112222Z2222222
V
MVTGG5
. -
'
f
lll