ML20154F193

From kanterella
Jump to navigation Jump to search
Insp Repts 50-317/88-20 & 50-318/88-20 on 880817-19. Violations Noted.Major Areas Inspected:Events Associated W/ Higher than Anticipated Worker Exposure on 880621
ML20154F193
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/08/1988
From: Loesch R, Shanbaky M, Weadock A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20154F178 List:
References
50-317-88-20, 50-318-88-20, NUDOCS 8809190284
Download: ML20154F193 (6)


See also: IR 05000317/1988020

Text

,

_ _ - - - - _ - - - - _ - - - - - - - - - - - - - - - -

4

.-

.

.

,

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report Nos.

50-317 88-20

50-31 88-20

Docket Nos.

50-317

50-318

License Nos.

DPR-53

Category

C

DPR-69

Licensee:

Baltimore Gas and Electric Company

P.O. Box 1475

Baltimore, Maryland 21203

Facility Name:

Calvert Cliffs Nuclear Power Plant, Units 1 and 2

Inspection At:

Lusby, Maryland

Inspection Conducted:

August. 17-19, 1988

Inspectors:

8. (1/u [

4[6 [I5'

A. Weadock, Radiation Specialist

date

S WA

9hhr

R. Loerch, Radiation Specialist

date

Approved by:

4#. C

[M

9///I

-

1. Shanbaky,SectionChief, F4cilities Radiation

date

Protection

Inspection Summary:

Inspect'.on conducted on August 17-19, 1988 (Combined

Inspection Report Nos. 50-317/88-20,50-318/88-20).

Areas Inspected: Unannounced, reactive inspection of events associated with a

higher than anticipated worker exposure on June 21

1988.

This exposure

occurredduringroutinemaintenanceintheUnitIdux111aryBuilding27 foot

elevation valve alley.

Results: One violation was identified:

failure to perform an adequate survey

(see section 3.3).

8909190284 880909

gDR

ADOCK0500g7

.-

.

.

,

.

DETAILS

1.0 Persons Contacted

1.1 Licensee Personnel

  • A. Anuje

Supervisor, Quality Assurance (QA)

  • J. Carroll

General Supervisor, QA

  • C. Cruse

Manager, Nuclear Engineering Support

Manager'ical Controls Operations Supv. Quality Assurance

  • R. Douglass

Radiolog

  • J. Lenhart
  • J. Lohr

Assistant General Supervisor, Operations

  • N. Millis

Radiation Safety General Supv.

  • W.

Putnam

Senior QA Auditor

  • D.

Shaw

Licensing

ineer

  • C. Sly

Licensing

ineer

  • L. Smialek

Radiation

trol and Support Asst. Gen. Supv.

  • A. Vogel

Technical Training Supv.

1.2 NRC Personnel

  • H. Slosson

NRR Project Manaaer

  • D. Trimble

Senior Resident Inspector

  • Attended the exit interview on August 19, 1988.

Other licensee personnel were also contacted during the course of this

inspection.

2.0 Purpose

The purpose of this unannounced reactive inspection was to review events

associated with the higher than anticipated worker external exposure which

occurred on June 21, 1988.

This exposure occurred during routine

maintenance activities in the Unit 1 Auxiliary Building 27 foot elevation

valve alley.

No regulatory exposure limits were exceeded during this

event.

3.0 Higher Than Anticipated Exposure Event

The inspector evaluated the licensee's identification of and response to

the above higher than anticipated exposure event by the following methods:

- discussion with involved personnel,

-

.

.

,

.

3

- tour of the Unit 127' valve alley,

- review of associated radiological surveys, log entries, and Calvert

7

Cliffs Report (CCR),

- review of Special Work Permit (SWP)"88-003, "Inspections and Minor

Maintenance in High Radiation Areas ,

- review of General Orientation Training lesson plan,

- review of the following procedures:

o RSP 1-101, "Radiological Surveys",

o RSP l-201, "SWP Preparation".

Within the scope of the above review, one violation, concernirg a failure

to perform an adequate survey, was identified and is discussed below.

3.1 Event Summary

On June 21, 1988, two maintenance workers entered the Unit 1 27' valve

alley, a locked and posted High Radiation Area (Special Work PermitHRA), to lu

No.68-003, "Inspections and Minor Maintenance in High Radiation Area (SWP)

rod linkage fittings. The workers signed in on

s."

leted

The most recent routine radiological survey for the valve alley, comp /hr at

on June 9,1988,k location inside the valve alley. indicated general area radiation dos

the presumed wor

The valve alley was

also posted as a contaminated area, with the boundary and step-off pad

located just inside the locked doorway.

ThetwoworkersmetwiththeareaRadiationSafetyTechnician(RST)lvewho

performed a brief, "spot check" survey inside the doorway of the va

alley to verify the previous survey readings. The two workers equipped

with their own survey meter,

then entered the valve alley and, worked for

-

a) proximately 5 minutes. Anticipated exposure for this work entry was less

t1an 15 millirem. Upon exit, the workers read their pocket dosimeters

which indicated they had received 60 and 130 millirem, respectively.

The

workers notified the area RST.

in the valve alley and identified a

The RST 1mmediately performed a survey /hr located on a CVCS valve and

hot spot reading approximately 50-70 R

adjacent piping in the 13 CVCS ion exchanger discharge line, approximately

five feet from the work area. Although not recorded (see section 3.3),

survey measurements made in the work area adjacent to one of the

chest-level linkage fittings ranged from 800-2000 mR/hr, approximately

15-40 times the assumed dose rates. The RST then posted the valve alley as

an exclusion area, restricting all access.

Subsequent surveys performed by

a Radiation Control supervisor

.

-

.

,.

.

4

identified contact dose rates ranging from 30-70 R/hr on the valve and

short segment of CVCS piping, with 18 inch dose rates from 3-5 R/hr.

3.2 Licensee Followup

Licensee follow-up actions to the above event included the following:

Flush of the CVCS valve and piping on July 7, 1988.

-

-

Immediate initiation of an investigation into circumstances leading to

the event. The investigation was conducted by a QA auditor with

previous health physics experience.

The investigation and findings

which was submitted

to the p'lant safety review committee (PSORC CCR) August 4, 198

were documented in a Calvert Cliffs Raport

on

The

auditor s review included interviews with t e maintenance workers, the

RST, review of related surveys, and observation of the work area.

The CCR was not submitted to PSORC until August 4, 1988, approximately

-

six weeks after the incident. At that time, there was disagreement

between the CCR investigator and the RC staff as to whether an

inadequate survey had been performed.

It was not until the Assistant

General Supervisor, Radiation Control and Support, interviewed the

involved RST during the week of the NRC inspection, that the RC staff

concurred with the CCR.

The licensee's Radiation Safety Technicians were not briefed

-

concerning details of the event until the week of the inspection.

As of August 19, 1988, the RC staff had not independently interviewed

-

the two mi.intenance workers concerning the event. NRC interview of the

two workers identified significant discrepancies between the accounts

of the RST and the workers.

Followup surveys of the valve alley were not performed by the RC staff

-

until August 15, 1988, several weeks after the valve was flushed.

3.3 NRC Review

10 CFR 20.201, "Surveys", requires the licensee to make such surveys as are

necessary to comply with the regulations in 10 CFR 20 and are reasonable to

evaluate the extent of radiation hazards that may be present.

The

inspector determined through interview of the involved RST that the

pre-work survey performed on June 21, 1988, was made just inside the

doorway to the valve alley, rather than in the area in which the

maintenance workers would be working, approximately six feet away.

Subsequent measurements identified that area dose rates in the work area

were much greater than antici)ated and that the presence of a significant

radiation hazard (50-70 R/hr lotspot) was unknown at the time work was

initiated.

Failure to perform an adequate survey of the work area

constitutes an apparent violation of 10 CFR 20.201 (50-317/88-20 01).

.

_ _ _ _ _ _ _ _ _ _ _ _ _ _

-

-

.

.

5

The inspector noted the licensee's CCR identified the pre work survey as

inadequate, and therefore this violation potentially qualifies for

enforcement discretion as a licensee-identified violation as provided for

in 10 CFR 2, App. C.

Qual;fication for such discretion requires the

apparent violation to meet several conditions, including the requirement

that measures to prevent recurrence be completed within a reasonable period

of time.

The inspector stated that mitigation of the violation was not a propriate

as the QA auditor's findings relative to the inadequate radiolo ical survey

were being refuted by the RC group rather than initiating promp and

aggressive action to prevent recurrence.

The licensee stated their immediate corrective actions were directed at

posting and access control of the valve alley and hot spot and that these

actions were done in a timely fashion. The inspector acknowledged the area

was quickly and effectively controlled. The inspector also stated that the

poor survey practices exhibited, whether practiced on an individual or a

widespread basis, represented a significant concern in radiological work

control which should have been quickly addressed and corrected.

The following additional concerns were also identified during this review:

The use of a broad-scope, routine SWP for work in the valve alley was

-

inappropriate.

Licensee procedure RSP 1-201, section 3.6, states that

routine SWPs are designed to allow access to controlled areas for

activities involving minimal or clearly defined radiological hazards.

The inspector noted that the valve alley is an area with the potential

for rapid and dramatic changes in area dose rates, based on radwaste

operations. The licensee indicated that the use of a routine SWP for

this and other HRAs would be evaluated. The licensee also stated that

the use of additional controls over work in HRAs (i.e., continuous

coverage) was being evaluated.

The pre-job surve performed by the RST was not documented. As this

-

survey is the sub eet of one cpp(arent violation, no additional

citation against 0 CFR 20.401

i.e., failure to maintain survey

records

is warranted.

The inspector noted however add

examples)ofweaknessesinsurveydocumentatIonpractices.itional

Area dose

rate measurements in the ) resumed work location were apparently taken

after identification of tie hotspot and were stated to the inspector

however, these measurements

asbeing800and2000mR/hrrespectivelylsorecentlyimplementedthe

were not documented. The licensee has a

use of a "work ticket" form that accompanies the work party and

requires the area technician to document survey measurements on the

form.

The inspector noted the use of this unproceduralized form is

inconsistent; although it was used for similar activities in the valve

alley on previous days it was not used on June 21, 1988, for the

subject incident.

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _

.. ..

,

.

.

6

NRC interview of the RST and the two workers identified significant

-

inconsistencies concerning the level of the pre-job briefing and the

scope of work to be performed. A specific inconsistency of concern is

whether it was known that the workers would be climbing pipes in the

overhead, an unsurveyed area to reach two fittings 13 feet off the

floor. AsoftheweekofthIsinspectionthelicenseehadnot

followed up on this concern.

The licensee indicated that the investigation into activities

surrounding the incident was still continuing and the above concern

would be evaluated.

No formal dose assessment had been performed by the licensee to

-

evaluate whether the worker's dosimetry placement was adequate to

monitor exposure to the unanticipated hot spot, and whether

adjustments to the recorded dose were necessary.

The licensee

indicated that the survey of the valve performed by tb3 RC supervisor

on June 21, 1988, indicated that the hot spot represented a whole body

exposure source to the workers and was adequately monitored by the

worker's TLDs. This was due to the consistency in dose rates, and the

valve's location and inaccessibility. No follow up to this initial

assessment, however, such as interviewing the workers concerning their

location or survey of the valve alley general areas prior to the

hotspot flush was performed. The inspector concluded, based on visual

inspection of the valve alley that the licensee's dose assessment of

60 and 130 mrem for the two workers was appropriate. The licensee

stated that the maintenance workers would be interviewed concerning

their movements to determine if the licensee's initial assessment

remained valid.

Licensee evaluations and any additional actions addressing the above

concerns will be reviewed in a subsequent inspection.

4.0 Exit Meeting

The inspector met with licensee re)resentatives, denoted in Section 1.0 of

this report, on August 19, 1988. Juring this meeting the inspector

summarized the purpose, scope and findings of the inspection.

l

. _ .