Monthly Operating Rept for Jan 1996 for Wnp Unit 2.W/960209 Ltr
ML17291B229
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 01/31/1996
From: EMBREE D G, PARRISH J V
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GO2-96-023, GO2-96-23, NUDOCS 9602210250
Download: ML17291B229 (8)


Text

CATEGORY j.REGULATOR INFORMATION DISTRZBUTIONGSTEM (RIDE)ACCESSION NRR.9602210250 DOC.DATE:,96/01/31, NOTARIZED:

NO DOCKET FACIL:5G-4

/ŽQPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH.NAMED AUTHOR AFFILIATION EMBREE,D.G.

Washington Public Power Supply System PARRISH,J.V.

Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION k

SUBJECT:

Monthly operating rept for Jan 1996 for WNP Unit 2.W/960209 ltr.DISTRIBUTION CODE: ZE24D COPIES RECEIVED:LTR i ENCL L SIZE: TITLE: Monthly Operating Report (per Tech Specs)NOTES: RECIPIENT ID CODE/NAME, PD4-2 PD INTERNAL: 8R ILE CENTER RG EXTERNAL: LITCO BRYCE,J H NRC PDR COPIES LTTR ENCL 1 1 10 10 1 1 1 1 1 1 1 1 , RECIPIENT ID CODE/NAME CLIFFORD,J AEOD/SPD/RRAB NRR/DRPM/PECB NOAC COPIES LTTR ENCL 1 1'1 1 1 1 1 NOTE TO ALL"RIDS" RECIPIENTS:

'4 PLEASE HELP US TO REDUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOM OWFN 5D-5(EXT.415-2083)TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 19 ENCL.19 ai WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O.Box 968~3000 George Washington Way~Richland, Washington 99352 February 9, 1996 G02-96-023 Docket No.50-397 U.S.Nuclear Regulatory Commission Document Control Desk Washington, D.C.20555 Gentlemen:

Subject:

WNP-2 OPERATING LICENSE NPF-21 MONTHLY OPERATING REPORT JANUARY 1996 Transmitted herewith is the Monthly Operating Report for the month of January 1996 as required by Technical Specification 6.9.1.6.Sincerely, J.Parrish anaging Director (Mail Drop 1023)JVP:DGE CC: LJ Callan, NRC R IV NRC Sr.Resident Inspector (927N)INPO ANI Library Utility Data Institute BPA (399)0042 96022i0250 960i31 PDR ADGCK 050003'P7 R PDR t..t 4 A$a I

~OPERATING STATUS REPOR'1 for WNP-2 Date: February 1, 1996 2.3.4.5.6.7.8.9.3486 1199 1153 1145 1099 none Docket: 50-397 Reporting Period: JANUARY 1996 Outage+On-line Hours: 744.0 Utility Contact: David G.Embree (509)377-8448 Licensed Thermal Power (MW,): Nameplate Rating (Gross MW,): Design Electrical Rating (Net MW,): Maximum Dependable Capacity-summer (Gross MW,): Maximum Dependable Capacity-summer (Net MW,): If changes occur above since last report, give reasons: 10.11.12.13.14.15.16.17.18.19.20.21.22.23.24.25.Report Period Hours Hours Reactor Critical Rx Reserve Shutdown Hours Hours Generator On-Line Unit Reserve Shutdown Hours Gross Thermal Energy (MWH)Gross Electrical Energy (MWH)Net Electrical Energy (MWH)Unit Service Factor Unit Availability Factor Unit Capacity Factor (MDC Net)Unit Capacity Factor (DER Net)Unit Forced Outage Rate Forced Outage Hours Power to which restricted, if any (Net MW,): about 99%for January Reasons for restrictions, if any: administrative limit placed on plant operations until special feedwater flow test results were validated, which resulted in about a 1%decrease in power.Revised electrical ratings in the process of being re-calculated.

MONTH YEAR CUMULATIVE 744.0 744.0 97,592.2 744.0 744.0 70,379.8 0.0 0.0 744.9 744.0 744.0 67,994.5 0.0 0.0 958,8 2,416,449 2,416,449 202,873,999 827,600 827,600 68,405,080 799,679 799,679 65,557,997 100.0%100.0%69.7%100.0%100.0%70.7%97.8%97.8%61.5%93.2%93.2%60.7%0.0%0.0%10,9%0.0 0.0 8,319.7 26, Shutdowns scheduled over the next 6 months (type, date, duration):

27.If currently shutdown, estimated startup date: Refueling, 4/13/96, 55 days NA Note: Cumulative Unit Capacity Factors (MDC&, DER)are calculated with weighted averages.

AVERAGE DAILY UNIT POWER LEVEL REPORT PERIOD: JANUARY 1996 DOCKET NO.: UNIT: DATE: COMPLETED BY: TELEPHONE:

50-397 WNP-2 February 1, 1996 D.G.Embree (509)377-8448 DAY AVERAGE DAILY POWER LEVEL (Net MWe)AVERAGE DAILY POWER LEVEL DAY (Net MWe)10 12 13 14 15 1159 1156 1148 1159 1159 1157 1156 1158 1157 1152 1154 1083 693 688 820 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1049 1157 1155 1132 692 687 1045 1152 1155 1160 1159 1153 1157 1152 1155 1162 INSTRUCTIONS On this form, list the average daily unit power level in MWe (net)for each day in the reporting month.Compute to the nearest whole megawatt.These figures will be used to plot a graph for each reporting month.Note that when maximum dependable capacity is used for the net electrical rating of the unit, there may be occasions when the daily average power level exceeds the 100%line (or the restricted power level line).In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

5 g r, UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT PERIOD: JANUARY 1996 DOCKET NO.: 50-397 UNIT NAME: WNP-2~.DATE: February 1, 1996 COMPLETED BY: D.G.Embree TELEPHONE:

(509)377444$No.Date Type Hours Reason Method LER Number System Component Cause and Corrective Action To Prevent Recurrence 9641 1/12/96 S 97.0 H NA ZZ ZZZZZZ Economic dispatch goal following) at the request of~the BPA.9642 1/19/96 S 68.5 H NA ZZ ZZZZZZ Economic dispatch (load following) at the request of the BPA.

SUMMARY

At the beginning of the month, the plant was operating near full power.The plant was placed in economic dispatch goad~following) at the request of the BPA for a portion of the month.The plant returned to full power operation at the end of the month, TYPE F-Forced S-Scheduled REASON A-Equipment Failure B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training&License Examination F-Administration G-Operational Error H-Other METHOD 1-Manual 2-Manual Scram 3-Auto Scram 4-Continued 5-Reduced Load 9-Other SYSTEM&COMPONENT NUREG4161 Exhibits F&H

~~'