ROP 16 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 & 3 (Report 05000277/2015006 & 05000278/2015006)
ML16060A376
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 03/02/2016
From: Schroeder D L
Reactor Projects Region 1 Branch 4
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
SCHROEDER, DL
Shared Package
ML16039A098 List:
References
IR 2015006
Download: ML16060A376 (5)


Text

March 2, 2016

Mr. Bryan Hanson Senior Vice President, Exelon Generation President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT: ANNUAL ASSESSMENT LETTER FOR PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 (REPORT 05000277/2015006 AND 05000278/2015006)

Dear Mr. Hanson:

On February 11, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Peach Bottom Atomic Power Station (PBAPS) Units 2 and 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2015 through December 31, 2015. This letter inspections at your facility. The NRC determined that overall, PBAPS Units 2 and 3 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at PBAPS Units 2 and 3 during the most recent quarter was within the Licensee inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through December 31, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to ROP baseline inspections, the NRC will perform Inspection Procedure (IP) 60855.1, nstallation at Operating Plants.The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In response to the accident at Fukushima, the Commission issued Order EA-12-Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-s with Regard to Reliable Spent remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The audit was completed for PBAPS Units 2 and 3, and the information gathered will aid staff in development of the Final Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing TI 2515-Instrumentation Orders and Emergency Preparedness Communications/Staffing/Multi-Unit In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 610-337-5262 with any questions you have regarding this letter.

Sincerely,/RA/ Daniel L. Schroeder, Chief Division of Reactor Projects Projects Branch 4 Docket Nos. 50-277 and 50-278 License Nos. NPF-44 and NPF-56

Enclosure:

Peach Bottom Inspection/Activity Plan cc w/encl: Distribution via ListServ

ML16060A376 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP RI/DRP NAME ATurilin/ AT BSmith/ BS via email JHeinly/ JH via email DSchroeder/ DLS DATE 02/25 /16 02/ 25 /16 02/24 /16 02/29 /16 Page 1 of 202/24/201616:00:45Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SitePeach BottomInspection / Activity Plan01/01/2016-12/31/20177111117T-PERMANENT PLANT MODIFICATIONS3 2, 3 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T01/25/201601/29/2016 2, 3 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T02/08/201602/12/2016EP-EP EXERCISE EVALUATION4 2, 3 IPExercise Evaluation711140104/25/201604/29/2016RS1234-HP INSPECTION1 2, 3 IPRadiological Hazard Assessment and Exposure Controls71124.0103/06/201603/10/2016 2, 3 IPOccupational ALARA Planning and Controls71124.0203/06/201603/10/2016 2, 3 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0303/06/201603/10/2016 2, 3 IPOccupational Dose Assessment71124.0403/06/201603/10/2016RS567PPI-HP TEAM INSPECTION3 2, 3 IPRadiation Monitoring Instrumentation71124.0506/06/201606/10/2016 2, 3 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0606/06/201606/10/2016 2, 3 IPRadiological Environmental Monitoring Program71124.0706/06/201606/10/2016 2 IPRETS/ODCM Radiological Effluent Occurrences71151-PR0106/06/201606/10/20167111107T-TRIENNIAL HEAT SINK1 2, 3 IPHeat Sink Performance7111107T06/13/201606/17/20163/20EXAM-PEACH BOTTOM INITIAL EXAM4 2 FY-17-PB INITIAL OPERATOR LICENSING EXAMU0194202/20/201702/24/2017 2 FY-17-PB INITIAL OPERATOR LICENSING EXAMU0194203/20/201703/31/20177111108G-PB U2 INSERVICE INSPECTION1 2 IPInservice Inspection Activities - BWR7111108G10/31/201611/04/2016RS1234PI-HP INSPECTION1 2, 3 IPRadiological Hazard Assessment and Exposure Controls71124.0110/31/201611/04/2016 2, 3 IPOccupational ALARA Planning and Controls71124.0210/31/201611/04/2016 2, 3 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0310/31/201611/04/2016 2, 3 IPOccupational Dose Assessment71124.0410/31/201611/04/2016 2, 3 IPOccupational Exposure Control Effectiveness71151-OR0110/31/201611/04/20167111111B-PB REQUAL INSP WITH P/F RESULTS2 2, 3 IPLicensed Operator Requalification Program7111111B03/06/201703/10/2017CBDI-COMPONENT DESIGN BASIS INSPECTION6 2, 3 IPComponent Design Bases Inspection711112101/30/201702/03/2017 2, 3 IPComponent Design Bases Inspection711112102/13/201702/17/2017 2, 3 IPComponent Design Bases Inspection711112102/27/201703/03/2017This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

Page 2 of 202/24/201616:00:45Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SitePeach BottomInspection / Activity Plan01/01/2016-12/31/2017EP-EP PROGRAM INSPECTION1 2, 3 IPAlert and Notification System Testing711140203/27/201703/31/2017 2, 3 IPEmergency Preparedness Organization Staffing and Augmentation System711140303/27/201703/31/2017 2, 3 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140503/27/201703/31/2017 2, 3 IPPerformance Indicator Verification7115103/27/201703/31/201771152B-PI&R BIENNIAL2 2, 3 IPProblem Identification and Resolution71152B03/13/201703/17/2017 2, 3 IPProblem Identification and Resolution71152B03/27/201703/31/2017RS12-HP INSPECTION1 2, 3 IPRadiological Hazard Assessment and Exposure Controls71124.0103/27/201703/31/2017 2, 3 IPOccupational ALARA Planning and Controls71124.0203/27/201703/31/2017ISFSI-ISFSI LOADING CAMPAIGN INSPECTION1 2, 3 IPOperation Of An ISFSI6085505/08/201705/12/2017 2, 3 IPOperation of an Independent Spent Fuel Storage Installation at Operating Plants60855.105/08/201705/12/2017RS34-HP INSPECTION1 2, 3 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0305/08/201705/12/2017 2, 3 IPOccupational Dose Assessment71124.0405/08/201705/12/2017 2 IPRETS/ODCM Radiological Effluent Occurrences71151-PR0105/08/201705/12/201771124.08-RADWASTE1 2, 3 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0807/17/201707/21/2017RS123-HP INSPECTION1 2, 3 IPRadiological Hazard Assessment and Exposure Controls71124.0110/23/201710/27/2017 2, 3 IPOccupational ALARA Planning and Controls71124.0210/23/201710/27/2017 2, 3 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0310/23/201710/27/2017 2 IPOccupational Exposure Control Effectiveness71151-OR0110/23/201710/27/20177111108G-U3 INSERVICE INSPECTION1 3 IPInservice Inspection Activities - BWR7111108G10/30/201711/03/2017This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.