MONTHYEARIR 05000261/19980031998-06-0909 June 1998 Errata to Notice of Violation of Insp Rept 50-261/98-03, Conducted on 980105-09.Correction Reflects More Accurately That Licensee Actions Taken to Correct Violation Were Ineffective in Correcting Condition ML14181A9961998-03-12012 March 1998 Notice of Violation from Insp on 980104-0214.Violation Noted:As of 970407,licensee Failed to Revise UFSAR to Include Following Effects of Changes Made in Facility or Procedures as Described in UFSAR ML14181A9911998-03-0404 March 1998 Notice of Violations from Insp on 980105-09.Violations Noted:Licensee Failed to Verify Adequacy of Design to Substantiate Final Design Documents Met Design Inputs & Adequate for Design Change Affecting Pumps B & C ML14181A9811998-02-0606 February 1998 Notice of Violation from Insp on 980105-09.Violation Noted: as of 970407,licensee Failed to Correct Conditions Adverse to Quality Associated W/Instrument Sensing Line Slope Deficiencies Documented in Ltrs & 960221 IR 07100012/20110221997-12-22022 December 1997 Notice of Violation from Insp on 971012-1122.Violation Noted:Licensee Failed to Accomplish Mod Related Activities as Evidenced.On 971007,licensee Did Not Evaluate Post Mod Test Acceptance Criteria for Measuring Total Air Flow ML20197E4841997-12-12012 December 1997 Notice of Violation from Insp on 970831-1011 & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:Licensee Failed to Establish Measures to Assure That Conditions Adverse to Quality Promptly Identified ML14181A9481997-09-26026 September 1997 Notice of Violation from Insp on 970720-0830.Violation Noted:Reactor Trip Channels Had Not Been Calibrated IAW Formula Specified in TS 2.3.1.2.e ML14181A9001997-04-18018 April 1997 Notice of Violation from Insp on 970209-0322.Violation Noted:On 970224,during Performance of Special Process Procedure SPP-002,freeze Plugging of Piping Not Requiring Brittle Fracture Steps 7.3.3,7.3.8 & 7.3.9 Not Followed ML14181A8541996-12-16016 December 1996 Notice of Violation from Insp on 960928-1116.Violation Noted:On 961016,operations Surveillance Test Procedure OST-160 Pressure Isolation Check Valve Back Leakage Test, Rev 23,inadequate,did Not Provide Adequate Instructions ML14181A8461996-10-25025 October 1996 Notice of Violation from Insp on 960818-0928.Violation Noted:Between 960917-19,shift Supervisors Assigned to Shifts Failed to Ensure That FMEA Controls Were Maintained in SFP Bldg While Fuel off-load Was Ongoing ML14181A8151996-04-25025 April 1996 Notice of Violation from Insp on 960311-0404.Violation Noted:From 951128 to 960309,licensee Allowed Access to Protected Area Using Hand Geometry Sys W/O Having Conducted Tests to Ensure Equipment Met 90% Detection Probability ML14182A2821996-03-12012 March 1996 Notice of Violation from Exam on 960209-15.Violation Noted: Licensee Failed to Take Adequate Corrective Action to Correct Deficiency Previously Identified ML14181A8041996-02-16016 February 1996 Notice of Violation from Insp on 960101-20.Violation Noted: Operating Procedure OP-402 Was Not Properly Implemented in That AFW-110 & AFW-111 Were Not Maintained Fully Open ML14181A7991996-01-26026 January 1996 Notice of Violation from Insp on 960126-31.Violation Noted: PIC-012 Did Not Provide Adequate Instructions for Ensuring That Accumulator Level Properly Calibr IR 05000917/20100211995-11-17017 November 1995 Notice of Violation from Insp on 950917-1021.Violation Noted:Lctr 95-01384 Did Not Provide Adequate Instructions for Ensuring That Air Start Sys Piping Associated W/B EDG Was Properly Isolated & Depressurized IR 05000618/20070151995-08-10010 August 1995 Notice of Violation from Insp on 950618-0715.Violation Noted:Fire Door to Pipe Alley Was Blocked Open for Approximately 30 Minutes W/O Notification of Operations Personnel IR 05000514/20060171995-07-17017 July 1995 Notice of Violation from Insp on 950514-0617.Violation noted:OMM-005 Was Not Followed in That Auxiliary Operator & Independent Verifier Initialed Local Clearance & Test Request Re Valve 20 IR 05000423/20050131995-06-12012 June 1995 Notice of Violation from Insp on 950423-0513.Violation Noted:Contracted Refueling Technician Failed to Follow Procedure FHP-001 IR 05000319/20040221995-05-19019 May 1995 Notice of Violation from Insp on 950319-0422.Violation Noted:Operators Failed to Follow Procedure OST-254 by Not Verifying RHR Sys to Be Aligned for Standby Low Pressure Injection ML14181A6661995-04-0707 April 1995 Notice of Violation from Insp on 950306-10.Violation Noted: Determined That Abnormal Operating Procedure AOP-014 Inadequately Maintained Re Insufficient Guidance for Connection of Cw to Two Pumps ML14181A6131994-10-0505 October 1994 Notice of Violation from Insp on 940821-0924.Violation Noted:On 940915,assigned Escort Left Two Visitors Unattended in Turbine Building While Escort Used Adjacent Restroom ML14181A6081994-10-0404 October 1994 Notice of Violation from Insp on 940912-16.Violation Noted: Licensee Test Activity on Plant Alternate AC Power Source & SBO Equipment Not Performed Adequately & According to Procedures ML14181A5811994-08-15015 August 1994 Notice of Violation from Insp on 940625-0723.Violation Noted:Resident Inspectors Identified That Train B Inlet & Outlet Filter Dampers for Tagged Shut W/No Limit on Time Equipment Could Remain Out of Svc ML14181A5621994-06-15015 June 1994 Notice of Violation from Insp on 940424-0521.Violation Noted:Wr/Jo 94-AEBT1 Inadequate & Did Not Provide Adequate Instructions for Ensuring That Control Room Differential Pressure Instrument DPI-6520 Properly Initialized ML14178A4961994-04-15015 April 1994 Notice of Violation from Insp on 940226-0326.Violation Noted:Three Radiation Monitor Setpoints Improperly Established Following Termination of Continuous Containment Vessel Purge on 940314 ML14178A4471994-02-18018 February 1994 Notice of Violation from Insp on 931226-940122.Violation Noted:Inadequate Debris Intrusion Control Measures Were Employed on 931115 ML14178A5271993-12-16016 December 1993 Notice of Violation from Insp on 931115-19.Violation Noted: Priority a Drawings Had Not Been Updated within 28 Working Days & Classified Overdue ML14178A4001993-11-0808 November 1993 Notice of Violation from Insp on 930912-1016.Violation Noted:Operator Deviated from OP-603 While Transferring Svc Water Pump D from Normal to Emergency Power ML14178A3921993-10-29029 October 1993 Notice of Violation from Insp on 930913-17 & 27-1001. Violations Noted:Onsite Equipment Certification/Calibration Documentation for Equipment on SG a & B Expired ML14178A3641993-07-0202 July 1993 Notice of Violation from Insp on 930515-0611.Violation Noted:Nrc Not Notified within 4 H of Notification of Sc Dept of Health & Environmental Control That Weir Discharge Temp Limits Had Been Exceeded ML14178A2701992-08-21021 August 1992 Notice of Violation from Insp on 920717-0807.Violation Noted:Written Procedures Were Not Implemented in That When CST High Level Alarm Was Received,Source of CST Makeup Water Was Throttled Instead of Being Stopped Per Procedures ML14178A2551992-07-22022 July 1992 Notice of Violation from Insp on 920615-19.Violation Noted: on 920615,feedwater Block Valve FW-2V-6A Failed to Close Fully Due to High Differential Pressure of 480 Psid ML14178A2451992-07-20020 July 1992 Notice of Violation from Insp on Stated Dates.Violation Noted:Licensee Failed to Follow Stated Procedures ML14178A1811991-12-16016 December 1991 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $37,000.Noncompliance Noted:Inadequate Control of Design Interfaces & Design Organizations Resulted in Failure to Adequately Check Design for SI Sys ML20138F7901991-04-12012 April 1991 Notice of Violation from Insp on 910216-0330.Violation Noted:Documented Instructions Were Not Provided for Method to Establish Temporary Heating Equipment to Maintain Reactor Vessel Head Flang Temp.Procedures & Drawings Not Provided ML14178A0871991-03-0505 March 1991 Notice of Violation from Insp on 910111-0215.Violations Noted:Procedure OST-351 Inadequately Established That Procedure Did Not Fully Test Steam Line Isolation Circuitry Associated W/Containment Pressure Channel ML20058H9781990-11-20020 November 1990 Notice of Violation from Insp on 901029-1102.Violation Noted:Inservice Insp Isometric Sketch Did Not Accurately Depict Actual Pipe Configuration ML14176A8841990-07-27027 July 1990 Notice of Violation from Insp on 900617-21.Violation Noted: Commitments for Activation of Operational Support Ctr & Technical Support Ctr Not Acceptably Demonstrated ML14191A9791988-08-12012 August 1988 Notice of Violation from Insp on 870309-0415.Violations Noted:Failure to Take Prompt Corrective Action to Determine Cause of Significant Conditions Adverse to Quality,Assure Correction & Preclude Repetition of Listed Events ML20196A9431988-06-15015 June 1988 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $50,000.Violation Noted:Combination of ECCS Subsystem Assumed to Be Operative in Evaluation Model in Updated SAR Did Not Reflect Failures of ECCS Equipment ML14191A9141988-04-14014 April 1988 Notice of Violation from Insp on 880111-15 & 0125-29. Violation Noted:On Four Occasions Licensee Reported Inoperability of All Diesel Generators While Operating at 100 Percent Power Under Incorrect Regulation ML14175B4421986-10-31031 October 1986 Notice of Violation from Insp on 860911-1010 ML14175B3931986-06-18018 June 1986 Notice of Violation from Insp on 860407-11 & 0516 ML14175B3211985-08-27027 August 1985 Notice of Violation from Insp on 850729-0802 ML20027E4651982-10-0101 October 1982 Notice of Violation from Insp on 820811-0910 ML20062J4381982-06-24024 June 1982 Notice of Violation from Investigation on 820111-0223 ML20054H0711982-04-22022 April 1982 Notice of Violation from Insp on 820311-0410 ML20052G2581982-03-30030 March 1982 Notice of Violation from Insp on 820222-26 ML20053B4911982-03-16016 March 1982 Notice of Violation from Insp on 820125-0204.Noncompliance Noted:Failure to Implement Plant Emergency Procedure 43 ML20052C1711982-03-16016 March 1982 Notice of Violation from Insp on 820111-0210 1998-06-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARPNO-II-99-039, on 990929,tornado Passed Through Protected Area.Tenting Matl from Turbine Deck Was Reported Blown on CR Roof.No Damage to Offsite Power Remained Available & No Fission Product Barriers Were Affected1999-09-30030 September 1999 PNO-II-99-039:on 990929,tornado Passed Through Protected Area.Tenting Matl from Turbine Deck Was Reported Blown on CR Roof.No Damage to Offsite Power Remained Available & No Fission Product Barriers Were Affected IR 05000261/19990041999-07-30030 July 1999 Insp Rept 50-261/99-04 on 990523-0703.One Violation of NRC Requirements Occured & Being Treated as Ncv.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000261/19990031999-06-16016 June 1999 Insp Rept 50-261/99-03 on 990411-0522.Non-cited Violation Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support IR 05000261/19990021999-05-11011 May 1999 Insp Rept 50-261/99-02 on 990228-0410.One NCV Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000261/19990101999-05-0606 May 1999 Insp Repts 50-261/99-10,50-324/99-10,50-325/99-10 & & 50-400/99-10 on 990310,18,19 & 25.Five Apparent Violations Identified:Failure to Review & Evaluate Background Info for Persons Granted Unescorted AA IAW 10CFR73.56(b)(3) IR 05000261/19990011999-03-29029 March 1999 Insp Rept 50-261/99-01 on 990117-0227.No Violations Noted. Major Areas Inspected:Licensee Operations,Maint,Engineering & Plant Support IR 05000261/19980121999-02-12012 February 1999 Insp Rept 50-261/98-12 on 981206-990116.No Violations Noted. Major Areas Inspected:Licensee Operations,Maint,Engineering & Plant Support IR 05000261/19980131999-01-0808 January 1999 Partially Withheld Insp Rept 50-261/98-13 on 981207-11 (Per 10CFR73.21).No Violations Identified.Major Areas Inspected: Physical Security Program for Power Reactors IR 05000261/19980111998-12-23023 December 1998 Insp Rept 50-261/98-11 on 981025-1205.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000261/19980091998-11-23023 November 1998 Insp Rept 50-261/98-09 on 980913-1024.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000261/19980081998-10-0909 October 1998 Insp Rept 50-261/98-08 on 980802-0912.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000261/19980061998-07-16016 July 1998 Insp Rept 50-261/98-06 on 980510-0620.No Violations Noted. Major Areas Inspected:Licensee Operations,Maint,Engineering & Plant Support IR 05000261/19980101998-06-29029 June 1998 Insp Repts 50-261/98-10,50-324/98-12,50-325/98-12 & 50-400/98-12 on 980601-04.No Violation Noted.Major Areas Inspected:Plant Support.Areas Specifically Evaluated,Access Authorization & Fitness for Duty Programs IR 05000261/19980031998-06-0909 June 1998 Errata to Notice of Violation of Insp Rept 50-261/98-03, Conducted on 980105-09.Correction Reflects More Accurately That Licensee Actions Taken to Correct Violation Were Ineffective in Correcting Condition ML14181B0101998-06-0808 June 1998 Insp Rept 50-261/98-05 on 980329-0509.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000261/19980021998-04-27027 April 1998 Insp Rept 50-261/98-02 on 980215-0328.No Violations Noted. Major Areas Inspected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000261/19980041998-03-24024 March 1998 Partially Withheld Insp Rept 50-261/98-04 on 980223-25 (Ref 10CFR73.21).No Violations Identified.Major Areas Inspected:Physical Security Program for Power Reactors ML14181A9961998-03-12012 March 1998 Notice of Violation from Insp on 980104-0214.Violation Noted:As of 970407,licensee Failed to Revise UFSAR to Include Following Effects of Changes Made in Facility or Procedures as Described in UFSAR ML14181A9911998-03-0404 March 1998 Notice of Violations from Insp on 980105-09.Violations Noted:Licensee Failed to Verify Adequacy of Design to Substantiate Final Design Documents Met Design Inputs & Adequate for Design Change Affecting Pumps B & C IR 05000261/19970141998-02-10010 February 1998 Errata to Insp Rept 50-261/97-14,transmitted on 980202.Typo Was Discovered on Pages 9 & 12 of Rept ML14181A9811998-02-0606 February 1998 Notice of Violation from Insp on 980105-09.Violation Noted: as of 970407,licensee Failed to Correct Conditions Adverse to Quality Associated W/Instrument Sensing Line Slope Deficiencies Documented in Ltrs & 960221 ML14181A9781998-02-0202 February 1998 Insp Rept 50-261/97-14 on 971123-980103.No Violations Noted. Major Areas Inspected:Licensee Operations,Maint,Engineering & Plant Support IR 07100012/20110221997-12-22022 December 1997 Notice of Violation from Insp on 971012-1122.Violation Noted:Licensee Failed to Accomplish Mod Related Activities as Evidenced.On 971007,licensee Did Not Evaluate Post Mod Test Acceptance Criteria for Measuring Total Air Flow ML20197E4841997-12-12012 December 1997 Notice of Violation from Insp on 970831-1011 & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:Licensee Failed to Establish Measures to Assure That Conditions Adverse to Quality Promptly Identified ML14181A3961997-12-0909 December 1997 EN-97-111:on 971212,notice of Proposed Imposition of Civil Penalty in Amount of $55,000 Issued to Licensee.Action Based on Severity Level III Problem Re Failure to Identify Promptly & Correct Mispositioned EDG Output Breaker Switch ML14181A9591997-11-0707 November 1997 Insp Rept 50-261/97-10 on 970831-1011.Violations Noted But Not Cited & Being Considered for Escalated Enforcement Action.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support ML14181A9481997-09-26026 September 1997 Notice of Violation from Insp on 970720-0830.Violation Noted:Reactor Trip Channels Had Not Been Calibrated IAW Formula Specified in TS 2.3.1.2.e IR 05000261/19970081997-08-18018 August 1997 Insp Rept 50-261/97-08 on 970608-0719.No Violations Noted. Major Areas Inspected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000261/19972011997-08-14014 August 1997 Insp Rept 50-261/97-201 on 970407-0523.No Violations Noted. Major Areas Inspected:Si & AFW Sys & Support Sys ML14181A9331997-07-0707 July 1997 Insp Rept 50-261/97-07 on 970427-0607.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000261/19970041997-04-18018 April 1997 Insp Rept 50-261/97-04 on 970209-0322.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML14181A9001997-04-18018 April 1997 Notice of Violation from Insp on 970209-0322.Violation Noted:On 970224,during Performance of Special Process Procedure SPP-002,freeze Plugging of Piping Not Requiring Brittle Fracture Steps 7.3.3,7.3.8 & 7.3.9 Not Followed IR 05000261/19970051997-04-18018 April 1997 Insp Rept 50-261/97-05 on 970317-21.No Violations Noted. Major Areas Inspected:Plant Support & Security Program Plans IR 05000261/19970011997-03-24024 March 1997 Pages 1 & 29 to Insp Rept 50-261/97-01 ML14181A8811997-02-28028 February 1997 Insp Repts 50-261/97-02,50-324/97-01 & 50-325/97-01 & 50-400-97-02 on 970113-0206.Violations Noted.Major Areas Inspected:Access Authorization & Fitness for Duty Programs ML14181A8541996-12-16016 December 1996 Notice of Violation from Insp on 960928-1116.Violation Noted:On 961016,operations Surveillance Test Procedure OST-160 Pressure Isolation Check Valve Back Leakage Test, Rev 23,inadequate,did Not Provide Adequate Instructions ML14181A8551996-12-16016 December 1996 Insp Rept 50-261/96-12 on 960928-1116.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML14181A8461996-10-25025 October 1996 Notice of Violation from Insp on 960818-0928.Violation Noted:Between 960917-19,shift Supervisors Assigned to Shifts Failed to Ensure That FMEA Controls Were Maintained in SFP Bldg While Fuel off-load Was Ongoing IR 05000261/19963011996-09-20020 September 1996 Exam Rept 50-261/96-301 on 960816-24.Exam results:14 SROs Passed & 1 Failed IR 05000261/19960081996-08-0101 August 1996 Insp Rept 50-261/96-08 on 960526-0706.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000261/19960071996-06-28028 June 1996 Insp Rept 50-261/96-07 on 960603-14.No Violations Noted. Major Areas Inspected:Integrated Performance Assessment to Development Perspective of Plant Strengths & Weaknesses; Operations,Maint,Engineering,Plant Support,Safety,Security IR 05000261/19960051996-06-24024 June 1996 Insp Rept 50-261/96-05 on 960414-0525.No Violations Noted. Major Areas Inspected:Plant Operations,Maint,Engineering & Plant Support IR 05000261/19960041996-05-10010 May 1996 Insp Rept 50-261/96-04 on 960303-0413.No Violations Noted. Major Areas Inspected:Plant Operations,Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems & Close Out of Items & Fire Protection Program ML14181A8151996-04-25025 April 1996 Notice of Violation from Insp on 960311-0404.Violation Noted:From 951128 to 960309,licensee Allowed Access to Protected Area Using Hand Geometry Sys W/O Having Conducted Tests to Ensure Equipment Met 90% Detection Probability ML14181A8161996-04-23023 April 1996 Insp Rept 50-261/96-03 on 960311-0404.Violations Noted. Major Areas Inspected:Security Program for Power Reactors, Mgt Support,Security Program Plans & Procedures;Safeguards Info,Audits & Security Lighting IR 05000261/19960021996-03-27027 March 1996 Insp Rept 50-261/96-02 on 960121-0302.No Violations Noted. Major Areas Inspected:Plant Operations,Close Out of Open Issues,Maint & Surveillance,Physical Security Program, Internal & External Exposure Controls & Training ML14182A2821996-03-12012 March 1996 Notice of Violation from Exam on 960209-15.Violation Noted: Licensee Failed to Take Adequate Corrective Action to Correct Deficiency Previously Identified ML14181A8041996-02-16016 February 1996 Notice of Violation from Insp on 960101-20.Violation Noted: Operating Procedure OP-402 Was Not Properly Implemented in That AFW-110 & AFW-111 Were Not Maintained Fully Open IR 05000261/19950301996-01-26026 January 1996 Insp Rept 50-261/95-30 on 951126-1231.Violations Noted. Major Areas Inspected:Plant Operations,Maintenance, Surveillance,Engineering & Plant Support ML14181A7991996-01-26026 January 1996 Notice of Violation from Insp on 960126-31.Violation Noted: PIC-012 Did Not Provide Adequate Instructions for Ensuring That Accumulator Level Properly Calibr 1999-09-30
[Table view] |
Text
ENCLOSURE 1 NOTICE OF VIOLATION Carolina Power and Light Company Docket No. 50-261 H. B. Robinson Unit 2 License No. DPR-23 During the NRC inspection conducted on May 15 - June 11, 1993, violations of NRC requirements were identified. In accordance with the "General Statement of Policy and Procedure For NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violations are listed below:
A.
10 CFR 50.72 (b)(2)(vi) requires that the NRC be notified within four hours of any event for which notification to other government agencies has been made.
Contrary to the above, on May 25, 1993, the NRC was not notified within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> of notification of South Carolina Department of Health and Environmental Control that weir discharge temperature limits had been exceeded.
This a Severity Level IV Violation (Supplement I).
B.
Technical Specification 6.5.1.1.1.a. requires that procedures be implemented for activities referenced in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978. Appendix A, Item 5 requires written procedures for alarm conditions of safety-related annunciators. Appendix A, Items 1.d, 3.d, and 3.n require written procedures pertaining to procedure adherence, temporary procedure changes, operation of the emergency core cooling system, and operation of the chemical and volume control system, respectively.
Technical specification 6.5.1.1.5 requires that temporary changes to procedures, tests or experiments be approved by two members of the plant staff, at least one of whom holds a Senior Reactor Operator License.
The temporary change must be documented and reviewed within 21 days to determine if the change constitutes an unreviewed safety question.
Annunciator panel procedure APP-036-H2 was established to provide operator actions for Boric Acid Heat Trace Trouble Alarms. The procedure requires in part, that responding personnel determine the cause of the alarm.
Operations Management Manual Procedure, OMM-001, Operations - Conduct of Operations, Section 5.9.2., Annunciator Panel Procedure Guidelines, provides guidance for implementing annunciator panel procedures and direction for unexpected alarm conditions for which annunciator procedures are not appropriate. The procedure requires in part, that responding personnel take corrective actions and document their conclusions regarding the alarm.
9306050093 930702 PDR ADOCK 05000261 G
PDR
Carolina Power and Light Company 2
Docket No. 50-261 H. B. Robinson Unit 2 License No. DPR-23 Administrative Procedure, AP-006, Procedure Adherence, states in section 5.1, that adherence to approved plant operating procedures is mandatory.
Section 5.2 delineates the only three mechanisms through which a deviation from an approved procedure can occur; those being either a permanent procedure change, a temporary procedure change, or a procedure deviation in the case of an emergency.
Contrary to the above;
- 1.
On May 20, 1993, procedures in response to a Boric Acid Heat Trace Trouble alarm on a Technical Specification required circuit were not implemented in that: Operations personnel failed to determine the cause of the alarm as required by APP-036-H2; failed to document their conclusions regarding the alarm as required by Section 5.9.2 of OMM-001; and failed to take corrective actions as required by Section 5.16 of OMM-001. As a result, a heat trace circuit was allowed to remain in alarm for approximately 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
- 2.
On May 27, 1993, during the performance of Operations Surveillance Test Procedure OST-254, Residual Heat Removal System and RHR Loop Sampling Leak Test, control room operators did not follow the procedure in that when they were unsuccessful in getting valve HCV-142 to open when performing step 16 of section 7.1, they altered the chemical and volume control system's operation and configuration outside the scope of the applicable procedure; however, they did not initiate a temporary procedure change, nor discuss their actions with the shift supervisor.
This a Severity Level IV Violation (Supplement I).
C.
Technical Specification 6.5.1.1.1.a. requires that procedures be maintained for activities referenced in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978. Appendix A, Item 9 requires written procedures for maintenance that can affect the performance of safety related equipment. Implicit in these requirements is the requisite that the procedures be technically and administratively adequate.
Corrective Maintenance Procedure CM-008 (Steam Driven Auxiliary Feedwater Pump, Turbine, and Auxiliaries Maintenance) was established to provide maintenance instructions for the steam driven auxiliary feedwater pump.
Contrary to the above, corrective maintenance procedure CM-008 was inadequate in that on November 25, 1992, a precaution to test the overspeed trip setpoint following renewal of the trip striker pin or striker spring was erroneously deleted from the procedure.
This a Severity Level IV Violation (Supplement I).
Carolina Power and Light Company 3
Docket No. 50-261 H. B. Robinson Unit 2 License No. DPR-23 Pursuant to the provisions of 10 CFR 2.201, Carolina Power and Light Company is hereby required to submit a written statement or explanation to the U. S.
Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555, with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector, within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This reply should be clearly marked as a "Reply to a Notice of Violation" and should include for each violation:
(1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved. If an adequate reply is not received within the time specified in this Notice, an order may be issued to show cause why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. Where good cause is shown, consideration will be given to extending the response time.
Dated at Atlanta, Georgia this 2nd day of July 1993