Summary of the August 8, 2024, Public Outreach to Discuss the NRC 2023 End-of-Cycle Plant Performance Assessment of Dresden Nuclear Power Plant, Units 2 and 3
ML24232A153
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/21/2024
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To:
Shared Package
ML24057A270 List:
References
Download: ML24232A153 (1)


Text

LICENSEE:

Constellation Energy Generation, LLC FACILITY:

Dresden Nuclear Power Station, Units 2 and 3

SUBJECT:

SUMMARY

OF THE AUGUST 8, 2024, PUBLIC OUTREACH TO DISCUSS THE NRC 2023 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 On August 8, 2024, from 5:00 p.m. to 5:30 p.m. (CDT), an information meeting was held by representatives of the U.S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2023 End-of-Cycle plant performance assessment of the Dresden Nuclear Power Station, Units 2 and 3, and with general information on the NRC. The meeting was held via webinar. The NRC representatives were available to discuss plant performance with members of the public. Representatives from Constellation Energy were also present at the event.

The NRC discussed their assessment of Dresden Nuclear Power Station, Units 2 and 3 performances during the public outreach. The assessment information was documented in the February 28, 2024, End-of-Cycle Assessment Letter (ADAMS Accession Number ML24058A490). Members of the public were given the opportunity to ask questions of NRC staff.

Robert Ruiz, Branch Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 50-237 and 50-249 License Nos. DPR-19 and DPR-25 cc: Distribution via LISTSERV August 21, 2024 Signed by Ruiz, Robert on 08/21/24

SUBJECT:

SUMMARY

OF THE AUGUST 8, 2024, PUBLIC OUTREACH TO DISCUSS THE NRC 2023 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 DISTRIBUTION:

Michelle Simmons RidsNrrDorlLpl3 RidsNrrPMDresden Resource RidsNrrDroIrib Resource Jack Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker David Curtis Jonathan Feibus R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML24232A153 OFFICE RIII RIII NAME NShah:anm RRuiz DATE 08/21/2024 08/21/2024 OFFICIAL RECORD COPY

Enclosure PUBLIC MEETING ATTENDEES August 8, 2024 U.S. Nuclear Regulatory Commission R. Ruiz, Chief, Reactor Projects Branch 1 J. Steffes, Senior Resident Inspector Z. Helgert, Acting Resident Inspector N. Shah, Senior Project Engineer, Branch 1 V. Mitlyng, Senior Public Affairs Officer D. Bogedain, Resident Inspector Office Assistant T. Crabtree, Student Co-Op, Branch 1 Constellation Energy P. Dempsey Members of the Public H. Latimer S. Jenkins A. Sabet G. Buck D. Nally T. Barvitskie