Forwards Revised Pages for TS Change 93-02,submitted Via Util for Removal of 10CFR50,App J Containment Test Requirements from Ts,Based on Conversations W/Nrc
ML20063D763
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 01/31/1994
From: Fenech R
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20063D767 List:
References
NUDOCS 9402080293
Download: ML20063D763 (2)


Text

, _ _ .

7*, ,

T.' '

' V. ,

t k

i Tennessee VaHey Authority. Post Off+ce Box 2000. Soddy-Daisy, Tennessee 37379-2000 1

-[

Robert A. Fenech '

Vice President. Sequoyah Nuclear Plant January 31, 1994 TVA-SQN-TS-93-02 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:

r In the Matter of ) Docket Nos. 50-327 Tennessee Valley Authority ) 50-328 .

SEQUOYAll NUCLEAR PLANT (SQN) - REVISED PAGES FOR TECIINICAL SPECIFICATION (TS) CilANGE 93-02

Reference:

TVA letter to NRC dated March 10, 1993, "Sequoyah Nuclear j Plant (SQN) - Technical Specification (TS) Change 93-02, '!

' Removal of 10 CFR 50, Appendix J Containment Test Requirements from TS'" q In the referenced letter, TVA submitted a proposed TS change (TS Change 93-02) for SQN. The proposed TS change models SQN's TSs after the i standard TSs for Westinghouse Electric Corporation plants (NUREG-1431) and eliminates duplication of 10 CFR 50, Appendix J requirements within '

TSs.

t Based on conversations with NRC, editorial changes were-identified by_ the  ;

staff that would clarify TVA's proposed TS change. Accordingly, TVA is submitting revised TS pages that supersede the TS pages from TVA's referenced letter. For administrative ease, all pages of TS Change 93-02 have been resubmitted for-Units 1 and 2.

?

The changes to the TS pages are considered to be editorial in nature, and do not impact the overall intent of the affected specifications.

Consequently,.the no significant hazards consideration provided in the referenced letter remains unchanged. l

() A n n " C /

9402080293 940131 'l g PDR ADOCK 05000327

  • k P. PDR gj q g

.--_____i

'i a

~ '

't

s. ,

U.S. Nuclear Regulatory Commission Page 2.

January 31, 1994  ;

4 t

Please direct questions concerning this issue to D. V. Goodin at  ;

(615) 843-7734.

I Sincerely, I

(4 - ~%A Robert A. Fenech -

i Sworn to and subsexibed before me this 3 / 2 day of }) _ 1994 {

t .I q Notary Public 1 /

My Commission Expires _77 /g/

Enclosure r cc (Enclosure)*

Mr. D. E. LaBarge, Project Manager "

U.S. Nuclear Regulatory Commission One White Flint, North ,

11555 Rockville Pike Rockville, Maryland 20852-2739 Mr. Michael H. Mobley, Director (w/o Enclosure) t Division of Radiological Hea,1th  ;

3rd Floor -;

L & C Annex Lt 401 Chu ch Street -J Nashville, Tennessee 37243-1532 '

NRC Resident inspector [

Sequoyah Nuclear Plant [

2600 Igou Ferry Road I Soddy-Daisy, Tennessee 37379-3624 .I Regional Administrator 3 U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900  ;

Atlanta, Georgia 30323-2711 t 9

.. - ..