Letter Sequence RAI |
---|
|
|
MONTHYEARM170193, GE-Hitachi Nuclear Energy Americas, LLC - Submittal of Response to NRC Request for Additional Information2017-07-31031 July 2017 GE-Hitachi Nuclear Energy Americas, LLC - Submittal of Response to NRC Request for Additional Information Project stage: Response to RAI ML17312B3592018-01-18018 January 2018 Information Needed for the GE Hitachi Exemption Request for Alternate Decommissioning Schedules for Licenses DPR-1, DR-10 and TR-1 at the Vallecitos Nuclear Center (EPID No. L-2017-LLA-0052) (Docket Numbers: 50-18, 50-183, 50-70; License Nu Project stage: Other M180064, GEH Response Plan for NRC Request for Additional Information2018-03-28028 March 2018 GEH Response Plan for NRC Request for Additional Information Project stage: Request ML18123A3042018-05-21021 May 2018 GE Hitachi Response Plan for NRC Request for Additional Information Project stage: RAI M190202, GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules2019-11-15015 November 2019 GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules Project stage: Request ML20071G4112020-03-16016 March 2020 Request for Additional Information, GE Hitachi Request for Alternate Decommissioning Schedules for the Shutdown Reactors at the Vallecitos Nuclear Center Project stage: RAI M200102, GEH - Response to NRC Request for Additional Information (Rai), March 16, 20202020-07-15015 July 2020 GEH - Response to NRC Request for Additional Information (Rai), March 16, 2020 Project stage: Response to RAI ML20197A0122020-07-15015 July 2020 GEH - Response to NRC Request for Additional Information (Rai), March 16, 2020 Project stage: Response to RAI ML20174A1162020-07-15015 July 2020 Vbwr Request for Additional Information Enclosure Project stage: RAI ML20174A1152020-07-15015 July 2020 GE Hitachi Nuclear Energy - Vallecitos Nuclear Center, Vbwr Alternate Decommissioning Schedule - Request for Additional Information - License Numbers: DPR-1 (Docket Number 50-18); DR-10 (Docket Number 50-183); and TR-1 (Docket Number 50-70) Project stage: RAI 2018-05-21
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000018/20240022024-10-29029 October 2024 GE Hitachi Nuclear Energy - NRC Inspection Report 05000018/2024-002, 05000070/2024002, 05000183/2024002, and 050-00073/2024002 ML24299A0682024-10-25025 October 2024 GEH Notification of GE Company Stock Beneficial Ownership Filing ML24284A1182024-10-10010 October 2024 GEH - Notification of GE Company Stock Beneficial Ownership Filing ML24271A1572024-09-27027 September 2024 Notification of Planned Closing, Trust Fund Balance at Transfer and Proof of Insurance ML24270A2242024-09-26026 September 2024 License Amendment Request - Historic and Cultural Resources Review Vallecitos Boiling Water Reactor and General Electric Test Reactor ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24165A2812024-06-13013 June 2024 Northstar Vallecitos, LLC, Documentary Evidence of Insurance Vallecitos Nuclear Center ML24157A0882024-06-0505 June 2024 GE-Hitachi Nuclear Energy Americas, LLC, Vallecitos Nuclear Center (Vnc) Organization Change ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000018/20240012024-05-29029 May 2024 GE Hitachi Nuclear Energy - NRC Inspection Report 05000018/2024-001, 050 00070/2024-001, 050-00183/2024-001, and 050-00073/2024-001 ML24039A0192024-04-25025 April 2024 Order Approving Transfer of the Vallecitos Nuclear Center Licenses and Conforming License Amendments ML24088A2392024-03-28028 March 2024 GE-Hitachi Nuclear Energy Americas, LLC, NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed - Step Two ML24051A1802024-02-22022 February 2024 Boiling Water Reactor License Termination Plan Request for Additional Information - Letter ML24032A1082024-02-0101 February 2024 GEH Notification of GE Company Stock Beneficial Ownership Filing ML24022A3232024-01-22022 January 2024 Geha/Northstar Response to NRC Request for Additional Information Regarding Direct Transfer of Vnc Licenses IR 05000018/20230022024-01-0909 January 2024 GE Hitachi Nuclear Energy - NRC Inspection Report 05000018/2023002, 05000070/2023002, and 05000183/2023002 ML23345A1222023-12-21021 December 2023 Request for Additional Information Regarding the Direct Transfer of Control of Vallecitos Nuclear Center Licenses and Conforming License Amendments ML23345A0812023-12-11011 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A1312023-12-0404 December 2023 GE-Hitachi Nuclear Energy Americas, LLC, Additional Information to Geha and GNF-A Application for Order Consenting to Indirect Transfer of Control (Reference 1) ML23334A2222023-11-30030 November 2023 GE Hitachi Nuclear Energy - NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed ML23283A3292023-11-30030 November 2023 NRC Issuance of Order Consenting to Indirect Transfer of Control of Ge/Geha/Gnfa Licenses ML23279A1322023-11-13013 November 2023 GE Hitachi Nuclear Energy - Vallecitos Nuclear Center, Getr Decommissioning Plan – (License Number TR-1, Docket Number 50-70) ML23310A1132023-11-0909 November 2023 FRN-Notice of Consideration of Approval of Direct Transfer of Control of Vallecitos Nuclear Center Licenses Conforming License Amendments Opportunity for a Hearing Transmittal Letter ML23305A0522023-11-0101 November 2023 GE Hitachi Nuclear Energy Additional Supplemental Information - Revised Exhibit H ML23275A1742023-10-26026 October 2023 Acceptance Review of Application for Consent to Direct Transfer of Control of Vallecitos Nuclear Center Licenses and Conforming License Amendments ML23292A3362023-10-19019 October 2023 Northstar Vallecitos, LLC, Supplemental Information - Financial Qualifications ML23276B3952023-10-13013 October 2023 The U.S. Nuclear Regulatory Commission Staff Assessment of Ge/Geha/Gnfa Reponses to Acceptance Observations Application for the U.S. Nuclear Regulatory Commission Consent to Indirect Transfer of Licenses ML23269A1062023-09-26026 September 2023 GEH Description of Process for Decommissioning the Vallecitos Nuclear Center (Vnc) Shutdown Reactors - Getr Decommissioning Plan ML23261A5922023-09-15015 September 2023 GE-Hitachi Nuclear Energy Americas, LLC, License Termination Plan for the Vallecitos Boiling Water Reactor License DPR-1 ML23257A2492023-09-14014 September 2023 Cultural Resources Report ML23248A2322023-09-0505 September 2023 GE Hitachi Nuclear Energy - Supplemental Information - Proposed Conforming Amendments & License Conditions ML23244A2472023-09-0101 September 2023 GE-Hitachi Nuclear Energy Americas, LLC and Northstar Vallecitos, LLC, Application for Consent to Direct Transfers of Control of Licenses and Related Conforming License Amendments ML23229A5122023-08-17017 August 2023 GE-Hitachi Nuclear Energy Americas, LLC, Response to NRC Staff Observations Enclosed with NRC Acceptance Letter (Reference 2) Related to GE, Geha and GNF-A Application (Reference 1) ML23191A8592023-07-27027 July 2023 Acceptance Letter GE GNFA and Geha Application for NRC Consent to Indirect Transfer of Licenses ML23150A0962023-05-30030 May 2023 GE Hitachi Nuclear Energy, Nuclear Center (Vnc) Organization Change ML23152A1162023-05-30030 May 2023 Application for Order Consenting to Indirect Transfer of Control with Respect to Reactor Licenses, Materials Licenses, and Export Licenses, and Notification Regarding Other Approvals IR 05000018/20230012023-05-0505 May 2023 GE Hitachi Nuclear Energy - NRC Inspection Report 05000018/2023001, 05000070/2023001, and 05000183/2023001 ML23123A0752023-04-12012 April 2023 Response to NRC Request for Inspection Documents ML23104A4172023-03-31031 March 2023 GNF-AGEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML23090A1802023-03-31031 March 2023 GEH - Financial Assurance Status Reports ML23083B3402023-03-24024 March 2023 GEH Annual Shutdown Reactor Reports for the Year 2022 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23054A3332023-02-23023 February 2023 GEH Notification of GE Company Stock Beneficial Ownership Filing ML23018A2832023-01-19019 January 2023 GE-Hitachi Nuclear Energy Americas, LLC Response to NRC Inspection Report 050-00018/2022-002; 050-00070/2022-002; 050-00183/2022-002 and Notice of Violation ML22339A1742022-12-13013 December 2022 GE Hitachi Nuclear Energy NRC Inspection Report 05000018/2022002 05000070/2022002 and 05000183/2022002 IR 05000018/20220022022-12-13013 December 2022 GE Hitachi Nuclear Energy NRC Inspection Report 05000018/2022002 05000070/2022002 and 05000183/2022002 ML22335A5262022-12-0101 December 2022 (Vnc) Organization Change ML22326A3522022-11-22022 November 2022 Limited Post Shutdown Decommissioning Activities Report Update ML22300A2102022-10-27027 October 2022 GE-Hitachi Nuclear Energy Americas, LLC, Nuclear Center (Vnc) Submittal of Radiological Emergency Plan (REP) Revision 2 ML22265A0442022-09-26026 September 2022 GE Hitachi Vallecitos Nuclear Center, U.S. Nuclear Regulatory Commissions Analysis of GE Hitachis Decommissioning Funding Status Reports for the Shutdown Power Reactors Vallecitos Boiling Water Reactor (License No. DPR-1, Docket No. 50-18) 2024-09-27
[Table view] |
Text
March 16, 2020 Matt J. Feyrer, Site Manager GE Hitachi Nuclear Energy Vallecitos Nuclear Center 6705 Vallecitos Rd.
Sunol, CA 94586
SUBJECT:
GE HITACHI REQUEST FOR ALTERNATE DECOMMISSIONING SCHEDULES FOR THE SHUTDOWN REACTORS AT THE VALLECITOS NUCLEAR CENTER - REQUEST FOR ADDITIONAL INFORMATION (EPID L-2017-LLA-0052)
Dear Mr. Feyrer:
By letter dated July 10, 2015, and as supplemented by letter dated October 15, 2015, GE Hitachi Nuclear Energy (GEH) submitted a request for alternate decommissioning schedules for licenses DPR-1 (VBWR), DR-10 (EVESR), and TR-1 (GETR) at the GEH Vallecitos Nuclear Center (VNC).
On July 15, 2016, GEH revised its request to the form of an exemption from the decommissioning schedule requirements of § 50.82(a)(3) (for VBWR and EVESR) and § 50.82(b)(4)(i) (for GETR), i.e., the schedule requirements for the termination of reactor licenses.
The exemption request was made in accordance with 10 CFR 50.12, Specific Exemptions.
NRC staff review of the request resulted in a request for additional information to GEH by letter dated May 16, 2017.
GEH responded on July 31, 2017 by, in part, further addressing the exemption criteria of § 50.12(a)(1) regarding ensuring that the requested exemption will not present an undue risk to the public health and safety. Also, in September 2017 NMSS staff conducted a follow up onsite audit of GEHs responses to the 2017 RAIs. As a result of NRC staffs review this response, and the onsite audit, staff found that further information was needed to determine if the § 50.12(a)(1) exemption criteria could be satisfied. Therefore, by letter dated January 18, 2018 NRC staff requested additional information. Through several partial responses and adjustments to the response schedule, GEH provided its final response to this RAI on November 15, 2019 (ADAMS Accession No. ML19319B843).
The NRC staff has reviewed your request and concluded that there is enough information for the staff to make an independent assessment regarding the acceptability of the proposed exemption to § 50.82(a)(3) for VBWR. However, the NRC staff has concluded that the information described in the enclosure to this letter is necessary to enable the staff to make an independent assessment regarding the acceptability of the proposed exemption to § 50.82(a)(3) for EVESR and § 50.82(b)(4)(i) for GETR in terms of regulatory requirements and undue risks to public health and safety.
M. Feyrer The NRC staff requests that GEH supplement the request to address the information described in the enclosure within 30 days of the date of this letter. This will enable the NRC staff to resume its detailed technical review.
The information requested and associated time frame in this letter were discussed with Scott Murray of your staff on March 12, 2020.
If you have any questions, please call me at (301) 415-6634 or e-mail at Jack.Parrott@nrc.gov.
Sincerely, Jack D. Parrott, Senior Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs, Office of Nuclear Material Safety and Safeguards Docket Nos. 50-18, 50-183, and 50-70
Enclosure:
Additional Information Needed cc: GE Hitachi shutdown reactor service list
ML20071G411 Package No. ML20071G413 *by e-mail OFFICE NMSS/DUWP/RDB/PM NMSS/DUWP/RDB/BC NRR//DEX/ESEB/BC NAME J.Parrott B.Watson J.Colaccino*
DATE 03/11/2020 03/12/2020 03/12/2020 OFFICE NMSS/DUWP/DD NMSS/DUWP/RDB/PM NAME P.Holahan* J.Parrott DATE 03/16/2020 03/16/2020