Acceptance for Detailed Review of American Centrifuge Operating Approval of Changes to Licensing Documents Resulting from Compliance with 32 CFR 117
ML22159A214
Person / Time
Site: 07007004
Issue date: 06/09/2022
From: Yawar Faraz
NRC/NMSS/DFM/FFLB
To: Karen Fitch
American Centrifuge Operating
Y FARAZ NMSS/DFM/FFLB 3014157220
References
EPID L-2022-SPR-0005
Download: ML22159A214 (3)


Text

June 9, 2022 Kelly L. Fitch, Regulatory Manager American Centrifuge Operating, LLC P.O. Box 628 Mail Stop 7560 3930 U.S. 23 South Piketon, Ohio 45661

SUBJECT:

ACCEPTANCE FOR DETAILED REVIEW OF AMERICAN CENTRIFUGE OPERATINGS REQUEST FOR APPROVAL OF CHANGES TO LICENSING DOCUMENTS RESULTING FROM COMPLIANCE WITH 32 CFR 117 (ENTERPRISE PROJECT IDENTIFICATION NUMBER: L-2022-SPR-0005)

Dear Kelly Fitch:

By letter dated April 7, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22102A092), American Centrifuge Operating, LLC (ACO), a wholly owned subsidiary of Centrus Energy Corp. (Centrus), provided the U.S. Nuclear Regulatory Commission (NRC) a license amendment request involving proposed changes to the following security plans:

SP-3605-0041, Security Plan for the Protection of Classified Matter at the American Centrifuge Plant; SP-3605-0042, Security Plan for the Physical Protection of Special Nuclear Material at the American Centrifuge Plant; SP-3605-0045, Security Plan for the Protection of Classified Matter at Centrus Energy Corp. Headquarters; and NR-SP-ACO-OR-0001, Security Program for American Centrifuge Operating, LLC at Oak Ridge, Tennessee.

The changes to the security plans resulted from ACOs proposed implementation of Title 32 of the Code of Federal Regulations (32 CFR) Part 117, National Industrial Security Program Operating Manual (NISPOM), and the Security Executive Agent Directive 3, Reporting Requirements for Personnel with Access to Classified Information or Who Hold a Sensitive Position (SEAD 3), requirements.

K. Fitch 2 We have completed our acceptance review of your submittal and have identified no administrative omissions or deficiencies. Your submittal has been assigned Enterprise Project Identification Number (EPID) L-2022-SPR-0005. Please reference this EPID number and Docket Number 07007004 in any future correspondence associated with this request. Please note that the NRC staffs detailed technical review of your submittal may identify omissions in the submittal information or technical issues which require additional information.

Based on our acceptance review and projection of current review schedules, we anticipate that we will complete the technical review of your submittal by October 14, 2022. In addition, the NRC staff estimates that completing the review of the submittal will require approximately 160 staff hours. The total cost of the review corresponds to $46,080 ($288.00/hour).

In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR), or from the Publicly Available Records component of the NRCs ADAMS. The PDR is open by appointment only. You may submit your request to the PDR via email at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST), Monday through Friday, except Federal holidays.

ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If you have any questions regarding this communication, please contact me by telephone at 301-415-7220, or via email at Yawar.Faraz@nrc.gov.

Sincerely, Yawar H. Faraz, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-7004 License No. SNM-2011 cc: centrus_acp@listmgr.nrc.gov M. Snider, General Manager, ACO S. Harlow, DOE NE-HQ R. Fischels, ACO J. Hutson, NRC Contractor

K. Fitch 3

SUBJECT:

ACCEPTANCE FOR DETAILED REVIEW OF AMERICAN CENTRIFUGE OPERATINGS REQUEST FOR APPROVAL OF CHANGES TO LICENSING DOCUMENTS RESULTING FROM COMPLIANCE WITH 32 CFR 117 (ENTERPRISE PROJECT IDENTIFICATION NUMBER: L-2022-SPR-0005)

DATED June 9, 2022 DISTRIBUTION:

LPitts, RII JTobin, NMSS KEverly, NSIR NStAmour, OGC TVukowinski, RII RWomack, RII SBazian, NSIR LHowell, NMSS SHelton, NMSS CSafford, NMSS RWilliams, RII DDecker, OCA JWeil, OCA DMcIntyre, OPA PJehle, OGC NPitoniak, RII CWolf, OCA TSteinfeldt, OGC MMangefrida, NSIR SLee, NSIR THarris, NSIR CTeal, NSIR ADAMS Accession Number: ML22159A214 OFFICE NMSS/DFM/ NMSS/DFM/ NSIR/DSO/ NSIR/DPCP/ NMSS/DFM/

FFLB/PM FFLB/LA ISB/BC MSB/BC FFLB/BC (A)

NAME YFaraz ELee DParsons ARivera TBoyce DATE 06/08/2022 06/08/2022 06/09/2022 06/08/2022 06/09/2022 OFFICIAL RECORD COPY