Kelly L. Fitch, Regulatory Manager American Centrifuge Operating, LLC P.O. Box 628 Mail Stop 7560 3930 U.S. 23 South Piketon, OH 45661
SUBJECT:
ACCEPTANCE OF THE AMERICAN CENTRIFUGE OPERATING, LLCS LICENSE APPLICATION FOR PHASE II OPERATIONS (ENTERPRISE PROJECT IDENTIFICATION NUMBER L-2023-LLA-0024)
Dear Kelly Fitch:
The U.S. Nuclear Regulatory Commission (NRC) staff have received your request to amend your license dated February 13, 2023 (Agencywide Documents Access and Management System {ADAMS} Accession No. ML23047A089). This submittal provided your application for increasing the production of High Assay Low Enriched Uranium at the American Centrifuge Plant in Piketon, Ohio to 1,400 kilograms UF6 by December 31, 2024.
We have completed our acceptance review of your submittal and determined that the application provides sufficient information to proceed with a detailed technical review. We have established a review schedule to be completed by December 2023. The schedule includes time for the NRC staff to issue any requests for additional information (RAI) in May 2023. The schedule also presumes that American Centrifuge Operating, LLC (ACO) will provide sufficient responses to resolve the RAIs within 30 days from issuance and that a second round of RAIs will not be needed.
Please note that the projected review dates could change depending on the need for a second round of RAIs, the findings of our technical review, or other pressing safety or security work.
The NRC staff estimates that completing the review of your submittal will require approximately 300 staff hours for the license application review which corresponds to about $87,000.00
($290.00/hr). We will promptly communicate any significant schedule or cost changes.
April 13, 2023
K. Fitch 2
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs ADAMS.
ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
If you have any questions regarding this communication, please contact me at 301-415-2328 or via e-mail at Yawar.faraz@nrc.gov.
Sincerely, Yawar Faraz, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 07007004 License No. SNM-2011 cc:
M. Snider, Enrichment Operations Plant Manager, ACO S. Harlow, DOE-NE centrus_acp@listmgr.nrc.gov Signed by Faraz, Yawar on 04/13/23
Ltr ML23086A088 OFFICE NMSS/DFM/FFLB NSIR/DSO/SOSB NMSS/REFS NMSS/DFM/FFLB NAME JTobin JCurry SSoto YFaraz DATE Mar 27, 2023 Mar 27, 2023 Apr 6, 2023 Apr 13, 2023