Insp Repts 50-324/97-14 & 50-325/97-14 on 971209-12. Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Controls,Miscellaneous Radiation Protection & Chemistry Issues & Mgt MeetingsML20198N656 |
Person / Time |
---|
Site: |
Brunswick |
---|
Issue date: |
12/30/1997 |
---|
From: |
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
---|
To: |
|
---|
Shared Package |
---|
ML20198N643 |
List: |
---|
References |
---|
50-324-97-14, 50-325-97-14, NUDOCS 9801210160 |
Download: ML20198N656 (7) |
|
|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000324/19990061999-10-0606 October 1999 Insp Repts 50-324/99-06 & 50-325/99-06 on 990801-0911.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000324/19990051999-08-27027 August 1999 Insp Repts 50-324/99-05 & 50-325/99-05 on 990620-0731.Two Violations Noted Being Treated as Ncv.Major Areas Inspected: Operations,Maint & Plant Support IR 05000324/19990041999-07-19019 July 1999 Insp Repts 50-324/99-04 & 50-325/99-04 on 990509-0619. Non-cited Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support.Includes Results of Y2K Readiness Program Review IR 05000324/19990031999-06-0707 June 1999 Insp Repts 50-324/99-03 & 50-325/99-03 on 990328-0508.Two Violations Noted & Being Treated as non-cited Violations. Major Areas Inspected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000324/19990021999-04-26026 April 1999 Forwards Insp Repts 50-324/99-02 & 50-325/99-02 on 990214-0327.No Violations Noted.Major Areas Inspected: Licensee Operation,Engineering,Maint & Plant Support IR 05000324/19980141999-03-18018 March 1999 Insp Repts 50-324/98-14 & 50-325/98-14 on 990111-15,25 & 29. No Violations Noted.Major Areas Inspected:Licensee Calculations,Analysis,Performance Test Procedures & Other Engineering Activities IR 05000324/19990011999-03-15015 March 1999 Insp Repts 50-324/99-01 & 50-325/99-01 on 990103-0213.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000324/19980111999-01-28028 January 1999 Insp Repts 50-324/98-11 & 50-325/98-11 on 981122-990102.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint & Plant Support IR 05000324/19980101998-12-21021 December 1998 Insp Repts 50-324/98-10 & 50-325/98-10 on 981011-1121. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support.Also Includes Results of Engineering & Health Physics Insp IR 05000324/19980131998-11-24024 November 1998 Partially Withheld Insp Repts 50-324/98-13 & 50-325/98-13 on 981026-30 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Aspects of Licensee Plant Support IR 05000324/19980091998-11-0909 November 1998 Insp Repts 50-324/98-09 & 50-325/98-09 on 980830-1010. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000324/19980081998-09-28028 September 1998 Insp Repts 50-324/98-08 & 50-325/98-08 on 980719-0829.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19980071998-08-11011 August 1998 Insp Repts 50-324/98-07 & 50-325/98-07 on 980607-0718. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19980061998-07-0606 July 1998 Insp Repts 50-324/98-06 & 50-325/98-06 on 980426-0606. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19980051998-06-0101 June 1998 Insp Repts 50-324/98-05 & 50-325/98-05 on 980315-0425. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20216H4431998-04-16016 April 1998 Insp Repts 50-324/98-04 & 50-325/98-04 on 980209-13,0309-12 & 16-20.Violations Noted.Major Areas inspected:follow-up on Licensee Corrective Actions for Electrical Equipment Environ Qualification & Review of Instrument Response Time Testing IR 05000324/19980031998-04-13013 April 1998 Insp Repts 50-324/98-03 & 50-325/98-03 on 980201-0314.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support.Also Includes Results of Health Physics Insp by Regional Inspectors ML20217C8061998-03-16016 March 1998 Insp Repts 50-324/98-01 & 50-325/98-01 on 980126-30. Violations Noted.Major Areas Inspected:Emergency Preparedness Exercise ML20216B1741998-03-0202 March 1998 Insp Repts 50-324/97-15 & 50-325/97-15 on 971228-980131. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support ML20202D3161998-02-0505 February 1998 Omitted Page 42 to Insp Repts 50-324/97-13 & 50-325/97-13 Transmitted on 980123 ML20199G7501998-01-23023 January 1998 Insp Repts 50-324/97-13 & 50-325/97-13 on 971109-1227. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support.Includes Results of Maint, Engineering & FP Insps ML20198N6561997-12-30030 December 1997 Insp Repts 50-324/97-14 & 50-325/97-14 on 971209-12. Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Controls,Miscellaneous Radiation Protection & Chemistry Issues & Mgt Meetings IR 05000324/19970141997-12-30030 December 1997 Insp Repts 50-324/97-14 & 50-325/97-14 on 971209-12. Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Controls,Miscellaneous Radiation Protection & Chemistry Issues & Mgt Meetings ML20197H1881997-12-0808 December 1997 Insp Repts 50-324/97-12 & 50-325/97-12 on 970928-1108. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19970111997-10-27027 October 1997 Insp Repts 50-324/97-11 & 50-325/97-11 on 970819-0927. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000324/19970091997-09-15015 September 1997 Insp Repts 50-324/97-09 & 50-325/97-09 on 970706-0816. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support Re Improper Processing of Changes to Fire Protection Instrumentation Surveillance IR 05000324/19970101997-08-0808 August 1997 Insp Repts 50-324/97-10 & 50-325/97-10 on 970728-30.No Violations Noted.Major Areas Inspected:Plant Support ML20198F4101997-08-0101 August 1997 Insp Repts 50-324/97-08 & 50-325/97-08 on 970525-0705. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19970071997-06-20020 June 1997 Integrated Insp Repts 50-324/97-07 & 50-325/97-07 on 970413-0524.No Violations Noted.Major Areas Inspected: Licensee Operations,Engineering,Maint & Plant Support ML20140D1781997-05-12012 May 1997 Insp Repts 50-324/97-05 & 50-325/97-05 on 970302-0412. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000324/19970061997-05-0909 May 1997 Safeguards Insp Repts 50-324/97-06 & 50-325/97-06 on 970409-11.No Violations Noted.Major Areas Inspected:Aspects of Licensee Plant Support,Status of Security Facilities & Equipment ML20138J5981997-05-0202 May 1997 Insp Repts 50-324/97-03 & 50-325/97-03 on 970303-0404. Violations Noted.Major Areas Inspected:Review of Licensee Engineering Activities to Support Operation of Plant EQ Program & Followup on Previous Insp Findings IR 05000324/19970041997-04-0404 April 1997 Safeguard Insp Repts 50-324/97-04 & 50-325/97-04 on 970303-07.No Violations Noted.Major Areas Inspected:Plant Support & Security & Safeguards Procedures & Documentation ML20137T5711997-03-31031 March 1997 Insp Repts 50-324/97-02 & 50-325/97-02 on 970119-0301. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering,Plant Support & Emergency Preparedness ML20134P1551997-02-14014 February 1997 Insp Repts 50-324/96-18 & 50-325/96-18 on 961208-970118. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20133L5931997-01-0909 January 1997 Errata to Insp Repts 50-324/96-15 & 50-325/96-15 on 960915- 1026.Statement in Executive Summary Under Operations Could Be Construed to Convey Wrong Meaning.Corrective Page to Be Inserted Encl ML20133H4881997-01-0202 January 1997 Insp Repts 50-324/96-16 & 50-325/96-16 on 961027-1207. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20132G8751996-12-13013 December 1996 Insp Repts 50-324/96-17 & 50-325/96-17 on 961113-15. Violations Noted.Major Areas Inspected:Damaged Locks & Licensee Actions IR 05000324/19960151996-11-22022 November 1996 Insp Repts 50-324/96-15 & 50-325/96-15 on 960915-1026. Violations Noted.Major Areas Inspected:License Operations, Engineering,Maint & Plant Support ML20129H1081996-10-11011 October 1996 Insp Repts 50-324/96-13 & 50-325/96-13 on 960804-0914. Violations Noted.Major Areas Inspected:Aspects of Operations,Engineering,Maint & Plant Support ML20134D3981996-10-0404 October 1996 Insp Repts 50-324/96-14 & 50-325/96-14 on 960624-0823. Violations Noted.Major Areas Inspected:Review of Licensees EQ Program & Followup on Previous Inspection Findings IR 05000324/19910061996-04-11011 April 1996 Insp Repts 50-324/91-06 & 50-325/91-06 on 910301-31.No Violations Noted.Major Areas Inspected:Maint,Surveillance Observation,Operation Safety Verification,Onsite Review Committee,Onsite Followup of Events IR 05000324/19940331994-12-21021 December 1994 Partially Withheld Insp Repts 50-324/94-33 & 50-325/94-33 on 941024-28 & 1121-23 (Ref 10CFR73.21).No Violations Noted. Major Areas Inspected:Protected & Vital Area Access Control of Personnel & Packages IR 05000324/19930561993-12-27027 December 1993 Insp Repts 50-324/93-56 & 50-325/93-56 on 931129-1203.No Violations Identified.Major Areas Inspected:Chemistry/ Effluent Department,Plant Water Chemistry,Radioactive Material Processing & Shipping IR 05000324/19930571993-12-22022 December 1993 Insp Repts 50-324/93-57 & 50-325/93-57 on 931129-1203. Violations Noted.Major Areas Inspected:Electrical Maintenance & Mod.Startup Open Item F2 Neutron Detector Repairs & Inspector Followup Item 92-46-01 Reviewed IR 05000324/19930531993-12-10010 December 1993 Insp Repts 50-324/93-53 & 50-325/93-53 on 931115-19.No Violations Noted.Major Areas Inspected:Employee Concerns Program & Actions on Previous Insp Findings IR 05000324/19930491993-11-24024 November 1993 Insp Repts 50-325/93-49 & 50-324/93-49 on 931009-31. Violations Noted But Not Cited.Major Areas Inspected: Maintenance,Operations,Onsite Review Committee & three-year Plan IR 05000324/19930471993-11-22022 November 1993 Partially Withheld Insp Repts 50-324/93-47 & 50-325/93-47 on 931004-08.Noncited Violation Identified.Major Areas Inspected:Physical Security Programs for Power Reactors,Mgt Support,Audits,Protected & Vital Area Barriers IR 05000324/19930501993-11-17017 November 1993 Insp Repts 50-324/93-50 & 50-325/93-50 on 931025-29.No Violations Noted.Major Areas Inspected:Investigation of Unit 2 Fuel Pool Leakage Problem,Tendon Surveillance Program & Followup on Previous Insp Findings IR 05000324/19930511993-11-10010 November 1993 Insp Repts 50-324/93-51 & 50-325/93-51 on 931025-29.No Violations Noted.Major Areas Inspected:Isi Review of Visual Exam Data & Evaluations for Select Welds in Unit 1 Reactor Vessel Shroud 1999-08-27
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000324/19990061999-10-0606 October 1999 Insp Repts 50-324/99-06 & 50-325/99-06 on 990801-0911.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000324/19990051999-08-27027 August 1999 Insp Repts 50-324/99-05 & 50-325/99-05 on 990620-0731.Two Violations Noted Being Treated as Ncv.Major Areas Inspected: Operations,Maint & Plant Support IR 05000324/19990041999-07-19019 July 1999 Insp Repts 50-324/99-04 & 50-325/99-04 on 990509-0619. Non-cited Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support.Includes Results of Y2K Readiness Program Review IR 05000324/19990031999-06-0707 June 1999 Insp Repts 50-324/99-03 & 50-325/99-03 on 990328-0508.Two Violations Noted & Being Treated as non-cited Violations. Major Areas Inspected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000324/19990021999-04-26026 April 1999 Forwards Insp Repts 50-324/99-02 & 50-325/99-02 on 990214-0327.No Violations Noted.Major Areas Inspected: Licensee Operation,Engineering,Maint & Plant Support IR 05000324/19980141999-03-18018 March 1999 Insp Repts 50-324/98-14 & 50-325/98-14 on 990111-15,25 & 29. No Violations Noted.Major Areas Inspected:Licensee Calculations,Analysis,Performance Test Procedures & Other Engineering Activities IR 05000324/19990011999-03-15015 March 1999 Insp Repts 50-324/99-01 & 50-325/99-01 on 990103-0213.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000324/19980111999-01-28028 January 1999 Insp Repts 50-324/98-11 & 50-325/98-11 on 981122-990102.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint & Plant Support IR 05000324/19980101998-12-21021 December 1998 Insp Repts 50-324/98-10 & 50-325/98-10 on 981011-1121. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support.Also Includes Results of Engineering & Health Physics Insp IR 05000324/19980131998-11-24024 November 1998 Partially Withheld Insp Repts 50-324/98-13 & 50-325/98-13 on 981026-30 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Aspects of Licensee Plant Support IR 05000324/19980091998-11-0909 November 1998 Insp Repts 50-324/98-09 & 50-325/98-09 on 980830-1010. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000324/19980081998-09-28028 September 1998 Insp Repts 50-324/98-08 & 50-325/98-08 on 980719-0829.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19980071998-08-11011 August 1998 Insp Repts 50-324/98-07 & 50-325/98-07 on 980607-0718. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19980061998-07-0606 July 1998 Insp Repts 50-324/98-06 & 50-325/98-06 on 980426-0606. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19980051998-06-0101 June 1998 Insp Repts 50-324/98-05 & 50-325/98-05 on 980315-0425. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20216H4431998-04-16016 April 1998 Insp Repts 50-324/98-04 & 50-325/98-04 on 980209-13,0309-12 & 16-20.Violations Noted.Major Areas inspected:follow-up on Licensee Corrective Actions for Electrical Equipment Environ Qualification & Review of Instrument Response Time Testing IR 05000324/19980031998-04-13013 April 1998 Insp Repts 50-324/98-03 & 50-325/98-03 on 980201-0314.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support.Also Includes Results of Health Physics Insp by Regional Inspectors ML20217C8061998-03-16016 March 1998 Insp Repts 50-324/98-01 & 50-325/98-01 on 980126-30. Violations Noted.Major Areas Inspected:Emergency Preparedness Exercise ML20216B1741998-03-0202 March 1998 Insp Repts 50-324/97-15 & 50-325/97-15 on 971228-980131. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support ML20202D3161998-02-0505 February 1998 Omitted Page 42 to Insp Repts 50-324/97-13 & 50-325/97-13 Transmitted on 980123 ML20199G7501998-01-23023 January 1998 Insp Repts 50-324/97-13 & 50-325/97-13 on 971109-1227. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support.Includes Results of Maint, Engineering & FP Insps ML20198N6561997-12-30030 December 1997 Insp Repts 50-324/97-14 & 50-325/97-14 on 971209-12. Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Controls,Miscellaneous Radiation Protection & Chemistry Issues & Mgt Meetings IR 05000324/19970141997-12-30030 December 1997 Insp Repts 50-324/97-14 & 50-325/97-14 on 971209-12. Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Controls,Miscellaneous Radiation Protection & Chemistry Issues & Mgt Meetings ML20197H1881997-12-0808 December 1997 Insp Repts 50-324/97-12 & 50-325/97-12 on 970928-1108. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19970111997-10-27027 October 1997 Insp Repts 50-324/97-11 & 50-325/97-11 on 970819-0927. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000324/19970091997-09-15015 September 1997 Insp Repts 50-324/97-09 & 50-325/97-09 on 970706-0816. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support Re Improper Processing of Changes to Fire Protection Instrumentation Surveillance IR 05000324/19970101997-08-0808 August 1997 Insp Repts 50-324/97-10 & 50-325/97-10 on 970728-30.No Violations Noted.Major Areas Inspected:Plant Support ML20198F4101997-08-0101 August 1997 Insp Repts 50-324/97-08 & 50-325/97-08 on 970525-0705. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000324/19970071997-06-20020 June 1997 Integrated Insp Repts 50-324/97-07 & 50-325/97-07 on 970413-0524.No Violations Noted.Major Areas Inspected: Licensee Operations,Engineering,Maint & Plant Support ML20140D1781997-05-12012 May 1997 Insp Repts 50-324/97-05 & 50-325/97-05 on 970302-0412. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000324/19970061997-05-0909 May 1997 Safeguards Insp Repts 50-324/97-06 & 50-325/97-06 on 970409-11.No Violations Noted.Major Areas Inspected:Aspects of Licensee Plant Support,Status of Security Facilities & Equipment ML20138J5981997-05-0202 May 1997 Insp Repts 50-324/97-03 & 50-325/97-03 on 970303-0404. Violations Noted.Major Areas Inspected:Review of Licensee Engineering Activities to Support Operation of Plant EQ Program & Followup on Previous Insp Findings IR 05000324/19970041997-04-0404 April 1997 Safeguard Insp Repts 50-324/97-04 & 50-325/97-04 on 970303-07.No Violations Noted.Major Areas Inspected:Plant Support & Security & Safeguards Procedures & Documentation ML20137T5711997-03-31031 March 1997 Insp Repts 50-324/97-02 & 50-325/97-02 on 970119-0301. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering,Plant Support & Emergency Preparedness ML20134P1551997-02-14014 February 1997 Insp Repts 50-324/96-18 & 50-325/96-18 on 961208-970118. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20133L5931997-01-0909 January 1997 Errata to Insp Repts 50-324/96-15 & 50-325/96-15 on 960915- 1026.Statement in Executive Summary Under Operations Could Be Construed to Convey Wrong Meaning.Corrective Page to Be Inserted Encl ML20133H4881997-01-0202 January 1997 Insp Repts 50-324/96-16 & 50-325/96-16 on 961027-1207. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20132G8751996-12-13013 December 1996 Insp Repts 50-324/96-17 & 50-325/96-17 on 961113-15. Violations Noted.Major Areas Inspected:Damaged Locks & Licensee Actions IR 05000324/19960151996-11-22022 November 1996 Insp Repts 50-324/96-15 & 50-325/96-15 on 960915-1026. Violations Noted.Major Areas Inspected:License Operations, Engineering,Maint & Plant Support ML20129H1081996-10-11011 October 1996 Insp Repts 50-324/96-13 & 50-325/96-13 on 960804-0914. Violations Noted.Major Areas Inspected:Aspects of Operations,Engineering,Maint & Plant Support ML20134D3981996-10-0404 October 1996 Insp Repts 50-324/96-14 & 50-325/96-14 on 960624-0823. Violations Noted.Major Areas Inspected:Review of Licensees EQ Program & Followup on Previous Inspection Findings IR 05000324/19910061996-04-11011 April 1996 Insp Repts 50-324/91-06 & 50-325/91-06 on 910301-31.No Violations Noted.Major Areas Inspected:Maint,Surveillance Observation,Operation Safety Verification,Onsite Review Committee,Onsite Followup of Events IR 05000324/19940331994-12-21021 December 1994 Partially Withheld Insp Repts 50-324/94-33 & 50-325/94-33 on 941024-28 & 1121-23 (Ref 10CFR73.21).No Violations Noted. Major Areas Inspected:Protected & Vital Area Access Control of Personnel & Packages IR 05000324/19930561993-12-27027 December 1993 Insp Repts 50-324/93-56 & 50-325/93-56 on 931129-1203.No Violations Identified.Major Areas Inspected:Chemistry/ Effluent Department,Plant Water Chemistry,Radioactive Material Processing & Shipping IR 05000324/19930571993-12-22022 December 1993 Insp Repts 50-324/93-57 & 50-325/93-57 on 931129-1203. Violations Noted.Major Areas Inspected:Electrical Maintenance & Mod.Startup Open Item F2 Neutron Detector Repairs & Inspector Followup Item 92-46-01 Reviewed IR 05000324/19930531993-12-10010 December 1993 Insp Repts 50-324/93-53 & 50-325/93-53 on 931115-19.No Violations Noted.Major Areas Inspected:Employee Concerns Program & Actions on Previous Insp Findings IR 05000324/19930491993-11-24024 November 1993 Insp Repts 50-325/93-49 & 50-324/93-49 on 931009-31. Violations Noted But Not Cited.Major Areas Inspected: Maintenance,Operations,Onsite Review Committee & three-year Plan IR 05000324/19930471993-11-22022 November 1993 Partially Withheld Insp Repts 50-324/93-47 & 50-325/93-47 on 931004-08.Noncited Violation Identified.Major Areas Inspected:Physical Security Programs for Power Reactors,Mgt Support,Audits,Protected & Vital Area Barriers IR 05000324/19930501993-11-17017 November 1993 Insp Repts 50-324/93-50 & 50-325/93-50 on 931025-29.No Violations Noted.Major Areas Inspected:Investigation of Unit 2 Fuel Pool Leakage Problem,Tendon Surveillance Program & Followup on Previous Insp Findings IR 05000324/19930511993-11-10010 November 1993 Insp Repts 50-324/93-51 & 50-325/93-51 on 931025-29.No Violations Noted.Major Areas Inspected:Isi Review of Visual Exam Data & Evaluations for Select Welds in Unit 1 Reactor Vessel Shroud 1999-08-27
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARPNO-II-99-045, on 991018,Hurricane Irene Was Located Approx 105 Miles East of Cape Hatteras,Nc.Ctr of Hurricane Was Estimated Near Latitude 35.6 North & Longitude 73.8 West. Storm Was Moving Northeast at 35 Mph1999-10-18018 October 1999 PNO-II-99-045:on 991018,Hurricane Irene Was Located Approx 105 Miles East of Cape Hatteras,Nc.Ctr of Hurricane Was Estimated Near Latitude 35.6 North & Longitude 73.8 West. Storm Was Moving Northeast at 35 Mph IR 05000324/19990061999-10-0606 October 1999 Insp Repts 50-324/99-06 & 50-325/99-06 on 990801-0911.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support PNO-II-99-037D, on 990915,Hurricane Floyd Was Located Approx 380 Miles Southeast of Wilmington,Nc.Ctr of Hurricane Was Estimated Near Latitude 28.8 North & Longitude 78.8 West. Storm Was Moving Northwest at 14 Mph.Max Winds Were 140 Mph1999-09-15015 September 1999 PNO-II-99-037D:on 990915,Hurricane Floyd Was Located Approx 380 Miles Southeast of Wilmington,Nc.Ctr of Hurricane Was Estimated Near Latitude 28.8 North & Longitude 78.8 West. Storm Was Moving Northwest at 14 Mph.Max Winds Were 140 Mph PNO-II-99-037E, on 990915,Hurricane Floyd Was Located Approx 380 Miles Southeast of Wilmington,Nc.Ctr of Hurricane Was Estimated Near Latitude 29.3 North & Longitude 78.8 West. Storm Was Moving north-northwest at 14 Mph1999-09-15015 September 1999 PNO-II-99-037E:on 990915,Hurricane Floyd Was Located Approx 380 Miles Southeast of Wilmington,Nc.Ctr of Hurricane Was Estimated Near Latitude 29.3 North & Longitude 78.8 West. Storm Was Moving north-northwest at 14 Mph PNO-II-99-037F, on 990915,Hurricane Floyd Was Located Approx 350 Miles Southeast of Wilmington,Nc.Ctr of Hurricane Was Estimated Near Latitude 29.9 North & Longitude 79.0 West. Storm Was Moving north-northwest at 14 Mph1999-09-15015 September 1999 PNO-II-99-037F:on 990915,Hurricane Floyd Was Located Approx 350 Miles Southeast of Wilmington,Nc.Ctr of Hurricane Was Estimated Near Latitude 29.9 North & Longitude 79.0 West. Storm Was Moving north-northwest at 14 Mph PNO-II-99-037H, on 990915,Hurricane Floyd Was Located Approx 168 Miles Southeast of Bsep.Ctr of Hurricane Was Estimated Near Latitude 31.3 North & Longitude 79.0 West.Storm Was Moving North at 17 Mph with Max Winds at 115 Mph1999-09-15015 September 1999 PNO-II-99-037H:on 990915,Hurricane Floyd Was Located Approx 168 Miles Southeast of Bsep.Ctr of Hurricane Was Estimated Near Latitude 31.3 North & Longitude 79.0 West.Storm Was Moving North at 17 Mph with Max Winds at 115 Mph PNO-II-99-037G, on 990915,Hurricane Floyd Was Located Approx 216 Miles Southeast of Bsep.Ctr of Hurricane Was Estimated Near Latitude 30.6 North & Longitude 79.1 West.Storm Was Moving north-northwest at 14 Mph with Max Winds at 125 Mph1999-09-15015 September 1999 PNO-II-99-037G:on 990915,Hurricane Floyd Was Located Approx 216 Miles Southeast of Bsep.Ctr of Hurricane Was Estimated Near Latitude 30.6 North & Longitude 79.1 West.Storm Was Moving north-northwest at 14 Mph with Max Winds at 125 Mph PNO-II-99-035, on 990830,util Secured from Notification of Unusual Event After Hurricane Warning Lifted for Area.Plant Had Been Placed in Hot Shutdown Due to Predicted Hurricane Track.Unit 2 Commenced Restart on 9908311999-08-31031 August 1999 PNO-II-99-035:on 990830,util Secured from Notification of Unusual Event After Hurricane Warning Lifted for Area.Plant Had Been Placed in Hot Shutdown Due to Predicted Hurricane Track.Unit 2 Commenced Restart on 990831 PNO-II-99-033, on 990830,Hurricane Dennis Was Located Approx 72 Miles Southeast of Bsep.No Significant Damage Has Been Sustained at Site.Ge Facility Suspended Fuel Fabrication Processes & No Significant Damage Was Sustained1999-08-30030 August 1999 PNO-II-99-033:on 990830,Hurricane Dennis Was Located Approx 72 Miles Southeast of Bsep.No Significant Damage Has Been Sustained at Site.Ge Facility Suspended Fuel Fabrication Processes & No Significant Damage Was Sustained IR 05000324/19990051999-08-27027 August 1999 Insp Repts 50-324/99-05 & 50-325/99-05 on 990620-0731.Two Violations Noted Being Treated as Ncv.Major Areas Inspected: Operations,Maint & Plant Support IR 05000324/19990041999-07-19019 July 1999 Insp Repts 50-324/99-04 & 50-325/99-04 on 990509-0619. Non-cited Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support.Includes Results of Y2K Readiness Program Review IR 05000324/19990031999-06-0707 June 1999 Insp Repts 50-324/99-03 & 50-325/99-03 on 990328-0508.Two Violations Noted & Being Treated as non-cited Violations. Major Areas Inspected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000324/19990021999-04-26026 April 1999 Forwards Insp Repts 50-324/99-02 & 50-325/99-02 on 990214-0327.No Violations Noted.Major Areas Inspected: Licensee Operation,Engineering,Maint & Plant Support IR 05000324/19980141999-03-18018 March 1999 Insp Repts 50-324/98-14 & 50-325/98-14 on 990111-15,25 & 29. No Violations Noted.Major Areas Inspected:Licensee Calculations,Analysis,Performance Test Procedures & Other Engineering Activities IR 05000324/19990011999-03-15015 March 1999 Insp Repts 50-324/99-01 & 50-325/99-01 on 990103-0213.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000324/19980111999-01-28028 January 1999 Insp Repts 50-324/98-11 & 50-325/98-11 on 981122-990102.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint & Plant Support ML20198P0261998-12-21021 December 1998 Notice of Violation from Insp on 981011-1121.Violation Noted:On 981030,licensee Failed to Correctly Shutdown & Verify That Unit 1 Standby Gas Treatment Sys in Standby Alignment Per Section 7.1 of Procedure 1OP-10 IR 05000324/19980101998-12-21021 December 1998 Insp Repts 50-324/98-10 & 50-325/98-10 on 981011-1121. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support.Also Includes Results of Engineering & Health Physics Insp PNO-II-98-050, on 981123,licensee Declared Notification of Unusual Event,Due to Release of Chlorine Gas from Svc Water Injection Sys in Chlorination Bldg.Personnel Were Moved to Alternate Locations Away from Gas Leak,As Precautionary1998-11-24024 November 1998 PNO-II-98-050:on 981123,licensee Declared Notification of Unusual Event,Due to Release of Chlorine Gas from Svc Water Injection Sys in Chlorination Bldg.Personnel Were Moved to Alternate Locations Away from Gas Leak,As Precautionary IR 05000324/19980131998-11-24024 November 1998 Partially Withheld Insp Repts 50-324/98-13 & 50-325/98-13 on 981026-30 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Aspects of Licensee Plant Support IR 05000324/19980091998-11-0909 November 1998 Insp Repts 50-324/98-09 & 50-325/98-09 on 980830-1010. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support ML20195G4191998-11-0909 November 1998 Notice of Violation from Insp on 980830-1010.Violation Noted:On 980916,licensee Failed to Perform Section 7.1.5 of Procedure OMST-RHR-28Q as Required When Returning Flow Transmitter E11-FT-3338 to Service IR 05000324/19980081998-09-28028 September 1998 Insp Repts 50-324/98-08 & 50-325/98-08 on 980719-0829.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support PNO-II-98-039D, on 980827,update on Hurricane Bonnie Made. Walkdowns Confirmed,No Significant Damage to Security Barriers.Licensee Preparations for Plant Restart Continuing, Including Restoration of Warning Sirens1998-08-27027 August 1998 PNO-II-98-039D:on 980827,update on Hurricane Bonnie Made. Walkdowns Confirmed,No Significant Damage to Security Barriers.Licensee Preparations for Plant Restart Continuing, Including Restoration of Warning Sirens PNO-II-98-039C, on 980827,update on Hurricane Bonnie Made. No Significant Damage Has Occurred at Brunswick Plant or GE Fuel Fabrication Facility.Licensee Continues to Staff Technical Support Ctr & Emergency Operations Facility1998-08-27027 August 1998 PNO-II-98-039C:on 980827,update on Hurricane Bonnie Made. No Significant Damage Has Occurred at Brunswick Plant or GE Fuel Fabrication Facility.Licensee Continues to Staff Technical Support Ctr & Emergency Operations Facility PNO-II-98-039B, on 980826,update on Hurricane Bonnie Made. Hurricane Force Winds Have Been Experienced at Site,But No Significant Damage Has Occurred.Licensee Continues to Staff Emergency Facilities.No Other Damage Has Been Reported1998-08-26026 August 1998 PNO-II-98-039B:on 980826,update on Hurricane Bonnie Made. Hurricane Force Winds Have Been Experienced at Site,But No Significant Damage Has Occurred.Licensee Continues to Staff Emergency Facilities.No Other Damage Has Been Reported PNO-II-98-039A, on 980826,update on Hurricane Bonnie Made. Brunswick Resident Inspectors & One Regional Inspector Remain on Site to Monitor Licensee Activities.Region II State Liaison Officer Arrived in Raleigh Area1998-08-26026 August 1998 PNO-II-98-039A:on 980826,update on Hurricane Bonnie Made. Brunswick Resident Inspectors & One Regional Inspector Remain on Site to Monitor Licensee Activities.Region II State Liaison Officer Arrived in Raleigh Area PNO-II-98-039, on 980525,preparations for Hurricane Bonnie Made.Licensee Monitoring Progress of Hurricane in Order to Have Both Units in Cold Shutdown Three H Prior to Arrival of Hurricane Force Winds on Site1998-08-25025 August 1998 PNO-II-98-039:on 980525,preparations for Hurricane Bonnie Made.Licensee Monitoring Progress of Hurricane in Order to Have Both Units in Cold Shutdown Three H Prior to Arrival of Hurricane Force Winds on Site IR 05000324/19980071998-08-11011 August 1998 Insp Repts 50-324/98-07 & 50-325/98-07 on 980607-0718. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20237B9211998-08-11011 August 1998 Notice of Violation from Insp on 980607-0718.Violation Noted:Licensee Failed to Accomplish Activities Affecting Quality in Accordance W/Documented Instructions in Procedures for Listed Examples IR 05000324/19980061998-07-0606 July 1998 Insp Repts 50-324/98-06 & 50-325/98-06 on 980426-0606. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20236N9451998-07-0606 July 1998 Notice of Violations from Insp on 980426-0606.Violations Noted:On 980521,licensee Made Temporary Procedure Change That Altered Intent of Maint Surveillance Test 1MST-DG11R, DG-1 Loading Test,By Substituting 25 for 50 Horsepower Load IR 05000324/19983001998-06-15015 June 1998 NRC Operator Licensing Exam Repts 50-324/98-300 & 50-325/98-300 on 980508-15.Six SRO & Four RO Candidates Tested.All Passed Exam.One Candidate Identified as Having Some Performance Weaknesses ML20249A2191998-06-0101 June 1998 Notice of Violation from Insp on 980315-0425.Violation Noted:On 980331 Licensee Failed to Accomplish Scaffolding Erection Activities in Accordance W/Documented Procedure OMMM-022 IR 05000324/19980051998-06-0101 June 1998 Insp Repts 50-324/98-05 & 50-325/98-05 on 980315-0425. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20216H4431998-04-16016 April 1998 Insp Repts 50-324/98-04 & 50-325/98-04 on 980209-13,0309-12 & 16-20.Violations Noted.Major Areas inspected:follow-up on Licensee Corrective Actions for Electrical Equipment Environ Qualification & Review of Instrument Response Time Testing ML20216H4341998-04-16016 April 1998 Notice of Violation from Insp on 980209-13,0309-12 & 16-20. Violation Noted:On 970603,licensee Failed to Accomplish Activities Affecting Quality in Accordance W/Procedure EGR-NGGC-0005 IR 05000324/19980031998-04-13013 April 1998 Insp Repts 50-324/98-03 & 50-325/98-03 on 980201-0314.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support.Also Includes Results of Health Physics Insp by Regional Inspectors ML20217C8011998-03-16016 March 1998 Notice of Violation from Insp on 980126-30.Violation Noted: Rev 46 to Licensee Emergency Plan Decreased Effectiveness of Plan That Adopted Regulatory Provision for Biennial Exercise ML20217C8061998-03-16016 March 1998 Insp Repts 50-324/98-01 & 50-325/98-01 on 980126-30. Violations Noted.Major Areas Inspected:Emergency Preparedness Exercise ML20216B1741998-03-0202 March 1998 Insp Repts 50-324/97-15 & 50-325/97-15 on 971228-980131. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support ML20216B1621998-03-0202 March 1998 Notice of Violation from Insp on 971228-980131.Violation Noted:On 971203 & 971230,for Unit 1 & 971203,971210 & 971220 & 980104 for Unit 2,Condition Repts Were Not Initiated to Address Repetitive Failures of Plant Computer ML20202D3161998-02-0505 February 1998 Omitted Page 42 to Insp Repts 50-324/97-13 & 50-325/97-13 Transmitted on 980123 IR 07100109/20120271998-01-23023 January 1998 Notice of Violation from Insp on 971109-1227.Violation Noted:On 971209,inspector Determined That Licensee Had Not Maintained Data Sheets or Logs for Equipment Alignment ML20199G7501998-01-23023 January 1998 Insp Repts 50-324/97-13 & 50-325/97-13 on 971109-1227. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support.Includes Results of Maint, Engineering & FP Insps ML20198N6461997-12-30030 December 1997 Notice of Violation from Insp on 971209-12.Violation Noted: on 971118,locked High Radiation Area Was Left Unattended & Entrance Was Not Secured W/Designated Special cal-core Locks Prior to Leaving Area Unguarded ML20198N6561997-12-30030 December 1997 Insp Repts 50-324/97-14 & 50-325/97-14 on 971209-12. Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Controls,Miscellaneous Radiation Protection & Chemistry Issues & Mgt Meetings IR 05000324/19970141997-12-30030 December 1997 Insp Repts 50-324/97-14 & 50-325/97-14 on 971209-12. Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Controls,Miscellaneous Radiation Protection & Chemistry Issues & Mgt Meetings ML20198P0561997-12-23023 December 1997 NOV from Insp Completed on 971113.Violation Noted:Licensee Failed to Promptly Correct Condition Adverse to Quality Re Unit 1 High Drywell Temp Condition ML20197H1691997-12-0808 December 1997 Notice of Violation from Insp on 970928-1108.Violation Noted:On 970923,torus Master clearance,2-97-555 Was Not Adequate to Prevent Draining of Water Into Unit 2 Torus 1999-09-15
[Table view] |
See also: IR 05000324/1997014
Text
_ - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
.
.. . .
- .
.
..
4 l1 S. NUCLEAR REGULATORY COMMISSION
REGION 11 ,,
Docket Nos: 50-325, 50-324
License Nos: DPR-71. DPR-62
Report No: 50-325/97-14, 50 324/97-14
Licensee: Carolina Power & Light (CP&L)
Facility: Brunswick Steam Electric Plant. Units 1 & 2
Location: 8470 River Road SE
Southport. NC 28461
Dates: December 9-12, 1997
Inspector: W. Rankin. Senior Project Manager
Approved by: K. Barr, Chief. Plant Support Branch
Division of Reactor Safety
'
9901210160 971230
PDR ADOCK 05000324
G PDR
Enclosure 2
__- - _-- ____--__ _-_-___-_________- __ _ _ =___ _ ___-- _ __ _ _ _ _ _ _ _ _ _ -_- - _ __ _ _
- .
-
.
EXECUTIVE SUMMARY
Brunswick Steam Electric Plant Units 1 & 2
NRC Inspection Report Nos. 50J> /97-14 '50-324/97-14
Plant Sunoort
e The radiation control program uas effectively implemented with good
occupational exposure controls c5 served during norndl plant operations,
(Section R1.1)
e The licensee's_off-site dose projection software. CPLDOSE, was evaluated
and determined to be functioning as designed with no flaws identified.
(Section R8.1)
e Ona violation was identified for failure to control a Locked High
Radiation Area in accordance with procedure. (Section RI.1)
'e One violation was identified for failure to initiate a condition report
- upon identifying a Locked High Radiation Area not co.ntrolled in
accordance with procedure. (Section R1.1)
s
__________.___.___._____m._______m. _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . __ ___
_____
- - .
L
t- .
-
.
Report Details
Plant Support
R1 Radiation Protection and Chemistry Controls
R1.2 Extern; Occooational Exoosure Conttch
a. Insoection Scooe (83750)
The inspector evaluated aspects of the licensee's radiation control
program against the applicable requirements of 10 CFR Part 20. Technical
Specifications, and the Updated Final Safety Analysis Report (UFSAR).
The inspector also evaluated licensee radiological controls with
emphasis on on external occupational exposure during normal plant
operations.
b. Observations and Findinas
The inspector made tours of the radiation control area, observed
compliance of licensee personnel with radiation protection procedures
for routine work evolutions, and conducted interviews with licensee
personnel with respect to knowledge of radiation controls and specific
radiological working conditions.
During plant walkdowns within the Radiologically Controlled Area IPCA),
the inspector conducted brief interviews at random with radiattor,
workers inside the RCA in order to determine the level of understanding
of Radiation Work Permit (RWP) requirements and radiation working
conditions. The workers interviewed were verified to have signed on to
an RWP. were wearing dosimetry appropriate to their work activities
'
within the RCA, and were performing specific work activities on
appropriate RWPs.
The inspector reviewed total effective doses for radiation workers at s
'
the site and determined that all personnel exposures assigned since the
beginning of 1997 through December 11, 1997 were within 10 CFR Part 20
limits. The inspector determined that the licensee had adequately
monitored and tracked individual occupation ' radiation exposures in
\ accordance with 10 CFR Part 20 requirements and that doses reported were
at a small percentage of regulatory limits.
The inspector reviewed and discussed with licensee representatives the
program for satrolling access to high radiation areas (HRAs), locked .
high radiation areas (LHRAs). and very high radiation areas (VHRAs).
These areas were inspected during tours of Unit 1 and Unit 2 for proper
posting and access controls. No HRAs. LHRAs. or VHRAs were identified
where required posting was needed but not posted. Areas controlled as-
a LHRAs-were inspected and found locked in accordance with licensee
.
- - _ - - - - - _ . - . _ _ _ _ _ - _ _ _ - _ . - _ - _ _ - - - - - _ . - . _ . _ . . . - _ _ - - - - _ - _ - _ _ _ _ - _ - _ . _ _ _ _ _ . _ _ - _ - _ - , _ _ _ _ _ ,
_ _ . _
_ _ _ _ _ _ _ _ -
-
.
.
.
2
procedure. Key controls for entry into locked and very high radiation
areas were evaluated against the requirements of the licensee's-
administrative control procedure and determined to be controlled in
accordance with procedure.
During evaluation of LHRA controls the inspector reviewed the licensee's
use of a 200 Curie Cs-137 source used primarily in the calibration of
pocket dosimeters maintained for emergency preparedness purposes. Upon
review of radiological surveys conducted during recent uses of the
Cs-137 source, it was determined that on November 18. 1997, the area met
Technical Specification 6.12.2 LHRA criteria and OE&RC-0040 " Control of
Locked High Radiation and Very High Radiation Areas". Rev. 15. Step 7.1.
procedural requirements for an area that must be controlled as a LHRA in
that area dose rates exceeded 1 Rem /hr. The applicable survey for the
calibration room (Survey No. 1118-30 dated 11/18/97) performed during
the calibration work with the Cs-137 source exposed (at the three foot
elevation with shields out) indicated 10 Rem /Hr. near the ceiling and
1.5-2.0 Rem /Hr. behind the shield window which constituted general area
readings in the room of greater than 1 Rem /Hr. These general area
radiation levels in the room at the time met LHRA criteriu and
necessitated LHRA controls for the period during which these conditions
existed. However. during interviews with radiation control personnel
directly involved with the specific controls that were in place at the
start of the dosimeter calibration work on November 18. 1997, the
inspector determined that the calibration room was not controlled in
accordance with LHRA procedural requirements. Specifically, access was
not properly controlled and the entrance to the room was not secured
with designated special cal-core locks required for LHRAs prior to to
leaving the area unguarded. Although the actual doses received by the
radiction workers involved with the dosimetry calibration work conducted
on November 18. 1997 were small. the radiological controls in place were
not sufficient to provide reasonable assurance against the potential for
greater exposure. Of particular concern were the insufficient controls
for the foot pedal and the " source up" control panel which were not
locked out or controlled in any positive manner. Although the door to
the calibration room containing the source was maintained locked,
insufficient positive control over the door key inventory was evident.
The licensee was informed the failure to control tne calibration room as
a LHRA was a violation of licensee procedure OE&RC-0040 requirements.
This is designated Violation 50-325(324)/97-14-01. Failure to control a
Locked High Radiation Area in accordance with procedural requirements.
During discussions with licensee radiation control personnel associated
with the November 18. 1997 dosimetry calibration work. the inspector
inquired as to the status of corrective actions for the adverse
conditions identified. Licensee representatives indicated that
immediate corrective actions were undertaken at the time of the incident
to include dedicated job coverage by a qualified Radiation Control
I
_ _ _ _
_ - - - - _
-
.
3 ,
,
Technician through completion of the dosimeter calibration work. The
inspector determined, however, that no follow up_ corrective actions had
occurred and in fact, the incident was ncver documented in Condition
Reports despite the relative significance of a failure to control a LHRA
in accordance with TS and procedural requirements. 10 CFR 50. Appendix
B. Criterion XVI, requires that measures shall be established to assure
that conditions adverse to quality, such as deficiencies and
nonconformances, are promptly identified and corrected. CP&L Procedure
PLP-04. " Corrective Act'on Management". Revision 23. dated 10/27/97.
1mplements the requirements of Criterion 16 at the Brunswick Nuclear
Plant. Attachment 6 of PLP-04. " Criteria for Condition Reports", states
under examples of conditions which should be Condition Reports, a person
who does not mmply with procedure requirements such as passes material
across a contamination barrier or who does not frisk when required.
Paragraph 6.0 of PLP-04 requires that personnel shall review their
activities for adverse conditions which meet the threshold for
initiating a Condition Report and, upon identifying such a condition,
personnel must initiate a Condition Report. Contrary to this procedural
requirement. on November 18. 1997, the licensee failed to initiate a
Condition Report upon identifying a LHRA not properly controlled in
accordance with procedures, an adverse condition which met the threshold
for initiating a Condition Report. The licensee was informed this
failure to initiate a Condition Report in accordance with procedure was
a violation and is designated Violation 50-325(324)/97-14-02. Failure to
initiate a Condition Report for a LHRA not properly controlled.
c. Conclusions
The radiological controls program was effectively implemented with good
occupational exposure controls demonstrated overall during routine plant
operations. However, one violation was identified for failure to
control a Locked High Radiation Area in accordance with procedural
requirements. Another violation was identified for failure to initiate
a Condition Report for the LHRA not properly controlled.
R8 Miscellaneous Radiation Protection & Chemistry Issues
R8.1 Offsite Dose Projection Under Acci P t Conditions
a. Insoection Scoce (827011
The inspector evaluated the licensee's capabilities to provide off-site
radiological dose projections during accident conditions consistent with
the requirements of the licensee's emergency plan and plant emergency
procedure OPEP-03.4.7. "Offsite Dose Projection". Rev.10. Emphasis was
given to capabilities of the licensee's dose projection software.
CPLDOSE. to provide dose projections for spent fuel handling accidents.
- - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ - . _ - _ _ _ _ _______-_-___ _ _ - _ _ -
.
.
I
4
b. Observati.gn s and Findinas
The inspector evaluated the dose projection capabilities of CPLDOSE
under accident conditions involving a dropped fuel bundle and related
fuel handling accident scenarios. Specifically examined was the design
basis refueling accident in which one fuel assembly is assumed to fall
on to the top of an uncovered reactor core as analyzed in Section 15.7.1
of the UFSAR. A review of CPLDOSE and projected outputs verified that
the CPLDOSE dose projection methodoloay made valid dose projections for
this bounding " worst case" fuel handling accident condition under a
range of source terms, durations, and atmospheric dispersion factors.
The inspector also reviewed a condition report (CR-02632 dated 7/31/97)
which stated that the CPLDOSE source term was potentially invalid for
fuel handling accidents because reactor shutdown time was believed to
affect source term calculations for fuel handling accidents. The CR
stated that data input for the variable time since reautor shutdown
should have little correlation to a fuel handling accident dose
projection. The inspector reviewed with the licensee's senior HP
analyst with technical cognizance for the CPLDOSE methodology the
licensee's evaluation for closure of the condition report. This
evaluation contained analysis for old spent fuel (>5 yrs.) and current
spent fuel and projected the off-site dose consequence for a series of
reactor shutdown times. In each case the source term changed with time
as expected and the dose projection model was validated for the input
data. The inspector reviawed the evaluation and determined the analysis
to be valid with reasonable assumptions used. No errors were identified
in the dose projection methodology during this review. During the
period of time that CPLDOSE was under a five evaluation for the
potential error above (7/31/97 until 8/13/97), the inspector was able to
verify with operations personnel that no fuel movements had occurred.
c. Conclusions
The licensee's offsite dose projection software. CPLDOSE was evaluated
and determined to be functioning as designed with no flaws identified.
V. Manaaement Meetinas
XI. Exit Meetina Summary
The inspector presented the inspection results to members of licensee
management at the conclusion of the inspection on December 12, 1997. The
licensee acknowledged the findings presented.
.
1
__ _ _ _ _ . _____________ ______________ _ ___
- . _ _ _
. .
.- .
5-
'
PARTIAL LIST OF PERSONS CONTACTED
L1sAufER
M. Christinziano. Manager. Environmental and Radiation Control
R. Crate. Superintendent. Radiation Protection
S. Hinnant. Vice. President. Brunswick Steam Electric Plant
W. Hinson, Radiation _ Control Supervisor-Dosimetry
K. Jury. Manager, Regulatory Affairs
J. Lyash. Plant General Manager
D. Pacini. Radiation Control Supervisor
T. Priest. Radiation Control Supervisor
P. Sawyer. Radiation Control Supervisor
S. Tabor. Senior Specialist. Regulatory Compliance
Other licensee employees or contractors included office, operations,
chemistry, and radiation control personnel.
IEC
E. Brown Resident Inspector
E. Guthrie. Resident Inspector
-C. Patterson. Senior Resident Inspector
INSPECTION PROCEDURES USED
1
IP 83750: Occupational Radiation Exposure Controls
ITEMS OPENED. CLOSED, AND DISCUSSED
Onened-
50-325(324)/97-14-01 VIO Failure to control a Locked High Radiation Area
in accordance with procedure (Section R1.1)
50-325(324)/97-14-02 VIO Failure to initiate a condition report upon
identifying a Locked High Radiation Area not
controlled in accordance with procedure
(Section Rl.1)