MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) ML24032A2182023-09-0101 September 2023 Information Request, Security IR 2024401 GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation ML23143A1202023-06-27027 June 2023 Request Number 4ISI-11 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Regarding Alternate Examination of Reactor Vessel Welds GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance ML23163A2502023-06-12012 June 2023 Summary of Changes and Analysis for Revision 41 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report ML23157A2702023-06-0101 June 2023 4-2022-011 -022 Letter - OI Closure to Licensee IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report ML23013A0812023-03-15015 March 2023 Issuance of Amendment No. 270 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4B GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 2024-01-08
[Table view] |
Text
" " January 10, 2017 EA-16-212
Mr. Mark Chief Executive Officer Energy Northwest 76 North Power Plant Loop P.O. Box 968 - Mail Drop 1023 Richland, WA 99352-0968 SUBJECT COLUMBIA GENERATING STATION - NRC SECURITY INSPECTION REPORT 05000397/2016404 AND APPARENT VIOLATION
Dear Mr. Reddemann:
This letter refers to the inspection conducted by the U.S. Nuclear Regulatory Commission at your Columbia Generating Station. The purpose of the inspection was to ensure compliance of your Security Training and Security Equipment Performance, Testing, and Maintenance programs. The enclosed report presents the results of this inspection. The inspector discussed the preliminary inspection finding with members of your staff at the conclusion of the on-site portion of the inspection. A final exit briefing was conducted (telephonically) with Mr. W. Hettel, Vice President, Operations, and other members of your staff on December 5, 2016.
This inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions in your license.
Within these areas, the inspection consisted of an examination of selected procedures and representative records, observations of activities, and interviews with personnel.
Based on the results of this inspection, apparent violations were identified and are being considered for escalated enforcement action in accordance with the NRC Enforcement Policy.
The current Enforcement Policy is included on the NRC's Web site at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html. The circumstances surrounding these apparent violations, the significance of the issues, and the need for lasting and effective corrective actions were discussed with members of your staff at the inspection exit meeting on December 5, 2016.
In addition, since you identified the issues, and based on our understanding of your corrective actions, a civil penalty may not be warranted in accordance with Section 2.3.4 of the Enforcement Policy. The final decision will be based on you confirming on the license docket that the corrective actions previously described to the NRC staff have been or are being taken. Before the NRC makes its enforcement decision, we are providing you an opportunity to (1) respond to the apparent violations addressed in this inspection report within 30 days of the date of this letter or (2) request a pre-decisional enforcement conference. If a pre-decisional enforcement conference is held, the NRC will issue a press release to announce the time and date of the conference; however, the pre-decisional enforcement conference will be closed to public observation since Security-Related Information will be discussed. If you decide to participate in a pre-decisional enforcement conference, please contact Mark S. Haire, Chief, Plant Support Branch 1, at 817-200-1527 within 10 days of the date of this letter. A pre-decisional enforcement conference should be held within 30 days of the date of this letter.
If you choose to provide a written response to the apparent violations, it should be clearly marked as "Response to Apparent Violations in NRC Inspection Report 05000397/2016404; EA16-212," and should include (1) the reason for the apparent violations or, if contested, the basis for disputing the apparent violations; (2) the corrective steps that have been taken and the results achieved; (3) the corrective steps that will be taken; and (4) the date when full compliance will be achieved. Your response may reference or include previously docketed correspondence, if the correspondence adequately addresses the required response. In addition, please mark your entire response, "Security-Related Information - Withhold from Public Disclosure Under Title 10 of the Code of Federal Regulations (10 CFR) 2.390." In accordance with 10 CFR 2.390(b)(ii), the NRC is waiving the affidavit requirements for your response to this letter. To the extent possible, your response should not include any personal privacy, proprietary, or Safeguards Information. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.
If you choose to request a pre-decisional enforcement conference, the conference will afford you the opportunity to provide your perspective on these matters and any other information that you believe the NRC should take into consideration before making an enforcement decision. The decision to hold a pre-decisional enforcement conference does not mean that the NRC has determined that violations have occurred or that enforcement action will be taken. This conference would be conducted to obtain information to assist the NRC in making an enforcement decision. The topics discussed during the conference may include information to determine whether violations occurred, information to determine the significance of the violations, information related to the identification of the violations, and information related to any corrective actions taken or planned.
In addition, please be advised that the number and characterization of apparent violations described in the enclosed inspection report may change as a result of further NRC review. You will be advised by separate correspondence of the results of our deliberations on this matter.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. If you have any questions concerning this matter, please contact Mark Haire of my staff at 817-200-1527.
Sincerely,/RA/ Anton Vegel, Director Division of Reactor Safety Docket No. 50-397 License No. NPF-21 Nonpublic
Enclosure:
Inspection Report 05000397/2016404
w/Attachment:
Supplemental Information
cc w/enclosure: Mr. Stephen Sullivan Security Operations Manager Energy Northwest Columbia Generating Station PE30 76 North Power Plant Loop Richland, WA 99352 cc w/o enclosure:
Electronic Distribution