MONTHYEARIR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) IR 05000263/20230062024-02-28028 February 2024 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2023006) IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) IR 05000263/20220062023-03-0101 March 2023 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2022006) ML23058A1522023-02-27027 February 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2023002 IR 05000263/20220052022-08-29029 August 2022 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2022005) IR 05000263/20210062022-03-0202 March 2022 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2021006) ML21322A2362021-11-18018 November 2021 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2022401 IR 05000263/20210052021-09-0101 September 2021 Updated Inspection Plan for Monticello Nuclear Generating Plant 2 (Report 05000263/2021005) ML21215A2172021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21147A5082021-06-0303 June 2021 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21099A0902021-04-0808 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000263/2021011 ML21085A8582021-03-26026 March 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000263/2021010 IR 05000263/20200062021-03-0404 March 2021 Annual Assessment Letter for the Monticello Nuclear Generating Plant (Report 05000263/2020006) ML21029A2982021-01-29029 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2021002 ML20275A3942020-10-0101 October 2020 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at the Monticello Nuclear Generating Plant IR 05000263/20200052020-09-0101 September 2020 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2020005) ML20134H9282020-05-12012 May 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000263/2020013 IR 05000263/20190062020-03-0303 March 2020 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2019006 and 07200058/2019006) ML19324F8512019-11-20020 November 2019 Long-Term Replacement Steam Dryer Inspection Plan ML19322C0512019-11-14014 November 2019 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report Number 05000263/2020011 IR 05000263/20190052019-08-28028 August 2019 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2019005) ML19136A0202019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19065A0832019-03-0505 March 2019 Ltr. 03/05/19 Monticello Nuclear Generating Plant - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2019002 (DRS-E.Fernandez) IR 05000263/20180062019-03-0404 March 2019 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2018006 and 07200058/2018006) IR 05000263/20180052018-08-28028 August 2018 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2018005) IR 05000263/20170062018-03-0202 March 2018 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2017006) ML17345A8402017-12-11011 December 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Monticello Nuclear Generating Plant IR 05000263/20170052017-08-28028 August 2017 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2017005) ML17159A6992017-06-0808 June 2017 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2017409 ML17094A4352017-04-0303 April 2017 Monticello - Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000263/20160062017-03-0101 March 2017 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2016006) ML17026A4302017-01-26026 January 2017 Notification of NRC Triennial Fire Protection Baseline Inspection and Request for Information 05000263/2017007 IR 05000263/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2016005) IR 05000263/20150062016-03-0202 March 2016 Annual Assessment Letter for Monticello Nuclear Generating Plant (Inspection Report 05000263/2015006) ML16041A0482016-02-0909 February 2016 Ltr. 02/09/16 Monticello Nuclear Generating Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000263/2016002 IR 05000263/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2015005) IR 05000263/20140012015-03-0404 March 2015 Annual Assessment Letter for the Monticello Nuclear Generating Plant, (Report 05000263/2014001) ML15027A0412015-01-26026 January 2015 ISI Request for Information ML14245A1442014-09-0202 September 2014 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant ML14216A5132014-08-0404 August 2014 Information Request to Support Upcoming Biennial Problem Identification and Resolution Inspection at the Monticello Nuclear Generating Plant IR 05000263/20130012014-03-0404 March 2014 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2013001) ML13246A2312013-09-0303 September 2013 2013 Monticello MOC Letter Combined ML13221A5712013-08-0909 August 2013 Ltr 8/9/13 Monticello MOD 50.59 Request for Information IR 05000263/20120012013-03-0404 March 2013 Annual Assessment Letter for Monticello Nuclear Generating Plant, (Report 05000263-12-001) ML12249A4222012-09-0404 September 2012 Mid-Cycle Assessment Letter for Monticello Generating Plant IR 05000263/20110072012-03-0505 March 2012 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2011007) IR 05000263/20110062011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plant for Monticello Nuclear Plant 05000263-11-006 IR 05000263/20110012011-03-0404 March 2011 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263-11-001) ML1104705722011-02-16016 February 2011 Request Notification of NRC Inspection and Request for Information ISI 2024-08-30
[Table view] Category:Letter
MONTHYEARML24283A1192024-10-28028 October 2024 Letter to Shawn Hafen, Re Monticello Subsequent License Renewal Schedule Change L-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI ML24277A0202024-10-0303 October 2024 Operator Licensing Examination Approval Monticello Nuclear Generating Plant, October 2024 IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 ML24199A1752024-10-0101 October 2024 Issuance of Amendment No. 212 Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality 05000263/LER-2024-002, Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure2024-08-27027 August 2024 Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure ML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24215A2992024-07-23023 July 2024 Minnesota State Historic Preservation Office Comments on Monticello SLR Draft EIS ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) ML24164A2402024-06-10010 June 2024 Minnesota State Historic Preservation Office- Comments on Draft Monticello SLR Draft EIS L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 ML24137A2792024-06-0303 June 2024 Audit Summary for License Amendment Request to Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report ML24135A1902024-05-14014 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 ML24128A0042024-05-0909 May 2024 Letter to Minnesota State Historic Preservation Office- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application ML24127A1472024-05-0909 May 2024 Letter to Mille Lacs Band- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renew. Application L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance IR 05000263/20240012024-04-29029 April 2024 Plan - Integrated Inspection Report 05000263/2024001 ML24115A2872024-04-25025 April 2024 Sec106 Tribal, Dupuis, Kevin-Fond Du Lac Band of Lake Superior Chippewa ML24115A2962024-04-25025 April 2024 Sec106 Tribal, Larsen, Robert-Lower Sioux Indian Community ML24115A3072024-04-25025 April 2024 Sec106 Tribal, Williams, Jr., James-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24115A3052024-04-25025 April 2024 Sec106 Tribal, Vanzile, Jr., Robert-Sokaogon Chippewa Community ML24115A2892024-04-25025 April 2024 Sec106 Tribal, Fowler, Thomas-St. Croix Chippewa of Wisconsin ML24115A3022024-04-25025 April 2024 Sec106 Tribal, Stiffarm, Jeffrey-Fort Belknap Indian Community ML24115A2972024-04-25025 April 2024 Sec106 Tribal, Miller, Cole-Shakopee Mdewakanton Sioux Community ML24115A2952024-04-25025 April 2024 Sec106 Tribal, Kakkak, Gena-Menominee Indian Tribe of Wisconsin ML24115A2922024-04-25025 April 2024 Sec106 Tribal, Jensvold, Kevin-Upper Sioux Community ML24115A3062024-04-25025 April 2024 Sec106 Tribal, Wassana, Reggie-Cheyenne and Arapaho Tribes ML24115A2912024-04-25025 April 2024 Sec106 Tribal, Jacskon, Sr., Faron-Leech Lake Band of Ojibwe 05000263/LER-2024-001, Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component2024-04-25025 April 2024 Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component ML24115A2982024-04-25025 April 2024 Sec106 Tribal, Reider, Anthony-Flandreau Santee Sioux Tribe ML24115A3032024-04-25025 April 2024 Sec106 Tribal, Taylor, Louis-Lac Courte Oreilles Band of Lake Superior Chippewa Indians ML24115A3012024-04-25025 April 2024 Sec106 Tribal, Seki, Darrell-Red Lake Nation ML24115A2882024-04-25025 April 2024 Sec106 Tribal, Fairbanks, Michael-White Earth Nation.Docx ML24115A2992024-04-25025 April 2024 Sec106 Tribal, Renville, J. Garret-Sisseton Wahpeton Oyate of the Lake Travers Reservation 2024-09-26
[Table view] |
Text
ber 1, 2020
SUBJECT:
UPDATED INSPECTION PLAN FOR MONTICELLO NUCLEAR GENERATING PLANT (REPORT 05000263/2020005)
Dear Mr. Conboy:
The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for the Monticello Nuclear Generating Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP),
including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020 memo, Inspection Guidance During Transition From COVID-19 Mandatory Telework (ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:
https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these baseline inspections are being developed by the NRC staff. Anticipated baseline inspection dates are presented in the attached; however, the staff will confirm the schedule for these inspections with each utility separately.
Additionally, during this period the NRC will perform inspections per Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01). This includes sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (ML19163A176), which included an option for relying on annunciation and operator manual actions instead of automatic protective features to isolate a power supply affected by an open phase condition. Licensees will be individually notified when the NRC schedules these inspections.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Hironori Peterson at 630-829-9707 with any questions you have regarding this letter.
Sincerely,
/RA/
Hironori Peterson, Chief Branch 3 Division of Reactor Projects Docket Nos. 05000263 License Nos. DPR-22 Enclosure(s):
Inspection Plan Letter to Thomas Conboy from Hironori Peterson dated September 1, 2020.
SUBJECT: UPDATED INSPECTION PLAN FOR MONTICELLO NUCLEAR GENERATING PLANT (REPORT 05000263/2020005)
DISTRIBUTION:
Jessie Quichocho Elise Burket RidsNrrDorlLpl3 RidsNrrPMMonticello RidsNrrDroIrib Resource John Giessner Kenneth OBrien Jamnes Cameron Allan Barker DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML20244A268 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII RIII NAME NShah:wc via email HPeterson: via email DATE 8/24/2020 8/26/2020 OFFICIAL RECORD COPY
IP 22 Inspection Activity Plan Report Monticello 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count Design Bases Assurance Inspection (Programs) 3 1 08/17/2020 08/21/2020 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 1 08/31/2020 09/04/2020 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements Monticello October 2020 Initial Exam 3 1 09/13/2020 09/19/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 10/18/2020 10/24/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
1 10/25/2020 10/28/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Security Baseline Inspection 1 1 09/28/2020 10/02/2020 IP 71130.02 000734 Access Control 1 09/28/2020 10/02/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 09/28/2020 10/02/2020 IP 71130.08 000740 Fitness For Duty Program 1 09/28/2020 12/31/2020 IP 71130.09 001656 Security Plan Changes 1 09/28/2020 10/02/2020 IP 71130.14 000743 Review of Power Reactor Target Sets Radiation Protection Baseline Inspection 1 1 11/02/2020 11/06/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1 11/02/2020 11/06/2020 IP 71124.04 000728 Occupational Dose Assessment Biennial Problem Identification and Resolution Inspection 4 1 11/16/2020 12/04/2020 IP 71152B 000747 Problem Identification and Resolution Security Baseline Inspection 2 1 02/22/2021 02/26/2021 IP 71130.01 000733 Access Authorization 1 02/22/2021 02/26/2021 IP 71130.02 000734 Access Control 1 02/22/2021 02/26/2021 IP 71151 001338 Performance Indicator Verification 1 03/15/2021 03/19/2021 IP 71130.02 000734 Access Control 1 04/12/2021 04/16/2021 IP 71130.07 000739 Security Training This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.
8/31/2020 1:29:31 PM
IP 22 Inspection Activity Plan Report Monticello 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count Radiation Protection Baseline Inspection 1 1 03/08/2021 03/12/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation Inservice Inspection Monticello 1 1 04/12/2021 05/08/2021 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
ISFSI Program Review Inspection 2Q2021 1 1 04/19/2021 04/23/2021 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants Radiation Protection Baseline Inspection 1 1 04/26/2021 04/30/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 04/26/2021 04/30/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls OPC Temporary Instruction 2515/194 1 1 06/21/2021 06/25/2021 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
Radiation Protection Baseline Inspection 2 1 06/28/2021 07/02/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment Emergency Preparedness Exercise Inspection / Performance Indicator Verification 4 1 08/09/2021 08/13/2021 IP 71114.01 000716 Exercise Evaluation 1 08/09/2021 08/13/2021 IP 71151 001397 Performance Indicator Verification Design Bases Assurance Inspection (Team) 8 1 08/16/2021 09/03/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.
8/31/2020 1:29:31 PM
IP 22 Inspection Activity Plan Report Monticello 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count Monticello 2021 Biennial Licensed Operator Requal Program Inspection 2 1 09/19/2021 09/25/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Security Baseline Inspection 1 1 10/01/2021 12/31/2021 IP 71130.09 001656 Security Plan Changes Force-On-Force Planning and Exercise Weeks - MON 6 1 10/04/2021 10/08/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1 10/25/2021 10/29/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Radiation Protection Baseline Inspection 1 1 11/01/2021 11/05/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls Cyber Security Inspection 2 1 11/01/2021 11/19/2021 IP 71130.10P 000741 Cyber Security Security Baseline Inspection 1 1 03/07/2022 03/11/2022 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 03/07/2022 03/11/2022 IP 71151 001338 Performance Indicator Verification 1 04/18/2022 04/22/2022 IP 71130.02 000734 Access Control 1 04/18/2022 04/22/2022 IP 71130.05 000737 Protective Strategy Evaluation Biennial Problem Identification and Resolution Inspection 4 1 03/28/2022 04/15/2022 IP 71152B 000747 Problem Identification and Resolution RP Baseline Inspection 1 1 04/18/2022 04/22/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.
8/31/2020 1:29:31 PM
IP 22 Inspection Activity Plan Report Monticello 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count RP Baseline Inspection 1 1 04/18/2022 04/22/2022 IP 71124.04 000728 Occupational Dose Assessment Emergency Preparedness Baseline Inspection / Performance Indicator Verification 1 1 06/13/2022 06/17/2022 IP 71114.02 000717 Alert and Notification System Testing 1 06/13/2022 06/17/2022 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 06/13/2022 06/17/2022 IP 71114.05 000720 Maintenance of Emergency Preparedness 1 06/13/2022 06/17/2022 IP 71151 001397 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.
8/31/2020 1:29:31 PM