IR 05000298/2019013

From kanterella
Revision as of 00:27, 2 January 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Temporary Instruction 2515/194 (Inspection Report 05000298/2019013)
ML19352E279
Person / Time
Site: Cooper Entergy icon.png
Issue date: 12/18/2019
From: Nick Taylor
Division of Reactor Safety IV
To: Dent J
Nebraska Public Power District (NPPD)
Taylor N
References
IR 2013013
Download: ML19352E279 (9)


Text

ber 18, 2019

SUBJECT:

COOPER NUCLEAR STATION - TEMPORARY INSTRUCTION 2515/194 (INSPECTION REPORT 05000298/2019013)

Dear Mr. Dent:

On November 7, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Cooper Nuclear Station and discussed the results of this inspection with Mr. K.

Dia, Director of Engineering, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Nicholas H. Taylor, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 05000298 License No. DPR-46

Enclosure:

As stated

Inspection Report

Docket Number: 05000298 License Number: DPR-46 Report Number: 05000298/2019013 Enterprise Identifier: I-2019-013-0020 Licensee: Nebraska Public Power District Facility: Cooper Nuclear Station Location: Brownville, Nebraska Inspection Dates: November 4, 2019, to November 7, 2019 Inspectors: S. Makor, Reactor Inspector Approved By: Nicholas H. Taylor, Chief Engineering Branch 2 Division of Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a temporary instruction 2515/194 at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations No findings or violations of more than minor significance were identified.

Additional Tracking Items None.

INSPECTION SCOPE

Inspections were conducted using the appropriate portions of the Temporary Instruction (TI) in effect at the beginning of the inspection unless otherwise noted. Samples were declared complete when the TI requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL Temporary Instruction 2515/194 - Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01)

This inspection was conducted using Temporary Instruction 2515/194 (ADAMS Accession No. ML17137A416) effective November 1, 2017, to verify that licensees have appropriately implemented the Nuclear Energy Institute Voluntary Industry Initiative (ADAMS Accession No. ML15075A454) dated March 16, 2015, including updating their licensing basis to reflect the need to protect against open phase conditions. The inspector reviewed the licensees implementation of Nuclear Energy Institute Voluntary Industry Initiative in compliance with Commission guidance. The inspector reviewed and discussed the licensees open phase condition system design, installation, testing and maintenance plans with plant staff, and performed system walkdowns to verify that the installed equipment was supported by the design documentation.

Temporary Instruction 2515/194-03.01 - Voluntary Industry Initiative (Part 1)

Nebraska Public Power District, LLC. selected the open phase detection system designed and manufactured by Power System Sentinel Technologies, LLC (PSSTech)as the design vendor for Cooper Nuclear Station.

During normal plant operation the Engineered Safety Feature (ESF) buses, 4160 Volt Bus 1F (Division 1) and 4160 Volt Bus 1G (Division 2), are normally powered from the Normal Station Service Transformer (NSST) via 4160 Volt Bus 1A for ESF Bus 1F and 4160 Volt Bus 1B for ESF Bus 1G. The NSST is powered from the main generator. The NSST supplies power to ESF buses during normal at power operation. During startup and shutdown or whenever the NSST becomes unavailable, the Startup Station Service Transformer (SSST) provides power to the ESF buses. Additionally, the Emergency Station Service Transformer (ESST) provides a second source of offsite power to the ESF buses in the event that both the NSST and SSST are unavailable. The SSST and ESST are the credited offsite power sources.

Cooper Nuclear Station prepared the design modification and associated documentation for this transition in Engineering Change 6038060, Installation of PSSTech OPP System on SSST and ESST, Revision 00. At the end of the inspection, the licensee had installed all four detectors on the SSST and the ESST. The licensee installed and tested redundant open phase detection systems on the SSST and ESST to support enabling the trip function and is in the monitoring mode of operations (tripping function disabled). Currently, all function switches are in the Alarm Only position with plans to have an approved risk evaluation in place before the end of the year. If the licensee fails to show that the risk reduction of an automatic trip versus a manual trip is small, then they will transition to full operation (tripping functions enabled) in December

INSPECTION RESULTS

Observation: Temporary Instruction 2515/194-03.01 - Voluntary Industry 2515/194 Initiative (Part 1)

Based on discussions with the licensee staff; review of design, installation and testing documentation; tour of the control room and discussions with operators; and walkdowns of the installed equipment, the inspector had reasonable assurance that the licensee has appropriately implemented the voluntary industry initiative.

Detection, Alarms, and General Criteria

(1) Open phase conditions will be detected and alarmed in the control rooms.
(2) Detection circuits are sensitive enough to identify an open phase condition for all credited loading conditions.
(3) The licensee demonstrated that the actuation circuit design did not result in lower overall plant operation reliability. The PSSTech system is designed to minimize misoperation or spurious actuation in the range of voltage unbalance normally expected in the transmission system that could cause separation from an operable offsite power source. The Open Phase Protection (OPP) System will automatically detect and alarm an open phase condition and/or trouble alarm in the control room.
(4) No Class-1E circuits were replaced with non-Class 1E circuits in the design.
(5) The licensee proposed an Updated Safety Analysis Report change to Chapter VIII, Section 2.2.5 and Chapter VIII, Section 3.5 to describe the OPP system and address the design features and analyses related to the effects of, and protection for, any open phase condition vulnerabilities.

Protective Actions Criteria

(1) Startup Station Service Transformer (SSST) and Emergency Station Service Transformer (ESST) were identified as susceptible to an open phase condition and the licensee implemented design changes to mitigate the effects.
(2) With an open phase condition present and no accident condition signal present, the PSSTech system would not adversely affect the function of important-to-safety systems, structures, or components. The licensees open phase condition design solution added a set of additional tripping inputs in parallel with existing transformer isolation controls. This addition added a new tripping condition (open phase) to the previously analyzed electrical faults which result in isolation of the transformers. The credited plant response was unaffected and would be the same independent of the conditions that generated the isolation of the transformer.
(3) The PSSTech OPP affects the 161 kV SSST and 69 kV ESST offsite power circuits by tripping the circuit breakers between the transformer and the plant buses if they are not supplied with 3-phase power as designed by the manufacturer for steady state operation.

With an open phase condition present and accident condition signal present, the PSSTech system would not adversely affect the transfer of 4160 Volt engineered safeguards buses to the onsite emergency diesel generators as required by the current licensing bases; only tripping condition (open phase) was added to the electrical faults which result in isolation of the alternate offsite source of power.

(4) During normal plant operation the Engineered Safety Feature (ESF) buses, 4160 Volt Bus 1F (Division 1) and 4160 Volt Bus 1G (Division 2), are normally powered from the Normal Station Service Transformer (NSST) via 4160 Volt Bus 1A for ESF Bus 1F and 4160 Volt Bus 1B for ESF Bus 1G. The NSST is powered from the main generator. The NSST supplies power to ESF buses during normal at power operation. During startup and shutdown or whenever the NSST becomes unavailable, the SSST provides power to the ESF buses. Additionally, the ESST provides a second source of offsite power to the ESF buses in the event that both the NSST and SSST are unavailable. The SSST and ESST are the credited offsite power sources. Additionally, the existing electrical protective devices are sufficiently sensitive to detect design basis conditions like a loss of voltage or a degraded voltage, but were not designed to detect a single phase open circuit condition. The 4160 Volt system is a high impedance grounded system and is therefore a grounded detection scheme. The ground detection will alarm for a 1.5 amp ground on the secondary windings of the NSST, SSST, or ESST to alert the operator of a ground condition.
(5) The inspector held discussions with the licensee staff and identified that the vendor guidance, including periodic tests, setpoint verification, and equipment maintenance and inspections had been integrated into plant procedures and processes. The licensee performed a pre-inspection self-assessment, 2019-0099, "TI 2515/194 Pre-Inspection Focused Self-Assessment," July 2, 2019, which documented, in part, whether the licensee appropriately implemented the Nuclear Energy Institute Voluntary Industry Initiative on open phase conditions. The licensee at the time of the inspection considered the maintenance rule program and integrated previous operating experience into their program. The licensee was in the process of developing additional procedures and processes to inspect and maintain the PSSTech equipment in addition to that recommended by the vendor, and to meet North American Reliability Council standards. At the end of the inspection, the licensee was completing a risk evaluation to determine whether they would transition from monitoring to fully activated. The expected determination is prior to December 31,

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On November 7, 2019, the inspectors presented the Temporary Instruction 2515/194 results to Mr. K. Dia, Director of Engineering, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

2515/194 Calculations NEDC 16-023 Review of Zachary Nuclear Calculation 16-101 0

2515/194 Corrective Action 2019-05776 Open Phase SAT Test Not in Records 11/6/2019

Documents

Resulting from

Inspection

2515/194 Corrective Action 2019-05800 Open Phase Neutral Conductor Question 11/7/2019

Documents

Resulting from

Inspection

2515/194 Drawings 3012 Main Three Line Diagram Sheet #4 AG/18

2515/194 Drawings 3700 SH 13 Annunciator Elementary Ladder Diagram AE/10

2515/194 Drawings 3701 SH 17 Annunciator Legends Panel C Annunciator AC/09

2515/194 Drawings 3771 SH 3 Annunciator Loop Diagram ANN-MUX-21 AC/05

2515/194 Drawings 4038 Civil Transformer Area Foundations AE/11

2515/194 Drawings CNS-EE-319 SSST OPP Cabinets #1 and #2 Connection Diagram AB/01

2515/194 Drawings CNS-EE-320 ESST OPP Cabinets #1 and #2 Connection Diagram AB/01

2515/194 Drawings NC02161 One-line Switching Diagram 345KV/161KV/4160V AJ34

2515/194 Drawings NC43456 Cooper 161KV Substation One-line Switching Diagram AI13

2515/194 Drawings NC66688 Cooper 345KV Substation One-Line Switching Diagram AM

2515/194 Drawings OPP-ELE-B101 Open Phase Detection and Protection System AB/01

2515/194 Miscellaneous 15-L22-139 Contract No. 15-010A 8/6/2015

2515/194 Miscellaneous EC 6038060 Open Phase Protection (OPP) System Operating and 00

Maintenance Manual

2515/194 Miscellaneous NLS2012081 90-Day Response to NRC Bulletin 2012-01, Design 10/24/2012

Vulnerability in Electric Power System Cooper Nuclear

2515/194 Miscellaneous NLS2014014 Response to Request for Additional Information Regarding 2/3/2014

Bulletin 2012-01 Cooper Nuclear Station, Docket No. 50-298,

DPR-46

2515/194 Procedures 15.EE.701 Open Phase Protection Active System Functional Test 3

Inspection Type Designation Description or Title Revision or

Procedure Date

2515/194 Procedures 2.1.11.3 Radwaste and Augmented Radwaste Building Data 111

2515/194 Work Orders 5065106 CED 6038060 Byron Open Phase Issue 11/7/2016

2515/194 Work Orders 5143406 Rev-3 ESST OPP Installation 5/22/2017

7