IR 05000298/2019001
| ML19130A227 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 05/10/2019 |
| From: | Jason Kozal NRC/RGN-IV/DRP/RPB-C |
| To: | Dent J Nebraska Public Power District (NPPD) |
| References | |
| IR 2019001 | |
| Download: ML19130A227 (26) | |
Text
May 10, 2019
SUBJECT:
COOPER NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT 05000298/2019001
Dear Mr. Dent:
On March 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Cooper Nuclear Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
NRC inspectors documented one finding of very low safety significance (Green) in this report.
This finding involved a violation of NRC requirements.
If you contest the violation or significance of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspector at Cooper Nuclear Station.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC resident inspector at Cooper.
J. Dent, Jr.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Jason W. Kozal, Chief Reactor Projects Branch C
Docket No. 50-298 License No. DPR-46
Enclosure:
Inspection Report 05000298/2019001 w/attachment: Detailed Risk Evaluation
Enclosure U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Numbers:
05000298
License Numbers:
Report Numbers:
Enterprise Identifier: I-2019-001-0003
Licensee:
Nebraska Public Power District
Facility:
Cooper Nuclear Station
Location:
Brownville, NE 68321
Inspection Dates:
January 01, 2019, to March 31, 2019
Inspectors:
M. Stafford, Resident Inspector (BWR)
P. Vossmar, Senior Resident Inspector (BWR/TL)
Approved By:
Jason W. Kozal
Chief, Reactor Projects Branch C
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a quarterly inspection at Cooper Nuclear Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. Violations being considered in the NRCs assessment and additional items are summarized in the tables below.
List of Findings and Violations
Failure to Maintain Configuration Control of a Fire Zone Boundary Barrier Resulting in a Fire Cornerstone Significance Cross-cutting Aspect Report Section Initiating Events Green NCV 05000298/2019001-01 Open/Closed
[H.11] -
Challenge the Unknown 71152 The inspectors reviewed a self-revealed, non-cited violation of License Condition 2.C(4), Fire Protection, for the failure to implement in effect all provisions of the approved fire protection program. Specifically, on September 19, 2018, the licensee failed to implement configuration control requirements for an FP2 fire zone boundary barrier during work activities associated with Maintenance Procedure 7.2.78.2, Pipe Penetration Seal Installation Using Gasket Placement, Revision 1. Contrary to procedure requirements, during work on a pipe penetration between the radwaste and augmented radwaste buildings, maintenance personnel injected a combustible foam sealant (Avanti-248) on piping that exceeded 150 degrees Fahrenheit. On December 29, 2018, the sealant caught fire, resulting in emission of toxic smoke and declaration of a Notification of Unusual Event.
Additional Tracking Items
Type Issue Number Title Inspection Procedure Status LER 05000298/2018-001-00 Inadequate Packing on Motor Operated Valve Results in Unplanned High Pressure Coolant Injection Inoperability and a Loss of Safety Function 71153 -
Follow-up of Events and Notices of Enforcement Discretion Closed LER 05000298/2018-003-00 Safety Valve Failure Results in Loss of Safety Function 71153 -
Follow-up of Events and Notices of Enforcement Discretion Closed
PLANT STATUS
Cooper Nuclear Station began the inspection period at rated thermal power. On February 22, 2019, the licensee reduced power to 70 percent for a control rod sequence exchange. The plant was returned to rated thermal power on February 23, 2019 and remained at or near rated thermal power for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
External Flooding Sample (IP Section 03.04) (1 Sample)
On March 11, 2019, the inspectors evaluated readiness to cope with external flooding for the following areas:
- Intake structure;
- Reactor building basement areas;
- Turbine building basement areas;
- External plant levees.
Impending Severe Weather Sample (IP Section 03.03) (1 Sample)
The inspectors evaluated readiness for impending adverse weather conditions for a winter weather advisory on January 18, 2019.
71111.04 - Equipment Alignment
Partial Walkdown (IP Section 02.01) (3 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Standby liquid control B with standby liquid control A out of service for maintenance on January 14, 2019;
- (2) Emergency diesel generator 2 starting air during emergency diesel generator 1 maintenance on February 5, 2019;
- (3) Reactor equipment cooling subsystem B with reactor equipment cooling A out of service for maintenance on March 11, 2019.
71111.04S - Equipment Alignment
Complete Walkdown (IP Section 02.02) (1 Sample)
The inspectors evaluated system configurations during a complete walkdown of the high pressure coolant injection system on March 8, 2019.
71111.05A - Fire Protection (Annual)
Annual Inspection (IP Section 03.02) (1 Sample)
The inspectors evaluated fire brigade performance on January 18, 2019.
71111.05Q - Fire Protection (Quarterly)
Quarterly Inspection (IP Section 03.01) (5 Samples)
The inspectors evaluated fire protection program implementation in the following selected areas:
- (1) Waste collector drain tank room on January 10, 2019;
- (2) Torus basement area on February 11, 2019;
- (3) Fire pump building on February 12, 2019;
- (4) Intake structure and service water pump room on March 4, 2019;
- (5) Southwest quad 859 feet elevation, Division 2 residual heat removal and high pressure coolant injection room on March 5, 2019.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
The inspectors observed and evaluated licensed operator performance in the control room during the first quarter downpower on February 23, 2019.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
The inspectors observed and evaluated a simulator scenario on March 26, 2019.
71111.12 - Maintenance Effectiveness
Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
- (1) MS-AO-738 and MS-AO-739 reactor vessel head vent valves on March 29, 2019;
- (2) Primary containment pressure monitoring and relief on March 29, 2019.
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the risk assessments for the following planned and emergent work activities:
- (1) Residual heat removal D and service water booster pump D maintenance windows on January 16, 2019;
- (2) Residual heat removal loop B maintenance window on January 25, 2019;
- (3) Reactor feed pump A discharge valve, RF-MOV-29MV, packing torque adjustment on January 30, 2019;
- (4) Emergency diesel generator 1 maintenance window on February 7, 2019;
- (5) Reactor equipment cooling heat exchanger cleaning and reactor core isolation cooling maintenance windows on March 6, 2019;
- (6) Emergent flooding preparations on March 14, 2019.
71111.15 - Operability Determinations and Functionality Assessments
Sample Selection (IP Section 02.01) (4 Samples)
The inspectors evaluated the following operability determinations and functionality assessments:
- (1) Elevated release point sump discharge check valve functionality on February 1, 2019;
- (2) Emergency diesel generator 1 turbo bearing wear on February 19, 2019;
- (3) High pressure coolant injection minimum flow valve closure signal failed to actuate on March 25, 2019;
- (4) Emergency diesel generator 2 jacket water heat exchanger flange leak on March 25, 2019.
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)
The inspectors evaluated the following temporary or permanent modifications:
- (1) High pressure coolant injection steam isolation valve, HPCI-MO-16, backseating due to packing leakage on February 6, 2019;
- (2) Reactor feed pump A discharge valve, RF-MOV-29MV, sealant injection modification on February 23, 2019.
71111.19 - Post Maintenance Testing
Post Maintenance Test Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the following post maintenance tests:
- (1) Standby liquid control post work test on January 11, 2019;
- (2) Residual heat removal B subsystem testing following system maintenance on January 25, 2019;
- (3) Reactor feed pump A discharge valve, RF-MOV-29MV, backseat and packing adjustment post work testing on January 28, 2019;
- (4) Reactor equipment cooling pump A testing following pump replacement on January 31, 2019;
- (5) Diesel fire pump D testing following hose, belt, and oil change on March 27, 2019.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Inservice Testing (IST) (IP Section 03.01)
- (1) High pressure coolant injection pump and valve quarterly inservice test on January 18, 2019;
- (2) Emergency diesel generator fuel oil transfer pump inservice test on March 6, 2019.
Surveillance Testing (IP Section 03.01) (3 Samples)
- (1) Standby liquid control chemistry sample on January 9, 2019;
- (2) Northwest quad fan coil unit flow test on February 11, 2019; (3)4160 V critical switchgear undervoltage relay testing on March 1, 2019.
71114.06 - Drill Evaluation
Emergency Preparedness (EP) Drill (IP Section 02.01) (1 Sample)
Emergency preparedness drill on February 26,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===
January 1, 2018 - December 31, 2018
IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)
January 1, 2018 - December 31, 2018
71152 - Problem Identification and Resolution
Annual Follow-up of Selected Issues (IP Section 02.03) (3 Samples)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Operator challenge assessment on February 7, 2019;
- (2) Declaration of a Notification of Unusual Event due to fire resulting in toxic gas on March 28, 2019;
- (3) Unplanned shutdown due to high pressure coolant injection packing leakage on March 29, 2019.
Semiannual Trend Review (IP Section 02.02) (1 Sample)
The inspectors reviewed the licensees corrective action program for potential adverse trends in emergency preparedness and training performance that might be indicative of a more significant safety issue.
71153 - Follow-up of Events and Notices of Enforcement Discretion Event Follow-up (IP Section 03.01)
- (1) The inspectors evaluated when elevated release point sumps were nonfunctional which challenged standby gas treatment operability, and the licensees response, on January 30, 2019;
- (2) The inspectors evaluated the March 2019 Missouri river flooding and the licensees response on March 25, 2019.
Event Report (IP Section 03.02) (2 Samples)
The inspectors evaluated the following licensee event reports (LERs) which can be accessed at https://lersearch.inl.gov/LERSearchCriteria.aspx:
(1)
- LER 05000298/2018-001-00, Inadequate Packing on Motor Operated Valve Results in Unplanned High Pressure Coolant Injection Inoperability and a Loss of Safety Function, (ADAMS Accession: ML18136A539):
The inspectors concluded that no violation of NRC requirements occurred.
(2)
- LER 05000298/2018-003-00, Safety Valve Failure Results in Loss of Safety Function, (ADAMS Accession: ML18353A279):
Based on information at the time of inspection, the inspectors did not identify a violation of NRC requirements. The inspectors are awaiting Revision 1 to the LER, which will include the licensee's causal determination.
INSPECTION RESULTS
Failure to Maintain Configuration Control of a Fire Zone Boundary Barrier Resulting in a Fire Cornerstone Significance Cross-cutting Aspect Report Section Initiating Events
Green NCV 05000298/2019001-01 Closed
[H.11] -
Challenge the Unknown 71152 The inspectors reviewed a self-revealed, non-cited violation of License Condition 2.C(4), Fire Protection, for the failure to implement in effect all provisions of the approved fire protection program. Specifically, on September 19, 2018, the licensee failed to implement configuration control requirements for an FP2 fire zone boundary barrier during work activities associated with Maintenance Procedure 7.2.78.2, Pipe Penetration Seal Installation Using Gasket Placement, Revision 1. Contrary to procedure requirements, during work on a pipe penetration between the radwaste and augmented radwaste buildings, maintenance personnel injected a combustible foam sealant (Avanti-248) on piping that exceeded 150 degrees Fahrenheit. On December 29, 2018, the sealant caught fire, resulting in emission of toxic smoke and declaration of a Notification of Unusual Event.
Description:
On December 29, 2018, Cooper experienced a fire in the augmented offgas (AOG) system pipe penetration F between the radwaste (RW) and augmented radwaste (ARW) buildings. The fire created hazardous smoke, preventing normal access to the RW and ARW buildings. As a result, the licensee declared a Notification of Unusual Event. The fire was caused by the licensees inappropriate injection of Avanti AV-248, a combustible foam sealant, into the penetration to address groundwater in-leakage.
Specifically, on September 19, 2018, maintenance personnel removed some of the insulation on piping running through penetration F and injected AV-248 sealant in response to groundwater in-leakage. The penetration contained AOG piping that normally operates at 500 degrees Fahrenheit (F). The licensee had a history of in-leakage at this location and had previously injected various types of Avanti sealant in 2004, 2011, and July 2018. During the July 2018 injection, noncombustible AV-315 was used because AV-248 was not allowed to be used in this location. On September 19, 2018, after AV-315 failed to adequately prevent the in-leakage, maintenance personnel injected AV-248 into the penetration. At the time the work activity occurred, the maintenance personnel questioned the use of AV-248 due to procedure limitations. Specifically, Maintenance Procedure 7.2.78.2, Pipe Penetration Seal Installation Using Gasket Placement, Revision 1, which was controlling the work, stated in Step 2.1, Avanti AV-248 Flexseal can be installed on piping systems with a maximum operating temperature up to 150 degrees F and, due to head pressure limitations, is not to be used on a penetration with the lowest point less than 886 feet elevation. Penetration F contained piping with 500 degrees F normal operating temperatures and was located in a basement elevation below 886 feet. Despite procedure compliance concerns, work continued due to an assumption that AV-248 was only combustible in its liquid form, and curing would occur prior to placing the 500 degrees F piping back in service.
On December 27, 2018, the licensee noticed a smoky haze around Penetration F. After engaging the vendor and discovering that the sealant material in the penetration was combustible, operations personnel acted to secure steam to AOG so that the combustible sealant could be removed. The licensee waited approximately 35 hours4.050926e-4 days <br />0.00972 hours <br />5.787037e-5 weeks <br />1.33175e-5 months <br /> before opening access covers on either side of the penetration tunnel. Sealant removal was performed with two teams, one on either side of the penetration. When the first team opened the access cover on the RW side and began removing sealant, they discovered unexpected smoke and notified supervision. Plant supervision determined that the first team should wait for the smoke to dissipate before resuming work. However, rather than stop the activity due to the uncertain conditions that were discovered, the licensee allowed the second team to continue work on the ARW side of the penetration. When the second team removed enough sealant from the second access point, they introduced fresh air into the space, which caused the AV-248 sealant that was already smoldering to ignite and release toxic fumes (carbon dioxide, carbon monoxide, nitrogen oxides).
Following the event, the inspectors reviewed the licensees apparent cause evaluation and applicable fire protection program requirements. The penetration in question was part of an FP2 fire zone boundary barrier. While not a fire-rated barrier credited in NFPA-805 nuclear safety capability analysis or controlled by the technical requirements manual, the barrier was credited in the licensees fire probabilistic risk analysis. As a result, according to Fire Protection Program Procedure 0.23, CNS Fire Protection Plan, Revision 79, FP2 barriers are qualified fire boundaries that must meet the requirements of the fire protection program.
Because the fire protection program requires control of installed combustible materials via configuration control through approved plant procedures, the inspectors determined that this issue represented a violation of the licensees fire protection program.
Corrective Action(s): Corrective actions included extinguishing the fire, removing all combustible sealant from the penetration, and long term actions to seal the penetration with a mechanical seal.
Corrective Action Reference(s): CR-CNS-2018-08638
Performance Assessment:
Performance Deficiency: The licensees failure to implement fire protection program configuration control requirements for an FP2 barrier was a performance deficiency.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the protection against external factors (including fire) attribute of the Initiating Events Cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the performance deficiency resulted in a fire that prevented normal access to the radwaste and augmented radwaste building basements, prevented operation of the augmented offgas system, and resulted in a plant emergency declaration.
Significance: The inspectors assessed the significance of the finding using Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, dated June 19, 2012. The inspectors determined that the finding required a detailed risk evaluation (DRE) because it impacted the frequency of a fire or internal flooding initiating event. The DRE combined initiating event probabilities with the total conditional core damage and conditional large early release probabilities and estimated that the fire resulted in an increase in core damage frequency of 7.0E-7/year, and an increase in large early release frequency of 3.1E-8/year. As a result, the performance deficiency had very low safety significance (Green). The DRE is included as Attachment 1 to this report.
Cross-cutting Aspect: H.11 - Challenge the Unknown: Individuals stop when faced with uncertain conditions. Risks are evaluated and managed before proceeding. Specifically, workers were uncertain about the use of AV-248 prior to sealant injection, and again when smoke was unexpectedly found during subsequent sealant removal from the penetration; however, in each case the work activity was not stopped, and risks were not evaluated or addressed prior to proceeding.
Enforcement:
Violation: License Condition 2.C(4) requires, in part, that, NPPD shall implement and maintain in effect all provisions of the approved fire protection program. Fire Protection Program Procedure 0.23, CNS Fire Protection Plan, Revision 79, defines FP2 barriers as qualified fire boundaries that meet the requirements of the Fire Protection Program, and further states, in Section 5, Fire Prevention, that nontransient combustible materials are controlled by the configuration control process. Procedure 0.31, Equipment Status Control, Revision 89, states, all deviations from normal configuration shall be controlled by approved documents. Maintenance on the FP2 barrier penetration between the radwaste and augmented radwaste building basements was controlled by Maintenance Procedure 7.2.78.2, Pipe Penetration Seal Installation Using Gasket Placement, Revision 1. Step 2.1 states, in part, Avanti AV-248 Flexseal can be installed on piping systems with a maximum operating temperature up to 150 degrees F.
Contrary to the above, on September 19, 2018, the licensee failed to ensure that Avanti AV-248 Flexseal was installed on piping systems with a maximum operating temperature of up to 150 degrees F. Specifically, maintenance personnel injected AV-248, a combustible foam sealant, into an FP2 barrier penetration between the radwaste and augmented radwaste building basements on piping with an operating temperature of 500 degrees F. As a result, on December 29, 2018, the sealant caught fire, resulting in emission of toxic smoke and declaration of a Notification of Unusual Event.
Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On April 18, 2019, the inspectors presented the quarterly integrated resident inspection results to Mr. K. Dia, Acting Site Vice President and Chief Nuclear Officer, and other members of the licensee staff.
THIRD PARTY REVIEWS Inspectors reviewed the most recently issued Institute of Nuclear Power Operations report during the inspection period.
DOCUMENTS REVIEWED
71111.01 - Adverse Weather Protection
Condition Reports (CR-CNS-)
2019-00304
Procedures
Number
Title
Revision
5.1FLOOD
Flood
25, 26, 27
5.1WEATHER
Operation During Weather Watches and Warnings
7.0.11
Flood Control Barriers
Drawings
Number
Title
Revision
4003
Overall Site & Vicinity Plan
4005, Sheet 5
Paving, Grading & Drainage
Cooper Nuclear Station - 345/161 kV Substation
71111.04 - Equipment Alignment
Condition Reports (CR-CNS-)
2016-03874
2016-06346
2017-06179
2018-01346
2019-01343
2019-01346
2019-01368
Work Orders
238426
240696
242443
Procedures
Number
Title
Revision
2.2.33A
High Pressure Coolant Injection System Component
Checklist
2.2.33B
High Pressure Coolant Injection System Instrument
Valve Checklist
2.2.74A
Standby Liquid Control System Component Checklist
2.2.74B
Standby Liquid Control System Instrument Valve
Checklist
2.2A.DG.DIV2
Standby AC Power System (Diesel Generator)
Component Checklist
2.2A.REC.DIV2
Reactor Equipment Cooling Water System Component
Checklist
2.2B.REC.DIV2
Reactor Equipment Cooling Water System Instrument
Valve Checklist
Drawings
Number
Title
Revision
2031, Sheet 2
Flow Diagram - Reactor Building - Closed Cooling
Water System
N65
2031, Sheet 3
Flow Diagram - Reactor Building - Closed Cooling
Water System
AB/34
2044
High Pressure Coolant Injection and Reactor Feed
System
2045
Flow Diagram - Standby Liquid Control System
N21
Miscellaneous
Documents
Number
Title
Revision/Date
High Pressure Coolant Injection System Health Report
2/2018
EC 18-055
Backseating Evaluation of HPCI-MOV-MO16
VM-0248
Crane Valve Composite Manual
VM-1282
Ohio Brass Valves
VM-1692
CT224 12 Channel Temperature Monitor, SLC-C-100
Controller
71111.05 - Fire Protection
Procedures
Number
Title
Revision
0.23
CNS Fire Protection Plan
0-BARRIER-
MAPS
Barrier Maps
5.1INCIDENT
Site Emergency Incident
5.4POST-FIRE-
Turbine
Turbine Building/Outside Areas Post-Fire Operational
Information
6.FP.305
Halon 1301 Service Water Pump Room Fire
Suppression Surveillance Checks
6.FP.606
Fire Barrier/Penetration Seal Visual Examination
Miscellaneous
Documents
Number
Title
Revision/Date
Fire Brigade Scenario #38
01/15/2019
CED 6029281
Bypass SW Halon Tanks Pressure Switches
CNS-FP-392
Reactor Building Suppression Pool, Elevation 859-9
AA/00
CNS-FP-214
Reactor Building Southwest Quadrant, Elevation 859-9
and 881-9
CNS-FP-39
Reactor Building Suppression Pool, Elevation 881-9
AA/00
CNS-FP-251
Turbine Building - Turbine Operating Floor
AC/11
Miscellaneous
Documents
Number
Title
Revision/Date
CNS-FP-252
Turbine Building - Non-Critical Switchgear Room
AB/04
CNS-FP-256
Intake Structure, Elevation 903 -6
CNS-FP-257
Radwaste Building Basement Floor, Elevation 877-6
CNS-FP-262
Augmented Radwaste Building Basement Floor,
Elevation 877-6
CNS-FP-265
Fire Protection Pump Rooms, Elevation 903-6
71111.11 - Licensed Operator Requalification Program
Condition Reports (CR-CNS-)
2019-01048
2019-01049
2019-01890
Procedures
Number
Title
Revision
0-EN-TQ-210
Conduct of Simulator Training
9C3
2.1.10
Station Power Changes
116
2.2.28.1
Feedwater System Operation
2.3_A-2
Panel A - Annunciator A-2
15.RF.101
RFPT Stop Valve Test
15.RF.102
RFPT Backup Oil Pumps and Filter/Cooler Differential
Pressure Alarm Tests
15.RF.103
RFPT Thrust Bearing Wear and Failure Alarm Test
Miscellaneous Documents
Title
Licensed Operator Requalification Scenario for 3/26/19
71111.12 - Maintenance Effectiveness
Condition Reports (CR-CNS-)
2016-07742
2018-07736
2018-07780
2018-08411
2019-00668
Work Orders
274155
274250
Miscellaneous
Documents
Number
Title
Revision
Maintenance Rule Function PC-COMP1
Maintenance Rule Function PC-F03
Maintenance Rule Function PC-PF02
Miscellaneous
Documents
Number
Title
Revision
Maintenance Rule Function MS-F04 Performance Criteria
Basis
274251
DEC-5274251
MS-AOV-739AV Indicating Lights
Notifications
11579749
11584473
11586252
11589374
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Condition Reports (CR-CNS-)
2018-00440
2018-00674
2019-00241
2019-00305
2019-00333
2019-00425
Work Orders
284609
284612
Procedures
Number
Title
Revision
0-BARRIER
Barrier Control Process
0-CNS-WM-104A
On-Line Fire Risk Management Actions
0-PROTECT-EQP Protected Equipment Program
Miscellaneous
Documents
Number
Title
Revision/Date
Missouri River Flood Protection Plan
Protected Equipment Program Tracking Form - DG 1
LCO Maintenance Week 1906
2/04/2019
Protected Equipment Program Tracking Form -
EE-CHG-125VDC 1B Maintenance Window
01/13/2019
Protected Equipment Program Tracking Form - RCIC
Window Week 1910
03/04/2019
Protected Equipment Program Tracking Form - RHR
Div 2 Window
01/23/2019
Protected Equipment Program Tracking Form - RHR
Pump D Maintenance
01/15/2019
Protected Equipment Program Tracking Form -
SWBP D Maintenance Window
01/15/2019
Protected Equipment Program Tracking Form - Week
03/03/2019
OI 11
Operations Instruction - Aggregate Risk Assessment
71111.15 - Operability Determinations and Functionality Assessments
Condition Reports (CR-CNS-)
2005-03329
2019-00439
2019-00443
2019-00534
2019-00549
2019-00553
2019-00569
2019-00702
2019-00757
2019-01659
2019-01680
2019-01945
Work Orders
5174247
5183073
Procedures
Number
Title
Revision
2.3_DG1
Panel DG-1 - Annunciator DG-1
6.HPCI.312
HPCI Pump Low Discharge Flow Channel Calibration
6.HPCI.712
HPCI Pump Low Discharge Flow Channel Functional
Test
Drawings
Number
Title
Revision
2044
Flow Diagram High Pressure Coolant Injection and
Reactor Feedwater Systems
2005, Sheet 2
Flow Diagram - Misc. Drains, Vents and Seal Systems
N49
2192
Composite Yard Piping Arrangement Plan
AB06
2193
Composite Yard Piping Arrangement Sections
N05
450212268
Detector Wear
N03
454223426
Composite Control Air Schematic
AB/09
Miscellaneous
Documents
Number
Title
Revision
Floating Head Heat Exchanger Training Documents
NEDC 97-023
HPCI Minimum Flow Line Evaluation
1, 2, 3
Notifications
11583394
11586078
11594524
71111.18 - Plant Modifications
Condition Reports (CR-CNS-)
2018-08548
2018-08579
2019-00149
2019-00305
19-00339
2019-00498
Work Orders
5175367
279727
284046
284609
Procedures
Number
Title
Revision
2.2.28A
Feedwater System Component Checklist
6.HPCI.201
HPCI Valve Operability Test (IST)
Drawings
Number
Title
Revision
2015081
Anchor Gate Valve
N01
Miscellaneous Documents
Title
Revision/Date
CEM Slides for WO 5284609 to Address Temporary Leak Repair of Reactor
Feed A Discharge Valve
Risk Management Plan for Downpower and Reactor Feed Pump A
Discharge Valve Maintenance
2/22/2019
Valve Pack AX MSDS
Valve Packing Datasheet: CNS-0-RF-MOV-29MV
Engineering
Reports
Number
Title
Revision
EC 18-055
Backseating Evaluation of HPCI-MOV-MO16
RF-MOV-29MV Packing Injection
0-2
71111.19 - Post Maintenance Testing
Condition Reports (CR-CNS-)
2019-00092
2019-00117
2019-00157
2019-00305
2019-00398
2019-00579
2019-00582
2019-01955
2019-01956
Work Orders
5117595
5171525
5175369
5188891
207682
209529
209530
209531
209532
209539
209540
209542
209544
209570
209576
209577
209584
210430
210828
211204
211566
232527
266729
268847
284609
284612
2114961
Procedures
Number
Title
Revision
0.31MOV
Motor Operated Valves
2.2.28
Feedwater System Startup and Shutdown
107
6.FP.101
Fire Pump Operability Test
6.SLC.101
SLC Pump Operability Test
6.1REC.101
REC Surveillance Operation (IST)(DIV 1)
6.2RHR.101
RHR Test Mode Surveillance Operation
Procedures
Number
Title
Revision
6.2RHR.201
RHR Power Operated Valve Operability Test
7.0.5
CNS Post-Maintenance Testing
7.5.8
Limitorque Mechanical/Electrical Examination
Miscellaneous
Documents
Number
Title
Revision
Guidelines for Inservice Testing at Nuclear Power Plants 2
71111.22 - Surveillance Testing
Condition Reports (CR-CNS-)
2016-03034
2019-00277
2019-00298
2019-00747
2019-00756
2019-00758
2019-00759
2019-00761
2019-00844
2019-01241
Work Orders
5112642
207784
Procedures
Number
Title
Revision
6.HPCI.103
6.SLC.601
SLC Tank Sampling
6.1DG.401
Diesel Generator Fuel Oil Transfer Pump IST Flow Test
6.1EE.306
4160 Bus 1F Undervoltage Relay Channel Functional
Test
6.1HV.603
Air Flow Test of Fan Coil Unit FC-R-1J (DIV 1)
7.3.28.1
Lead Removal/Installation and Lug Installation
8.7.1.4
Boron Potentiometric Analysis (High Range)
Miscellaneous
Documents
Number
Title
Revision
9C0
Surveillance Testing Recommendations for HPCI and
RCIC Systems
0, 1
HPCI Turbine Stop Valve Steam Balance Chamber
Pressure Adjustment Implemented
71114.06 - Drill Evaluation
Condition Reports (CR-CNS-)
2019-01118
2019-01467
Procedures
Number
Title
Revision
0-EN-EP-306
Drills and Exercises
9C0
5.7.1
Emergency Classification
5.7.2
Emergency Director EPIP
Miscellaneous Documents
Title
Drill Scenario Package for 2/26/19 EP Drill
71151 - Performance Indicator Verification
Miscellaneous Documents
Title
Date
2018 PI Validation Package
01/14/2019
CNS Operations Narrative Logs - May 2018 and November 2018
71152 - Problem Identification and Resolution
Condition Reports (CR-CNS-)
2017-02937
2018-01346
2018-04112
2018-04585
2018-04586
2018-08579
2018-08584
2018-08609
2018-08614
2018-08615
2018-08621
2018-08638
2018-08657
2019-00026
2019-00161
2019-00184
2019-00214
2019-00248
2019-01383
2019-01977
2019-02073
2019-02093
Work Orders
4368108
4783927
4789594
254033
260786
260787
266327
Procedures
Number
Title
Revision
0.23
CNS Fire Protection Plan
0.31
Equipment Status Control
0.31.1
Configuration Control During Maintenance Activities
0.7.1
Control of Combustibles
0-BARRIER
Barrier Control Process
2.0.12
Operator Challenges
6.FP.606
Fire Barrier/Penetration Seal Visual Examination
7.2.78.2
Pipe Penetration Seal Installation Using Gasket
Placement
Drawings
Number
Title
Revision
28
Structural Augmented Radwaste Building Modifications
to Existing Radwaste Building - SH 1
Miscellaneous
Documents
Number
Title
Revision
Curtis Wright Packing Guide
EE 18-028
Various MOV Packing Load Adjustment Calculation
Revisions
EE 18-030
HPCI-MOV-MO16 Packing Adequacy
EPRI Technical
Report
Valve Packing Maintenance and Program Practices
NEDC 10-004
Fire PRA Plant Boundary Definition and Partitioning
NEDC 10-080
NFPA 805 Chapter 3 Fundamental Fire Protection
Program and Design Elements Review
NEDC 14-043
Fire Safety Analysis for Entire Power Block
Operations
Instruction #25
Operations Routine Duties
Notifications
10656343
11152470
11343404
11361838
11375256
11383555
11425458
11458460
11465713
11470178
11480499
11494730
11513724
11515171
11542935
11547258
11559692
11563581
11564210
11564621
11566741
11567991
11568779
11569204
11570043
11571041
11575092
11575173
11575663
11577547
11577550
71153 - Follow-up of Events and Notices of Enforcement Discretion
Condition Reports (CR-CNS-)
2018-01323
2018-01327
2018-01341
2018-01344
2018-01346
2018-01369
2018-06301
2018-06791
2019-00005
2019-00534
2019-00549
2019-00553
2019-00569
2019-01754
2019-01757
2019-01765
Work Orders
238426
Procedures
Number
Title
Revision
2.2.27
Equipment, Floor, and Chemical Drain System
2.3_S-1
Panel S - Annunciator S-1
5.1FLOOD
Flood
25, 26
6.MS.401
Main Steam Safety Valve (SV) Testing (IST)
Drawings
Number
Title
Revision
2037
Flow Diagram - H&V Standby Gas Treatment & Off Gas 71
Drawings
Number
Title
Revision
Filters
Miscellaneous
Documents
Number
Title
Revision/Date
LBDCR 2007-018
TRM 3.7.1 and Bases River Level Change
06/12/2007
M266
Elevated Release Point Sump Drain Valve Installation
TR-113560
EPRI Topical Report for Dresser 3700 Series Relief
Valves
09/2000
Detailed Risk Evaluation
Cooper Nuclear Station
Penetration Sealant Fire
The analyst assumed that the sealant ignited and due to its location, the sealant could have
burned further and could have potentially caused fires in both the augmented radwaste building
basement and the radwaste building basement. As a result, two fire scenarios, one in each
basement room, were considered.
The analyst developed the initiating event probabilities for the two fire scenarios using the
following equation set forth in Volume 2, External Events, of the Risk Assessment of
Operational Events (RASP) Handbook:
IEfreq = Fif * SF * Pns, where
Ffi = Fire ignition frequency
SF = Severity Factor
Pns = Non-suppression probability
Using the guidance in Chapter 8, Initiating Events Analysis, Volume 1, Internal Events, of the
RASP Handbook, the analyst set Ffi, the fire ignition frequency, equal to 1.0 since an actual fire
event had occurred and all other fire initiating events were set to 0.0.
For development of the severity factor of the fires, the analyst used Appendix D, Severity
Factor vs. Vertical Distance to Target Above Ignition Source, and Appendix E, Severity Factor
vs. Radial Distance from Ignition Source to Target, from Attachment 8, Tables and Plots
Supporting the Phase 2 Risk Quantification, of Appendix F, of Manual Chapter 0609,
Appendix F, Fire Protection Significance Determination Process. After reviewing publicly
published information on the sealant material, the analyst considered the fire was best treated
as a transient fire. Discussions with the resident inspectors who toured the area of the fire
shortly after the fire event revealed that there were no targets or intervening combustibles within
feet of the fire event or sealant. Using Figure D.01, Severity Factor vs. Vertical Target
Distance for Motor, Pump, and Transient Fires, and Figure E.01, Severity Factor vs. Radial
Target Distance for Motor, Pump, and Transient Fires, the analyst estimated a severity factor
of 0.02. This analyst considered this to be a conservative assumption since there were no risk
significant targets in the areas and the combustibles were farther away than the lowest severity
factor of 0.02 in the referenced figures.
The analyst assigned a nonsuppression probability of 1.0 and assumed there were no automatic
suppression systems in the rooms and that the fire brigade would not be effective at
suppressing the fire. The analyst also viewed this as a conservative assumption.
In combining the assumed values, the initiating event probabilities of the fires in the two rooms
was estimated to be 2.0E-2, as calculated by:
IEfreq = Fif * SF * Pns
IEfreq = 1.0 * 0.02 * 1.0
IEfreq = 0.02 or 2.0E-2
The analyst used the licensees fire probabilistic risk assessment results to obtain a conditional
core damage probability to apply. Licensee Calculation NEDC 09-085, Task 7.14, Fire Risk
Quantification, Revision 3, Table D-6, All Fire Scenarios Sorted by Core Damage Frequency -
Post NFPA 805, detailed the following:
Scenario Conditional Core
Damage Probability
Scenario Conditional Large
Early Release Probability
Radwaste Building Basement
2.44E-5
8.69E-7
Augmented Radwaste
Building Basement
1.04E-5
6.65E-7
Combined Total
3.48E-5
1.53E-6
The analyst noted that the conditional core damage probability resulted largely from random
probabilistic failures and not from actual mitigating equipment becoming damaged in postulated
fire scenarios which led to considering the total conditional core damage and large early release
probabilities to be conservative.
When the analyst combined the initiating event probabilities with the total conditional core
damage and conditional large early release probabilities and multiplied the results by an inverse
year, estimates of an increase in core damage frequency of 7.0E-7/year and an increase in
large early release frequency of 3.1E-8/year for the fire event resulted. Use of qualitative
considerations for the conservatism of the assumptions led to analyst concluding that this issue
was of very low safety significance (Green).
SUNSI Review Complete
By: DLP
Yes No
Publicly Available
Non-Publicly Available
Non-Sensitive
Sensitive
Keyword:
OFFICE
SRI:DRP/C
RI:DRP/C
BC:DRS/EB1
ABC:DRS/EB2
BC:DRS/OB
BC:DNMS
NAME
PVossmar
MStafford
VGaddy
GPick
GWerner
GWarnick
SIGNATURE
PJV
MHS
vgg
GAP
GEW
JFK for
DATE
04/29/2019
04/29/2019
4/23/19
4/27/19
04/25/2019
4/25/2019
OFFICE
TL:DRS/IPAT
ABC:DRS/RCB
SPE:DRP/C
BC:DRP/C
NAME
RKellar
NMakris
DProulx
JKozal
SIGNATURE
RLK
NFM
DLP
JWK
DATE
04/29/2019
04/27/2019
4/30/19
5/10//19