IR 05000298/2018001

From kanterella
Jump to navigation Jump to search
NRC Integrated Inspection Report 05000298/2018001
ML18128A094
Person / Time
Site: Cooper Entergy icon.png
Issue date: 05/08/2018
From: Jason Kozal
NRC/RGN-IV/DRP/RPB-C
To: Dent J
Nebraska Public Power District (NPPD)
Kozal J
References
IR 2018001
Download: ML18128A094 (34)


Text

May 8, 2018

SUBJECT:

COOPER NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT 05000298/2018001

Dear Mr. Dent:

On March 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Cooper Nuclear Station. On April 16, 2018, the NRC inspectors discussed the results of this inspection with Mr. J. Kalamaja, General Manager Plant Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealed findings were identified during this inspection.

However, inspectors documented a licensee-identified violation, which was determined to be of very low safety significance, in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. Jr.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Jason Kozal, Chief Project Branch C Division of Reactor Projects

Docket No. 50-298 License No. DPR-46

Enclosure:

Inspection Report 05000298/2018001 w/ Attachments:

1. Documents Reviewed 2. NRC Request for Information 3. O

Inspection Report

Docket Number:

05000298

License Number:

DPR-46

Report Number:

05000298/2018001

Enterprise Identifier: I-2018-001-0003

Licensee:

Nebraska Public Power District

Facility:

Cooper Nuclear Station

Location:

72676 648A Ave

Brownville, NE

Inspection Dates:

January 1, 2018 to March 31, 2018

Inspectors:

P. Voss, Senior Resident Inspector

R. Kumana, Acting Senior Resident Inspector

M. Stafford, Resident Inspector

P. Elkmann, Senior Emergency Preparedness Inspector

S. Money, Health Physicist

J. ODonnell, CHP, Health Physicist

Approved By:

J. Kozal, Branch Chief

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified, non-cited violation is documented in report Section 71152.

No findings were identified.

PLANT STATUS

Cooper Nuclear Station began the inspection period at rated thermal power. On February 16, 2018, the licensee reduced power to 36 percent in order to enter single loop operation to perform maintenance on reactor recirculation motor generator B, repair condenser leaks, perform maintenance on control rod drives, and tune a reactor recirculation system motor generator set. The licensee restored power to 100 percent on February 18, 2018. On March 11, 2018, the licensee performed a normal shutdown to repair a reactor coolant leak inside the drywell. The licensee restarted the reactor on March 16, 2018, and resumed full power operation on March 19, 2018. The licensee maintained full power for the remainder of the reporting period, except for minor reductions in power to support scheduled surveillances and rod pattern adjustments.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather (1 Sample)

The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures.

Impending Severe Weather (1 Sample)

The inspectors evaluated readiness for impending adverse weather conditions for a winter weather advisory on January 10, 2018.

71111.04 - Equipment Alignment

Partial Walkdown (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Division 2 residual heat removal during service water booster pump A replacement on January 12, 2018
(2) Division 2 reactor equipment cooling during Division 1 reactor equipment cooling maintenance window on January 31, 2018
(3) Emergency diesel generator 2 lube oil during emergency diesel generator 1 work window on February 7, 2017
(4) Emergency diesel generator 1 starting air during emergency diesel generator 2 work window on March 22, 2018

71111.05AQ - Fire Protection Annual/Quarterly

Quarterly Inspection (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Reactor building 931 foot elevation, Fire Area RB-M, Zones 3C and 3D on January 31, 2018
(2) Emergency diesel generator 1, Fire Area DG-A, Zone 14A on February 26, 2018
(3) Condensate pump area, turbine building 882 foot elevation, Fire Area TB-A, Zone 11J on March 20, 2018
(4) Emergency diesel generator 2, Fire Area DG-B, Zone 14B on March 26, 2018

71111.06 - Flood Protection Measures

Internal Flooding (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the reactor building 931 foot elevation, reactor equipment cooling heat exchanger area on February 22, 2018.

71111.07 - Heat Sink Performance

Heat Sink (1 Sample)

The inspectors evaluated a residual heat removal heat exchanger thermal performance test on January 17, 2018.

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification (1 Sample)

The inspectors observed and evaluated a licensed operator requalification scenario in the simulator on January 23, 2018.

Operator Performance (1 Sample)

The inspectors observed and evaluated the quarterly downpower, including entry into single loop operations, power reduction to 45 percent, and planned trip of reactor recirculation motor generator set B and the associated pre-job briefs on February 17, 2018.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness (1 Sample)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Emergency diesel generator 2 system a(1) evaluation due to exceeding performance criteria on March 9, 2018

71111.13 - Maintenance Risk Assessments and Emergent Work Control

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Service water booster pump A replacement on January 9, 2018
(2) Service water booster pump D maintenance window on January 17, 2018
(3) Emergent service water valve maintenance due to reactor equipment cooling heat exchanger B leakage on January 29, 2018
(4) Emergency diesel generator 1 work window on February 6, 2018
(5) Reactor recirculation motor generator set maintenance and single loop operation on February 17, 2018
(6) Emergent steam leak repair affecting high pressure coolant injection on March 8, 2018
(7) Emergency diesel generator 2 work window on March 23, 2018

71111.15 - Operability Determinations and Functionality Assessments

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Jet pump 12 differential pressure reading step change on January 22, 2018
(2) Reactor equipment cooling heat exchanger outlet valve SW-MO-651 indications of potential leak path on January 22, 2018
(3) Scram discharge volume shielding evaluation on January 25, 2018
(4) Emergency diesel generator 2 field flash resistor insulation issue and extent of condition for emergency diesel generator 1 on March 23, 2018

71111.18 - Plant Modifications

The inspectors evaluated the following temporary or permanent modifications:

(1) Reactor equipment cooling heat exchanger B, SW-V-126 temporary flange on February 5, 2018

71111.19 - Post Maintenance Testing

The inspectors evaluated the following post maintenance tests:

(1) Service water booster pump A replacement on January 16, 2018
(2) Post maintenance test for emergency diesel generator 1 system maintenance on February 20, 2018
(3) South west residual heat removal quad fan coil unit maintenance on February 23, 2018
(4) Unplanned service water valve maintenance due to reactor equipment cooling heat exchanger B leakage on February 26, 2018
(5) Post maintenance test for emergency diesel generator 2 system maintenance on March 23, 2018

71111.20 - Refueling and Other Outage Activities

The inspectors evaluated forced outage activities due to reactor coolant system leakage from March 12, 2018, to March 16, 2018.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine

(1) Emergency diesel generator 1, 31-day operability test on January 8, 2018
(2) Reactor recirculation motor generator set B surveillance testing on February 17, 2018

In-service (1 Sample)

(1) Reactor core isolation cooling quarterly in-service surveillance test on March 29, 2018

Reactor Coolant System Leak Detection (1 Sample)

(1) Drywell unidentified leakage integrator functional test and calibration on February 20, 2018

71114.04 - Emergency Action Level and Emergency Plan Changes

The inspector evaluated two submitted Emergency Action Level and Emergency Plan changes in-office on January 30, 2018, and March 12, 2018. This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Drill/Training Evolution (1 Sample)

The inspectors evaluated the licensed operator training scenario in the simulator control room on January 23,

RADIATION SAFETY

71124.02 - Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls

Radiological Work Planning (1 Sample)

The inspectors evaluated the licensees radiological work planning by reviewing the following activities:

(1) 2016-01, refueling outage 29 control rod drive mechanism replacements
(2) 2016-03, reactor water cleanup pump B replace power frame
(3) 2016-05, RE-29 refuel floor activities
(4) 2016-12, RE-29, in-service inspection and flow accelerated corrosion exams
(5) 2016-23, reactor recirculation pump A motor, impeller, and seal
(6) 2017-01, spent fuel pool clean-up project (Online)

Verification of Dose Estimates and Exposure Tracking Systems (1 Sample)

The inspectors evaluated dose estimates and exposure tracking.

71124.04 - Occupational Dose Assessment

Source Term Characterization (1 Sample)

The inspectors evaluated the licensees source term characterization.

External Dosimetry (1 Sample)

The inspectors evaluated the licensees external dosimetry program.

Internal Dosimetry (1 Sample)

The inspectors evaluated the licensees internal dosimetry program.

Special Dosimetric Situations (1 Sample)

The inspectors evaluated the licensees performance for special dosimetric situations.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below.

=

(1) IE01: Unplanned Scrams per 7000 Critical Hours Sample (January 1,2017, through December 31, 2017)
(2) IE03: Unplanned Power Changes per 7000 Critical Hours Sample (January 1, 2017, through December 31, 2017)

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Both emergency diesel generators declared inoperable due to light bulb socket deficiencies

71153 - Follow-up of Events and Notices of Enforcement Discretion Events

The inspectors evaluated the failure of the primary alert and notification system and the licensees response on March 16,

INSPECTION RESULTS

Licensee Identified Non-Cited Violation 71152 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part, that for those systems, structures, and components to which this appendix applies, Design control measures shall provide for verifying or checking the adequacy of design.

Contrary to the above, between September 2003, and December 19, 2017, the licensee failed to verify or check the adequacy of design of quality-related components associated with the Division 1 and 2 emergency diesel generator 125 Vdc control power circuits. Specifically, in 2003, the licensee modified the design of the control power circuit through Part Evaluation (PE) 4222806 and replaced 24 original light bulb lamp assemblies with a different style of light bulb and a carbon film dropping resistor (vs. the original wire-wound design).

This change created an unrecognized vulnerability that left the affected portions of the circuit with dropping resistors that provided insufficient protection from shorting due to indication light bulb failures. As a result, on December 19, 2017, the licensee declared both emergency diesel generators inoperable due to the design vulnerability.

Significance/Severity Level: The finding created a design vulnerability in the emergency diesel generator control power circuits, and resulted in the Division 1 and 2 emergency diesel generators being declared inoperable at the time of discovery. Although the emergency diesel generators were declared inoperable, subsequent licensee analysis determined that the system retained its function, and maintained a reasonable expectation of operability while the design deficiencies existed. Accordingly, the inspectors assessed the significance of this finding in accordance with Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings at Power, dated June 19, 2012, and determined this finding was of very low safety significance (Green) because it was a deficiency affecting the design or qualification of a mitigating structure, system, or component (SSC), but the SSC maintained its operability.

Corrective Action Reference(s): Immediate corrective actions included compensatory measures to remove light bulbs from the vulnerable lamp assemblies in order to eliminate the shorting hazard. This issue was entered into the licensees corrective action program as Condition Report CR-CNS-2017-07513, and the licensee initiated a root cause evaluation.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On February 15, 2018, the inspectors presented the occupational radiation protection inspection results to Mr. J. Dent, Jr., Site Vice President and Chief Nuclear Officer, and other members of the licensee staff.

On March 12, 2018, the inspectors presented the results of the inspection of changes to the Cooper Nuclear Station emergency plan and emergency action levels to Mr. J. Stough, Manager, Emergency Preparedness, and other members of the licensee staff.

On April 16, 2018, the inspectors presented the quarterly resident inspector inspection results to Mr. J. Kalamaja, General Manager Plant Operations, and other members of the licensee staff.

DOCUMENTS REVIEWED

71111.01 - Adverse Weather Protection

Miscellaneous Documents

Title

Date

CNS Winter Weather Plan

January 10.

2018

List of Surveillance Procedures With Drop Dead Dates in the Next 5 Days

January 10,

2018

Procedures

Number

Title

Revision

2.1.11.1

Turbine Building Data

2

2.1.11.3

Radwaste and Augmented Radwaste Building Data

103

2.1.14

Seasonal Weather Preparations

5.1WEATHER

Operation During Weather Watches and Warnings

Condition Reports (CR-CNS-)

2018-00004

2018-00198

2018-00263

2018-00284

2018-00621

2018-00744

71111.04 - Equipment Alignment

Drawings

Number

Title

Revision

KSV46-5

Lube Oil Schematic

Miscellaneous Documents

Number

Title

Revision/Date

SWBP A Replacement Protected Equipment Program

Tracking Form

January 8,

2018

2031

Flow Diagram - Reactor Building - Closed Cooling Water

System, Sheet 2

N65

2040

Flow Diagram - Residual Heat Removal System Loop B,

Sheet 2

2077

Flow Diagram - Diesel Gen. Bldg. Service Water, Starting

Air, Fuel Oil, Sump System & Roof Drains

N78

Miscellaneous Documents

Number

Title

Revision/Date

VM-0245

Cooper Bessemer Diesel Generator Vendor Manual

Procedures

Number

Title

Revision

2.2A.DG.DIV1

Standby AC Power System (Diesel Generator) Component

Checklist (DIV 1)

2.2A.DG.DIV2

Standby AC Power System (Diesel Generator) Component

Checklist (DIV 2)

2.2A.REC.DIV2

Reactor Equipment Cooling Water System Component

Checklist (DIV 2)

2.2A.REC.DIV3

Reactor Equipment Cooling Water System Common

Divisional Component Checklist

2.2A.RHR.DIV2

Residual Heat Removal System Component Checklist

2.2B.DG.DIV2

Standby AC Power System (Diesel Generator) Instrument

Valve Checklist (DIV 2)

2.2B.REC.DIV2

Reactor Equipment Cooling Water System Instrument Valve

Checklist (DIV 2)

Condition Reports (CR-CNS-)

2018-01676

2018-01683

Work Orders

5145546

5167608

201413

71111.05 - Fire Protection

Drawings

CNS-FP-218

CNS-FP-236

CNS-FP-237

CNS-FP-245

Miscellaneous Documents

Number

Title

18-0006

Transient Combustible Permit

BCP-2017-0228

Barrier Control Permit

BCP-2018-0025

Barrier Control Permit

Procedures

Number

Title

Revision

0-BARRIER-

MAPS

Barrier Maps

0-BARRIER-

MISC

Miscellaneous Buildings

0-BARRIER-

REACTOR

Reactor Building

0-BARRIER-

TURBINE

Turbine Building

0.23

CNS Fire Protection Plan

2.3.1

General Alarm Procedure

15.FP.309

Fire Protection Manual Pull Station Functional Test

Condition Reports (CR-CNS-)

2018-01616

2018-01625

2018-01774

2018-01782

2018-01793

2018-01823

Work Orders

5167486

231480

71111.06 - Flood Protection Measures

Miscellaneous Documents

Number

Title

Revision

BCP-2017-0238

Barrier Control Permit

NEDC 09-102

Internal Flooding - HELB, MELB, and Feedwater Line

Break

Work Orders

5167308

5167485

71111.07 - Heat Sink Performance

Procedures

Number

Title

Revision

7.2.42.3

Heat Exchanger Tube Plugging

Procedures

Number

Title

Revision

13.17.2

Thermal Performance Test Procedure for Residual Heat

Removal Heat Exchangers

Condition Reports (CR-CNS-)

2018-00321

71111.11 - Licensed Operator Requalification Program and Licensed Operator

Performance

Miscellaneous Documents

Number

Title

Revision/Date

2018 1st Quarter Downpower; Just In Time Training

Initiation Form

January 14,

2018

DEP Performance Evaluation and Data Collection Form -

Scenario SKL052-52-17

January 23,

2018

Operations Pre-job Brief - Single Loop Operation Evolution

February 16,

2018

EPIP 5.7.1

Emergency Classification

EPIP 5.7.2

Emergency Director EPIP

SKL052-52-17

Licensed Operator Requalification Exam Scenario 17

January 3,

2018

Procedures

Number

Title

Revision

2.1.10

Station Power Changes

114

2.2.68.1

Reactor Recirculation System Operations

2.4RR

Reactor Recirculation Abnormal

Condition Reports (CR-CNS-)

2018-00892

2018-00896

2018-00898

2018-00914

2018-00919

2018-00921

71111.12 - Maintenance Effectiveness

Miscellaneous Documents

Number

Title

Revision

DG-PF01

Maintenance Rule Function DG-PF01 Performance Criteria

Basis Document

DGHV-PF04

Maintenance Rule Function DGHV-PF04 Performance

Criteria Basis Document

DGSA-PF01

Maintenance Rule Function DGSA-PF01 Performance

Criteria Basis Document

Procedures

Number

Title

Revision

3-EN-DC-204

Maintenance Rule Scope and Basis

3C1

3-EN-DC-206

Maintenance Rule (a)(1) Process

3C2

7.3.1.19

GE IJCV-51A/IFCV-51AD Overcurrent Relay Testing and

Maintenance

Condition Reports (CR-CNS-)

2000-02070

2015-06608

2016-00141

2016-03335

2017-00551

2017-01168

2017-02533

2017-02538

2017-04451

2017-05821

2017-06408

2018-00685

2018-00832

Work Orders

5115005

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Miscellaneous Documents

Number

Title

Revision/Date

DG2 LCO Protected Equipment Program Tracking Form

March 22,

2018

Div 1 DG Maintenance Window Protected Equipment

Program Tracking Form

February 6,

2018

Remain in Service List for Div 1 DG Work Window

SW-MOV-651 Maintenance Protected Equipment Program

Tracking Form

January 20,

2018

Miscellaneous Documents

Number

Title

Revision/Date

SWBP A Replacement Protected Equipment Program

Tracking Form

January 8,

2018

SWBP D Maintenance Window Protected Equipment

Program Tracking Form

January 16,

2018

11-198

Cooper Nuclear Station Service Water System Analysis

Procedures

Number

Title

Revision

0-CNS-WM-104

On-Line Schedule Risk Assessment

0-CNS-WM-

104A

On-Line Fire Risk Management Actions

0-PROTECT-

EQP

Protected Equipment Program

2.1.1

Startup Procedure

190

2.1.10

Station Power Changes

114

2.1.4.3

Power Reduction to <25/30%

2.2.68.1

Reactor Recirculation System Operations

2.2.71

Service Water System

2

2.3_A-4

Annunciator Response Procedure - Panel A-4

7.0.1.7

Troubleshooting Plant Equipment

Condition Reports (CR-CNS-)

2018-00138

2018-00291

2018-00292

2018-00328

2018-00341

2018-00342

2018-00352

2018-00371

2018-00375

2018-00376

2018-00377

2018-00461

2018-00541

2018-00657

2018-00658

2018-01597

2018-01649

Work Orders

5145546

5167094

5167469

5167606

5175025

201054

201413

203083

213083

231297

71111.15 - Operability Determinations and Functionality Assessments

Miscellaneous Documents

Number

Title

Revision

CNS Inservice Testing Basis Document

Failure Modes and Effects Analysis - SW-TE-387B

Indicated Flow with SW-MOV-651MV Closed

2036

Reactor Building Service Water System, Sheet 1

A3

2036

Control Building Service Water System, Sheet 4

PAD 121987

Process Applicability Determination for Isolation of REC

Division 2 SW Flow Path

Procedures

Number

Title

Revision

6.2SW.101

Service Water Surveillance Operation, Div 2 (IST)

Condition Reports (CR-CNS-)

2017-03717

2017-05742

2017-05797

2017-05819

2017-06869

2018-00007

2018-00122

2018-00142

2018-00182

2018-00299

2018-00342

2018-00354

2018-00362

2018-00459

2018-00461

2018-00538

2018-01621

2018-01644

2018-01651

Work Orders

206535

71111.18 - Plant Modifications

Miscellaneous Documents

Number

Title

Revision/Date

2036

Reactor Building Service Water System, Sheet 1

A3

2036

Control Building Service Water System, Sheet 4

EE 2013-04

RHR SWBP FCU 50.59 Inadequate for USAR Change LCR

93-10

LCR 93-0010

Specify a Summer Design Temperature of 131°F for the

RHR SWBP Room

February 5,

1993

Miscellaneous Documents

Number

Title

Revision/Date

NEDC 92-063

Maximum SWBP Room Temperatures w/ No Cooling From

Control Bldg HVAC

NEDC 92-064

Transient Temperature Rise in SWBP Room After Loss of

Cooling

3C2

PAD 121987

Process Applicability Determination for Isolation of REC

Division 2 SW Flow Path

TCC-5231919

Temporary Configuration Change - Replacement of

SW-V-126 With Blind Flange Spool Piece

UCR 98-019

USAR Change Request: SWBP Fan Coil Unit Description

Removal

April 28, 1998

Procedures

Number

Title

Revision

2.2.71

Service Water System

2

2.3_R-1

Panel R - Annunciator R-1

17, 18

7.3.50.4

SW-650MV and SW-651MV Flow Adjustment

Condition Reports (CR-CNS-)

2017-06120

2017-06196

2017-06241

2017-07601

2018-00342

2018-00362

2018-00461

Work Orders

231297

231480

232377

71111.19 - Post-Maintenance Testing

Drawings

Number

Title

Revision

454223426

Emergency Diesel Generator Composite Control Air

Schematic

Miscellaneous Documents

Number

Title

Revision

11445276

Notification

IST RAL

IST Reference/Acceptance Limits Data File

246

Procedures

Number

Title

Revision

2.2.20.1

Diesel Generator Operations

69, 70

6.1DG.101

Diesel Generator 31 Day Operability Test (IST)(DIV 1)

6.1HV.602

Air Flow Test of Fan Coil Unit HV-DG-1C (DIV 1)

6.1SWBP.101

RHR Service Water Booster Pump Flow Test and Valve

Operability Test (DIV 1)

6.2HV.603

Air Flow Test of Fan Coil Unit for FC-R-1H (Div 2)

6.2SW.101

Service Water Surveillance Operation Div 2 (IST)

6.SW.102

Service Water System Post-LOCA Flow Verification

7.0.5

CNS Post-Maintenance Testing

7.0.8.1

System Leakage Testing

7.3.50.4

SW-650MV and SW-651MV Flow Adjustment

14.17.1

DG-1 Annual Calibration

14.28.1

Service Water System Instrument Calibration

Condition Reports (CR-CNS-)

2016-07426

2018-00388

2018-00342

2018-00425

2018-00461

2018-00521

2018-00711

2018-00715

2018-00751

2018-00765

2018-01714

2018-01715

Work Orders

4832440

5145546

5145577

5167078

5167385

5167606

5167617

5169763

5169764

5169985

5184976

5188894

201054

201413

231297

231480

71111.20 - Refueling and Other Outage Activities

Procedures

Number

Title

Revision

2.1.4

Normal Shutdown

157

6.RCS.601

Technical Specification Monitoring of RCS

Heatup/Cooldown Rate

71111.22 - Surveillance Testing

Miscellaneous Documents

Number

Title

Revision/Date

List of Drywell Possible Leak Sources

January 23,

2018

Summary of Primary Containment Sample Results for

Current Fuel Cycle

February 2,

2018

EC 18-003

6.LOG.601 Revision to Address Effects of Voiding on

Drywell Floor Drain Sump Flow Indication

0, 1

Procedures

Number

Title

Revision

6.DWLD.301

Drywell Floor Drain Sump Flow Measuring System

Functional Test

6.DWLD.302

Drywell Floor Drain Sump 1F Flow Loop Channel

Calibration

6.LOG.601

Daily Surveillance Log - Modes 1, 2, and 3

130, 131, 132

6.RCIC.102

RCIC IST and 92 Day Test

6.RR.601B

RRMG B Positioner Maintenance and Setting Electrical and

Mechanical Stops

6.1DG.101

Diesel Generator 31 Day Operability Test (IST)(DIV 1)

15.SUMP.101

Sump Pump Operability Test

EN-OP-109

Drywell Leakage

Condition Reports (CR-CNS-)

2012-07093

2017-06119

2017-06820

2018-00123

2018-00127

2018-00310

2018-00336

2018-00340

2018-00436

2018-00905

2018-00907

Work Orders

5047898

5099572

5101207

5103351

5114307

5115900

23387

5167175

5177984

5190520

231292

71114.04 - Emergency Action Level and Emergency Plan Changes

Miscellaneous Documents

Number

Title

Revision

Cooper Nuclear Station Emergency Plan

EPIP 5.7.1

Emergency Classification

71114.06 - Drill Evaluation

Miscellaneous Documents

Number

Title

Revision/Date

DEP Performance Evaluation and Data Collection Form -

Scenario SKL052-52-17

January 23,

2018

EPIP 5.7.1

Emergency Classification

EPIP 5.7.2

Emergency Director EPIP

SKL052-52-17

Licensed Operator Requalification Exam Scenario 17

January 3,

2018

71124.02 - Occupational ALARA Planning and Controls

ALARA Committee Meeting Minutes

Meeting

Title

Date

February

Meeting Minutes

February

2017

August

Meeting Minutes

August 2017

October

Meeting Minutes

October 2017

December

Meeting Minutes

December

2017

ALARA Planning, In-Progress Reviews, and Post-Job Reviews

Number

Title

Date

2016-01

RE29 CRDM Replacements

November 5,

2016

2016-03

RWCU Pump B Replace Power Frame

June 8, 2016

2016-05

RE-29 Refuel Floor Activities

November 5,

2016

2016-12

RE29, ISI and FAC Exams

December

14, 2016

ALARA Planning, In-Progress Reviews, and Post-Job Reviews

Number

Title

Date

2016-23

RR-A Motor, Impeller and Seal

November 6,

2016

2017-01

Spent Fuel Pool Clean-Up Project (Online)

December

11, 2017

Audits and Self-Assessments

Number

Title

Date

LO-2017-0204

Focused Self-Assessment:

Occupational ALARA Planning and Controls

December 1,

2017

Miscellaneous Documents

Title

5-Year CRE Reduction Plan (2018-2022)

RE29 Radiological Post Outage Report

2017 Cooper Nuclear Station ALARA Program

Procedures

Number

Title

Revision

9.ALARA.4

Radiation Work Permits

9.ALARA.8

ALARA Document Control

9.EN-RP-110

ALARA Program

9.EN-RP-110-03 Collective Radiation Exposure (CRE) Reduction Guidelines

9.EN-RP-110-04 Radiation Protection Risk Assessment Process

9.EN-RP-110-05 ALARA Planning and Controls

9.EN-RP-110-06 Outage Dose Estimating and Tracking

Radiation Work Permits

Number

Title

Revision

2016-014

Refuel Floor Activities

2016-055

RWCU-P-B Replacement and RWCU-CV11 Inspection

2016-060

Refuel Floor General SWP Work

2016-406

CRDMs Support - Support Work - RWP (NO ENTRY

ALLOWED INTO AN AREA POSTED SWP)

Radiation Work Permits

Number

Title

Revision

2016-506

Under vessel CRDMs Change outs Also Keyway Worker

and RP Under vessel Coverage

2016-523

RR-A Motor and Impeller Replacement in RE29 - SWP

2017-107

2017 SFP Cleanup

Condition Reports (CR-CNS-)

2016-06415

2016-06567

2016-07197

2016-08576

2017-02319

2017-04201

2017-04896

2017-04899

2017-05538

2017-06603

71124.04 - Occupational Dose Assessment

Audits and Self-Assessments

Number

Title

Date

Radiation Protection Program Annual Report

2016

16-05

QA Audit of Radiological Controls

August 10,

2016

LO-2017-0204

Focused Self-Assessment:

Occupational Dose Assessment

December 1,

2017

Miscellaneous Documents

Title

Date

2016 DAW Part 61 Analysis

March 29,

2017

100555-0 National Voluntary Laboratory Accreditation Program (NVLAP)

Certificate for Mirion Technologies

July 1, 2017

Internal Dose Assessment Prospectus

2017

Internal Dose Assessment Prospectus

2018

Multiplication Factor for the Merlin Gerin DMC 2000S (White Paper)

March 22,

2012

Procedures

Number

Title

Revision

9.ALARA.1

Personnel Dosimetry and Occupational Radiation Exposure 47

9.ALARA.13

Radiation Worker and Tour Group Dosimetry Management

Procedures

Number

Title

Revision

9.EN-RP-102

Radiological Control

9.EN-RP-104

Personnel Contamination

9.EN-RP-110-05 ALARA Planning and Controls

9.EN-RP-122

Alpha Monitoring

9.EN-RP-203

Dose Assessment

9.EN-RP-205

Prenatal Monitoring

9.EN-RP-206

Dosimeter of Legal Record Quality Assurance

9.EN-RP-208

Whole Body Counting and In-Vitro Bioassay

9.EN-RP-210

Area Monitoring Program

9.EN-RP-311

Self-Reading Dosimeters

9.RADOP.1

Radiation Protection at CNS

9.RADOP.5

Airborne Radioactivity Sampling

Condition Reports (CR-CNS-)

2016-01718

2016-04881

2016-07077

2017-04996

2017-05538

71151 - Performance Indicator Verification

Procedures

Number

Title

Revision

EN-LI-114

Performance Indicator Process

5C2

71152 - Problem Identification and Resolution

Miscellaneous Documents

Number

Title

Revision/Date

3059

EE-PNL-DG1 125VDC Load & Fuse Schedule, Sheet 11

3059

EE-PNL-DG2 125VDC Load & Fuse Schedule, Sheet 12

EE 2018-001

Characterization of Potential Risk of EDG Indicating Light

Failure

0, 1

G5-262-743

Emergency Diesel Generator #1 Electrical Schematic

Sheet 1

Miscellaneous Documents

Number

Title

Revision/Date

G5-262-743

Emergency Diesel Generator #2 Electrical Schematic

Sheet 1

NPP-61852

Failure Analysis of a Lamp Assembly

November

27, 2017

PAD 121981

Process Applicability Determination - Caution Order:

DG-1-DG-SW-DG2(43CM) Green Ind

PAD 121982

Process Applicability Determination - Caution Order:

DG-1-DG #1 Bulb Control

Condition Reports (CR-CNS-)

2017-01168

2017-05434

2017-05456

2017-06219

2017-07078

2017-07513

2018-00124

2018-00125

2018-00685

2018-00832

2018-01281

Work Orders

26885

71153 - Follow-up of Events and Notices of Enforcement Discretion

Procedures

Number

Title

Revision

2.0.5

Reports to NRC Operations Center

NRC Request for Information

System: Emergency Diesel Generators, Divisions 1 and 2

CD Date Requested by: January 2, 2018

Date Range of Document Request: December 31, 2015 - Current

Please provide the following documents:

1. Copies of all root and apparent cause evaluations performed on this system.

2. Summary list of all condition reports written on this system, sorted by CR classification

3. List of all surveillances performed on this system, sortable by component if possible.

4. Provide copies of the three most recently completed quarterly surveillances for both

divisions

5. List of all corrective maintenance work orders, with description of work, performed on this

system

6. Provide a list of control room deficiencies associated with this system

7. Copies of ODMIs, OWA/OWBs, prompt operability evaluations, and standing orders

associated with this system

8. Summarized list of all Maintenance Rule equipment issues evaluated for the system,

(including their conclusions), copies of each MRule evaluation for the system, and the

MRule Basis Document(s) for the system

9. List of all work orders, with description of work, planned for this system within the next year

10. Provide a list and description of overdue PMs, deferred PMs, and PM change requests for

this system

11. Provide copies of maintenance rule functional failure assessmentsregardless of the

resultperformed on these systems. Include CR number for each item on the list.

2. System design calculations for DG loading capabilities

13. Provide fire impairments associated with this system

14. Provide copies of any QA audits or self-assessments associated with this system

15. Copies of vendor manuals, drawings (P&IDs), and system training manuals

16. System health reports and system engineering logs for this system

17. List and description of temporary modifications; completed ECs (December 31, 2015 -

Current); and planned ECs (within the next year) associated with this system

18. Schedule of activities (Fragnets) for the planned AOT for the Division 1 and 2 DGs

scheduled for the work weeks of 1806 and 1812.

The following items are requested for the

Occupational Radiation Safety Inspection

at Cooper Nuclear Station

(February 12-16, 2018)

Integrated Report 2018001

Inspection areas are listed in the attachments below.

Please provide the requested information on or before January 25, 2018.

Please submit this information using the same lettering system as below. For example, all

contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled

1-A, applicable organization charts in file/folder 1-B, etc.

If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at

least 30 days later than the onsite inspection dates, so the inspectors will have access to the

information while writing the report.

In addition to the corrective action document lists provided for each inspection procedure listed

below, please provide updated lists of corrective action documents at the entrance meeting.

The dates for these lists should range from the end dates of the original lists to the day of the

entrance meeting.

If more than one inspection procedure is to be conducted and the information requests appear

to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which

file the information can be found.

If you have any questions or comments, please contact John ODonnell at (817) 200-1441 or

john.odonnell@nrc.gov. The other inspector will be Shawn Money.

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget,

control number 3150-0011.

2.

Occupational ALARA Planning and Controls (71124.02)

Date of Last Inspection:

October 3, 2016

A.

List of contacts and telephone numbers for ALARA program personnel

B.

Applicable organization charts

C.

Copies of audits, self-assessments, and LERs, written since date of last inspection,

focusing on ALARA

D.

Procedure index for ALARA Program

E.

Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures may be requested by number after the inspector reviews

the procedure indexes.

1. ALARA Program

2. ALARA Committee

3. Radiation Work Permit Preparation

F.

A summary list of corrective action documents (including corporate and sub-tiered

systems) written since date of last inspection, related to the ALARA program. In addition

to ALARA, the summary should also address Radiation Work Permit violations,

Electronic Dosimeter Alarms, and RWP Dose Estimates

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

G.

List of work activities greater than 1 rem, since date of last inspection,

Include original dose estimate and actual dose.

H.

Site dose totals and 3-year rolling averages for the past 3 years (based on dose of

record)

I.

Outline of source term reduction strategy

J.

If available, provide a copy of the ALARA outage report for the most recently completed

outages for each unit

K.

Please provide your most recent Annual ALARA Report.

4. Occupational Dose Assessment (Inspection Procedure 71124.04)

Date of Last Inspection:

March 23, 2016

A.

List of contacts and telephone numbers for the following areas:

1. Dose Assessment personnel

B.

Applicable organization charts

C.

Audits, self-assessments, vendor or NUPIC audits of contractor support, and LERs

written since date of last inspection, related to:

1. Occupational Dose Assessment

D.

Procedure indexes for the following areas:

1. Occupational Dose Assessment

E.

Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures will be requested by number after the inspector reviews

the procedure indexes.

1. Radiation Protection Program

2. Radiation Protection Conduct of Operations

3. Personnel Dosimetry Program

4. Radiological Posting and Warning Devices

5. Air Sample Analysis

6. Performance of High Exposure Work

7. Declared Pregnant Worker

8. Bioassay Program

F.

List of corrective action documents (including corporate and sub-tiered systems) written

since date of last inspection, associated with:

1. National Voluntary Laboratory Accreditation Program (NVLAP)

2. Dosimetry (TLD/OSL, etc.) problems

3. Electronic alarming dosimeters

4. Bioassays or internally deposited radionuclides or internal dose

5. Neutron dose

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

G.

List of positive whole body counts since date of last inspection, names redacted if

desired

H.

Part 61 analyses/scaling factors

I.

The most recent NVLAP accreditation report or, if dosimetry is provided by a vendor, the

vendors most recent results

ML18128A094

SUNSI Review

By: CHY/rdr

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

Keyword:

NRC-002

OFFICE

ASRI:DRP/C

RI:DRP/C

BC:DRS/EB1

BC:DRS/EB2

BC:DRS/OB

BC:DRS/PSB2

NAME

RKumana

MStafford

TFarnholtz

JDrake

VGaddy

HGepford

SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/

DATE

4/23/18

4/23/18

04/23/2018

4/23/2018

4/24/18

4/23/18

OFFICE

TL:DRS/IPAT

SPE:DRP/C

BC:DRP/C

NAME

GGeorge

CYoung

JKozal

SIGNATURE

/RA/

/RA/

/RA/

DATE

4/24/2018

4/27/2018

5/08/2018

May 8, 2018

Mr. John Dent, Jr.

Vice President-Nuclear and CNO

Nebraska Public Power District

Cooper Nuclear Station

2676 648A Avenue

P.O. Box 98

Brownville, NE 68321

SUBJECT:

COOPER NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT

05000298/2018001

Dear Mr. Dent:

On March 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at your Cooper Nuclear Station. On April 16, 2018, the NRC inspectors discussed the results of

this inspection with Mr.

J. Kalamaja, General Manager Plant Operations, and other members of

your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealed findings were identified during this inspection.

However, inspectors documented a licensee-identified violation, which was determined to be of

very low safety significance, in this report. The NRC is treating this violation as a non-cited

violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

J. Dent Jr.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

Sincerely,

/RA/

Jason Kozal, Chief

Project Branch C

Division of Reactor Projects

Docket No. 50-298

License No. DPR-46

Enclosure:

Inspection Report 05000298/2018001

w/ Attachments:

1. Documents Reviewed

2. NRC Request for Information

3. Occupational Radiation Safety Inspection

Request for Information

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number:

05000298

License Number:

DPR-46

Report Number:

05000298/2018001

Enterprise Identifier: I-2018-001-0003

Licensee:

Nebraska Public Power District

Facility:

Cooper Nuclear Station

Location:

2676 648A Ave

Brownville, NE

Inspection Dates:

January 1, 2018 to March 31, 2018

Inspectors:

P. Voss, Senior Resident Inspector
R. Kumana, Acting Senior Resident Inspector
M. Stafford, Resident Inspector
P. Elkmann, Senior Emergency Preparedness Inspector
S. Money, Health Physicist
J. ODonnell, CHP, Health Physicist

Approved By:

J. Kozal, Branch Chief

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Cooper Nuclear Station, in accordance

with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for

overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-

identified, non-cited violation is documented in report Section 71152.

No findings were identified.

PLANT STATUS

Cooper Nuclear Station began the inspection period at rated thermal power. On

February 16, 2018, the licensee reduced power to 36 percent in order to enter single loop

operation to perform maintenance on reactor recirculation motor generator B, repair condenser

leaks, perform maintenance on control rod drives, and tune a reactor recirculation system motor

generator set. The licensee restored power to 100 percent on February 18, 2018. On

March 11, 2018, the licensee performed a normal shutdown to repair a reactor coolant leak

inside the drywell. The licensee restarted the reactor on March 16, 2018, and resumed full

power operation on March 19, 2018. The licensee maintained full power for the remainder of

the reporting period, except for minor reductions in power to support scheduled surveillances

and rod pattern adjustments.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed plant status activities described in

IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem

Identification and Resolution. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather (1 Sample)

The inspectors evaluated readiness for seasonal extreme weather conditions prior to the

onset of seasonal cold temperatures.

Impending Severe Weather (1 Sample)

The inspectors evaluated readiness for impending adverse weather conditions for a winter

weather advisory on January 10, 2018.

71111.04 - Equipment Alignment

Partial Walkdown (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1) Division 2 residual heat removal during service water booster pump A replacement on

January 12, 2018

(2) Division 2 reactor equipment cooling during Division 1 reactor equipment cooling

maintenance window on January 31, 2018

(3) Emergency diesel generator 2 lube oil during emergency diesel generator 1 work

window on February 7, 2017

(4) Emergency diesel generator 1 starting air during emergency diesel generator 2 work

window on March 22, 2018

71111.05AQ - Fire Protection Annual/Quarterly

Quarterly Inspection (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected

areas:

(1) Reactor building 931 foot elevation, Fire Area RB-M, Zones 3C and 3D on

January 31, 2018

(2) Emergency diesel generator 1, Fire Area DG-A, Zone 14A on February 26, 2018

(3) Condensate pump area, turbine building 882 foot elevation, Fire Area TB-A, Zone 11J

on March 20, 2018

(4) Emergency diesel generator 2, Fire Area DG-B, Zone 14B on March 26, 2018

71111.06 - Flood Protection Measures

Internal Flooding (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the reactor building

931 foot elevation, reactor equipment cooling heat exchanger area on February 22, 2018.

71111.07 - Heat Sink Performance

Heat Sink (1 Sample)

The inspectors evaluated a residual heat removal heat exchanger thermal performance test

on January 17, 2018.

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification (1 Sample)

The inspectors observed and evaluated a licensed operator requalification scenario in the

simulator on January 23, 2018.

Operator Performance (1 Sample)

The inspectors observed and evaluated the quarterly downpower, including entry into single

loop operations, power reduction to 45 percent, and planned trip of reactor recirculation

motor generator set B and the associated pre-job briefs on February 17, 2018.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness (1 Sample)

The inspectors evaluated the effectiveness of routine maintenance activities associated

with the following equipment and/or safety significant functions:

(1) Emergency diesel generator 2 system a(1) evaluation due to exceeding performance

criteria on March 9, 2018

71111.13 - Maintenance Risk Assessments and Emergent Work Control (7 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent

work activities:

(1) Service water booster pump A replacement on January 9, 2018

(2) Service water booster pump D maintenance window on January 17, 2018

(3) Emergent service water valve maintenance due to reactor equipment cooling heat

exchanger B leakage on January 29, 2018

(4) Emergency diesel generator 1 work window on February 6, 2018

(5) Reactor recirculation motor generator set maintenance and single loop operation on

February 17, 2018

(6) Emergent steam leak repair affecting high pressure coolant injection on March 8, 2018

(7) Emergency diesel generator 2 work window on March 23, 2018

71111.15 - Operability Determinations and Functionality Assessments (4 Samples)

The inspectors evaluated the following operability determinations and functionality

assessments:

(1) Jet pump 12 differential pressure reading step change on January 22, 2018

(2) Reactor equipment cooling heat exchanger outlet valve SW-MO-651 indications of

potential leak path on January 22, 2018

(3) Scram discharge volume shielding evaluation on January 25, 2018

(4) Emergency diesel generator 2 field flash resistor insulation issue and extent of condition

for emergency diesel generator 1 on March 23, 2018

71111.18 - Plant Modifications (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Reactor equipment cooling heat exchanger B, SW-V-126 temporary flange on

February 5, 2018

71111.19 - Post Maintenance Testing (5 Samples)

The inspectors evaluated the following post maintenance tests:

(1) Service water booster pump A replacement on January 16, 2018

(2) Post maintenance test for emergency diesel generator 1 system maintenance on

February 20, 2018

(3) South west residual heat removal quad fan coil unit maintenance on February 23, 2018

(4) Unplanned service water valve maintenance due to reactor equipment cooling heat

exchanger B leakage on February 26, 2018

(5) Post maintenance test for emergency diesel generator 2 system maintenance on

March 23, 2018

71111.20 - Refueling and Other Outage Activities (1 Sample)

The inspectors evaluated forced outage activities due to reactor coolant system leakage

from March 12, 2018, to March 16, 2018.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine (2 Samples)

(1) Emergency diesel generator 1, 31-day operability test on January 8, 2018

(2) Reactor recirculation motor generator set B surveillance testing on February 17, 2018

In-service (1 Sample)

(1) Reactor core isolation cooling quarterly in-service surveillance test on March 29, 2018

Reactor Coolant System Leak Detection (1 Sample)

(1) Drywell unidentified leakage integrator functional test and calibration on

February 20, 2018

71114.04 - Emergency Action Level and Emergency Plan Changes (2 Samples)

The inspector evaluated two submitted Emergency Action Level and Emergency Plan

changes in-office on January 30, 2018, and March 12, 2018. This evaluation does not

constitute NRC approval.

71114.06 - Drill Evaluation

Drill/Training Evolution (1 Sample)

The inspectors evaluated the licensed operator training scenario in the simulator control

room on January 23, 2018.

RADIATION SAFETY

71124.02 - Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls

Radiological Work Planning (1 Sample)

The inspectors evaluated the licensees radiological work planning by reviewing the

following activities:

(1) 2016-01, refueling outage 29 control rod drive mechanism replacements

(2) 2016-03, reactor water cleanup pump B replace power frame

(3) 2016-05, RE-29 refuel floor activities

(4) 2016-12, RE-29, in-service inspection and flow accelerated corrosion exams

(5) 2016-23, reactor recirculation pump A motor, impeller, and seal

(6) 2017-01, spent fuel pool clean-up project (Online)

Verification of Dose Estimates and Exposure Tracking Systems (1 Sample)

The inspectors evaluated dose estimates and exposure tracking.

71124.04 - Occupational Dose Assessment

Source Term Characterization (1 Sample)

The inspectors evaluated the licensees source term characterization.

External Dosimetry (1 Sample)

The inspectors evaluated the licensees external dosimetry program.

Internal Dosimetry (1 Sample)

The inspectors evaluated the licensees internal dosimetry program.

Special Dosimetric Situations (1 Sample)

The inspectors evaluated the licensees performance for special dosimetric situations.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below. (2 Samples)

(1)

IE01: Unplanned Scrams per 7000 Critical Hours Sample (January 1,2017, through

December 31, 2017)

(2)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (January 1, 2017,

through December 31, 2017)

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

(1) Both emergency diesel generators declared inoperable due to light bulb socket

deficiencies

71153 - Follow-up of Events and Notices of Enforcement Discretion

Events (1 Sample)

The inspectors evaluated the failure of the primary alert and notification system and the

licensees response on March 16, 2018.

INSPECTION RESULTS

Licensee Identified Non-Cited Violation

71152

This violation of very low safety significance was identified by the licensee and has been

entered into the licensee corrective action program and is being treated as a non-cited

violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part,

that for those systems, structures, and components to which this appendix applies, Design

control measures shall provide for verifying or checking the adequacy of design.

Contrary to the above, between September 2003, and December 19, 2017, the licensee failed

to verify or check the adequacy of design of quality-related components associated with the

Division 1 and 2 emergency diesel generator 125 Vdc control power circuits. Specifically,

in 2003, the licensee modified the design of the control power circuit through Part

Evaluation (PE) 4222806 and replaced 24 original light bulb lamp assemblies with a different

style of light bulb and a carbon film dropping resistor (vs. the original wire-wound design).

This change created an unrecognized vulnerability that left the affected portions of the circuit

with dropping resistors that provided insufficient protection from shorting due to indication light

bulb failures. As a result, on December 19, 2017, the licensee declared both emergency

diesel generators inoperable due to the design vulnerability.

Significance/Severity Level: The finding created a design vulnerability in the emergency

diesel generator control power circuits, and resulted in the Division 1 and 2 emergency diesel

generators being declared inoperable at the time of discovery. Although the emergency

diesel generators were declared inoperable, subsequent licensee analysis determined that

the system retained its function, and maintained a reasonable expectation of operability while

the design deficiencies existed. Accordingly, the inspectors assessed the significance of this

finding in accordance with Inspection Manual Chapter 0609, Appendix A, The Significance

Determination Process (SDP) for Findings at Power, dated June 19, 2012, and determined

this finding was of very low safety significance (Green) because it was a deficiency affecting

the design or qualification of a mitigating structure, system, or component (SSC), but the SSC

maintained its operability.

Corrective Action Reference(s): Immediate corrective actions included compensatory

measures to remove light bulbs from the vulnerable lamp assemblies in order to eliminate the

shorting hazard. This issue was entered into the licensees corrective action program as

Condition Report CR-CNS-2017-07513, and the licensee initiated a root cause evaluation.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On February 15, 2018, the inspectors presented the occupational radiation protection inspection

results to Mr.

J. Dent, Jr., Site Vice President and Chief Nuclear Officer, and other members of

the licensee staff.

On March 12, 2018, the inspectors presented the results of the inspection of changes to the

Cooper Nuclear Station emergency plan and emergency action levels to Mr.

J. Stough,

Manager, Emergency Preparedness, and other members of the licensee staff.

On April 16, 2018, the inspectors presented the quarterly resident inspector inspection results to

Mr.

J. Kalamaja, General Manager Plant Operations, and other members of the licensee staff.

DOCUMENTS REVIEWED

71111.01 - Adverse Weather Protection

Miscellaneous Documents

Title

Date

CNS Winter Weather Plan

January 10.

2018

List of Surveillance Procedures With Drop Dead Dates in the Next 5 Days

January 10,

2018

Procedures

Number

Title

Revision

2.1.11.1

Turbine Building Data

2

2.1.11.3

Radwaste and Augmented Radwaste Building Data

103

2.1.14

Seasonal Weather Preparations

5.1WEATHER

Operation During Weather Watches and Warnings

Condition Reports (CR-CNS-)

2018-00004

2018-00198

2018-00263

2018-00284

2018-00621

2018-00744

71111.04 - Equipment Alignment

Drawings

Number

Title

Revision

KSV46-5

Lube Oil Schematic

Miscellaneous Documents

Number

Title

Revision/Date

SWBP A Replacement Protected Equipment Program

Tracking Form

January 8,

2018

2031

Flow Diagram - Reactor Building - Closed Cooling Water

System, Sheet 2

N65

2040

Flow Diagram - Residual Heat Removal System Loop B,

Sheet 2

2077

Flow Diagram - Diesel Gen. Bldg. Service Water, Starting

Air, Fuel Oil, Sump System & Roof Drains

N78

Miscellaneous Documents

Number

Title

Revision/Date

VM-0245

Cooper Bessemer Diesel Generator Vendor Manual

Procedures

Number

Title

Revision

2.2A.DG.DIV1

Standby AC Power System (Diesel Generator) Component

Checklist (DIV 1)

2.2A.DG.DIV2

Standby AC Power System (Diesel Generator) Component

Checklist (DIV 2)

2.2A.REC.DIV2

Reactor Equipment Cooling Water System Component

Checklist (DIV 2)

2.2A.REC.DIV3

Reactor Equipment Cooling Water System Common

Divisional Component Checklist

2.2A.RHR.DIV2

Residual Heat Removal System Component Checklist

2.2B.DG.DIV2

Standby AC Power System (Diesel Generator) Instrument

Valve Checklist (DIV 2)

2.2B.REC.DIV2

Reactor Equipment Cooling Water System Instrument Valve

Checklist (DIV 2)

Condition Reports (CR-CNS-)

2018-01676

2018-01683

Work Orders

5145546

5167608

201413

71111.05 - Fire Protection

Drawings

CNS-FP-218

CNS-FP-236

CNS-FP-237

CNS-FP-245

Miscellaneous Documents

Number

Title

18-0006

Transient Combustible Permit

BCP-2017-0228

Barrier Control Permit

BCP-2018-0025

Barrier Control Permit

Procedures

Number

Title

Revision

0-BARRIER-

MAPS

Barrier Maps

0-BARRIER-

MISC

Miscellaneous Buildings

0-BARRIER-

REACTOR

Reactor Building

0-BARRIER-

TURBINE

Turbine Building

0.23

CNS Fire Protection Plan

2.3.1

General Alarm Procedure

15.FP.309

Fire Protection Manual Pull Station Functional Test

Condition Reports (CR-CNS-)

2018-01616

2018-01625

2018-01774

2018-01782

2018-01793

2018-01823

Work Orders

5167486

231480

71111.06 - Flood Protection Measures

Miscellaneous Documents

Number

Title

Revision

BCP-2017-0238

Barrier Control Permit

NEDC 09-102

Internal Flooding - HELB, MELB, and Feedwater Line

Break

Work Orders

5167308

5167485

71111.07 - Heat Sink Performance

Procedures

Number

Title

Revision

7.2.42.3

Heat Exchanger Tube Plugging

Procedures

Number

Title

Revision

13.17.2

Thermal Performance Test Procedure for Residual Heat

Removal Heat Exchangers

Condition Reports (CR-CNS-)

2018-00321

71111.11 - Licensed Operator Requalification Program and Licensed Operator

Performance

Miscellaneous Documents

Number

Title

Revision/Date

2018 1st Quarter Downpower; Just In Time Training

Initiation Form

January 14,

2018

DEP Performance Evaluation and Data Collection Form -

Scenario SKL052-52-17

January 23,

2018

Operations Pre-job Brief - Single Loop Operation Evolution

February 16,

2018

EPIP 5.7.1

Emergency Classification

EPIP 5.7.2

Emergency Director EPIP

SKL052-52-17

Licensed Operator Requalification Exam Scenario 17

January 3,

2018

Procedures

Number

Title

Revision

2.1.10

Station Power Changes

114

2.2.68.1

Reactor Recirculation System Operations

2.4RR

Reactor Recirculation Abnormal

Condition Reports (CR-CNS-)

2018-00892

2018-00896

2018-00898

2018-00914

2018-00919

2018-00921

71111.12 - Maintenance Effectiveness

Miscellaneous Documents

Number

Title

Revision

DG-PF01

Maintenance Rule Function DG-PF01 Performance Criteria

Basis Document

DGHV-PF04

Maintenance Rule Function DGHV-PF04 Performance

Criteria Basis Document

DGSA-PF01

Maintenance Rule Function DGSA-PF01 Performance

Criteria Basis Document

Procedures

Number

Title

Revision

3-EN-DC-204

Maintenance Rule Scope and Basis

3C1

3-EN-DC-206

Maintenance Rule (a)(1) Process

3C2

7.3.1.19

GE IJCV-51A/IFCV-51AD Overcurrent Relay Testing and

Maintenance

Condition Reports (CR-CNS-)

2000-02070

2015-06608

2016-00141

2016-03335

2017-00551

2017-01168

2017-02533

2017-02538

2017-04451

2017-05821

2017-06408

2018-00685

2018-00832

Work Orders

5115005

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Miscellaneous Documents

Number

Title

Revision/Date

DG2 LCO Protected Equipment Program Tracking Form

March 22,

2018

Div 1 DG Maintenance Window Protected Equipment

Program Tracking Form

February 6,

2018

Remain in Service List for Div 1 DG Work Window

SW-MOV-651 Maintenance Protected Equipment Program

Tracking Form

January 20,

2018

Miscellaneous Documents

Number

Title

Revision/Date

SWBP A Replacement Protected Equipment Program

Tracking Form

January 8,

2018

SWBP D Maintenance Window Protected Equipment

Program Tracking Form

January 16,

2018

11-198

Cooper Nuclear Station Service Water System Analysis

Procedures

Number

Title

Revision

0-CNS-WM-104

On-Line Schedule Risk Assessment

0-CNS-WM-

104A

On-Line Fire Risk Management Actions

0-PROTECT-

EQP

Protected Equipment Program

2.1.1

Startup Procedure

190

2.1.10

Station Power Changes

114

2.1.4.3

Power Reduction to <25/30%

2.2.68.1

Reactor Recirculation System Operations

2.2.71

Service Water System

2

2.3_A-4

Annunciator Response Procedure - Panel A-4

7.0.1.7

Troubleshooting Plant Equipment

Condition Reports (CR-CNS-)

2018-00138

2018-00291

2018-00292

2018-00328

2018-00341

2018-00342

2018-00352

2018-00371

2018-00375

2018-00376

2018-00377

2018-00461

2018-00541

2018-00657

2018-00658

2018-01597

2018-01649

Work Orders

5145546

5167094

5167469

5167606

5175025

201054

201413

203083

213083

231297

71111.15 - Operability Determinations and Functionality Assessments

Miscellaneous Documents

Number

Title

Revision

CNS Inservice Testing Basis Document

Failure Modes and Effects Analysis - SW-TE-387B

Indicated Flow with SW-MOV-651MV Closed

2036

Reactor Building Service Water System, Sheet 1

A3

2036

Control Building Service Water System, Sheet 4

PAD 121987

Process Applicability Determination for Isolation of REC

Division 2 SW Flow Path

Procedures

Number

Title

Revision

6.2SW.101

Service Water Surveillance Operation, Div 2 (IST)

Condition Reports (CR-CNS-)

2017-03717

2017-05742

2017-05797

2017-05819

2017-06869

2018-00007

2018-00122

2018-00142

2018-00182

2018-00299

2018-00342

2018-00354

2018-00362

2018-00459

2018-00461

2018-00538

2018-01621

2018-01644

2018-01651

Work Orders

206535

71111.18 - Plant Modifications

Miscellaneous Documents

Number

Title

Revision/Date

2036

Reactor Building Service Water System, Sheet 1

A3

2036

Control Building Service Water System, Sheet 4

EE 2013-04

RHR SWBP FCU 50.59 Inadequate for USAR Change LCR

93-10

LCR 93-0010

Specify a Summer Design Temperature of 131°F for the

RHR SWBP Room

February 5,

1993

Miscellaneous Documents

Number

Title

Revision/Date

NEDC 92-063

Maximum SWBP Room Temperatures w/ No Cooling From

Control Bldg HVAC

NEDC 92-064

Transient Temperature Rise in SWBP Room After Loss of

Cooling

3C2

PAD 121987

Process Applicability Determination for Isolation of REC

Division 2 SW Flow Path

TCC-5231919

Temporary Configuration Change - Replacement of

SW-V-126 With Blind Flange Spool Piece

UCR 98-019

USAR Change Request: SWBP Fan Coil Unit Description

Removal

April 28, 1998

Procedures

Number

Title

Revision

2.2.71

Service Water System

2

2.3_R-1

Panel R - Annunciator R-1

17, 18

7.3.50.4

SW-650MV and SW-651MV Flow Adjustment

Condition Reports (CR-CNS-)

2017-06120

2017-06196

2017-06241

2017-07601

2018-00342

2018-00362

2018-00461

Work Orders

231297

231480

232377

71111.19 - Post-Maintenance Testing

Drawings

Number

Title

Revision

454223426

Emergency Diesel Generator Composite Control Air

Schematic

Miscellaneous Documents

Number

Title

Revision

11445276

Notification

IST RAL

IST Reference/Acceptance Limits Data File

246

Procedures

Number

Title

Revision

2.2.20.1

Diesel Generator Operations

69, 70

6.1DG.101

Diesel Generator 31 Day Operability Test (IST)(DIV 1)

6.1HV.602

Air Flow Test of Fan Coil Unit HV-DG-1C (DIV 1)

6.1SWBP.101

RHR Service Water Booster Pump Flow Test and Valve

Operability Test (DIV 1)

6.2HV.603

Air Flow Test of Fan Coil Unit for FC-R-1H (Div 2)

6.2SW.101

Service Water Surveillance Operation Div 2 (IST)

6.SW.102

Service Water System Post-LOCA Flow Verification

7.0.5

CNS Post-Maintenance Testing

7.0.8.1

System Leakage Testing

7.3.50.4

SW-650MV and SW-651MV Flow Adjustment

14.17.1

DG-1 Annual Calibration

14.28.1

Service Water System Instrument Calibration

Condition Reports (CR-CNS-)

2016-07426

2018-00388

2018-00342

2018-00425

2018-00461

2018-00521

2018-00711

2018-00715

2018-00751

2018-00765

2018-01714

2018-01715

Work Orders

4832440

5145546

5145577

5167078

5167385

5167606

5167617

5169763

5169764

5169985

5184976

5188894

201054

201413

231297

231480

71111.20 - Refueling and Other Outage Activities

Procedures

Number

Title

Revision

2.1.4

Normal Shutdown

157

6.RCS.601

Technical Specification Monitoring of RCS

Heatup/Cooldown Rate

71111.22 - Surveillance Testing

Miscellaneous Documents

Number

Title

Revision/Date

List of Drywell Possible Leak Sources

January 23,

2018

Summary of Primary Containment Sample Results for

Current Fuel Cycle

February 2,

2018

EC 18-003

6.LOG.601 Revision to Address Effects of Voiding on

Drywell Floor Drain Sump Flow Indication

0, 1

Procedures

Number

Title

Revision

6.DWLD.301

Drywell Floor Drain Sump Flow Measuring System

Functional Test

6.DWLD.302

Drywell Floor Drain Sump 1F Flow Loop Channel

Calibration

6.LOG.601

Daily Surveillance Log - Modes 1, 2, and 3

130, 131, 132

6.RCIC.102

RCIC IST and 92 Day Test

6.RR.601B

RRMG B Positioner Maintenance and Setting Electrical and

Mechanical Stops

6.1DG.101

Diesel Generator 31 Day Operability Test (IST)(DIV 1)

15.SUMP.101

Sump Pump Operability Test

EN-OP-109

Drywell Leakage

Condition Reports (CR-CNS-)

2012-07093

2017-06119

2017-06820

2018-00123

2018-00127

2018-00310

2018-00336

2018-00340

2018-00436

2018-00905

2018-00907

Work Orders

5047898

5099572

5101207

5103351

5114307

5115900

23387

5167175

5177984

5190520

231292

71114.04 - Emergency Action Level and Emergency Plan Changes

Miscellaneous Documents

Number

Title

Revision

Cooper Nuclear Station Emergency Plan

EPIP 5.7.1

Emergency Classification

71114.06 - Drill Evaluation

Miscellaneous Documents

Number

Title

Revision/Date

DEP Performance Evaluation and Data Collection Form -

Scenario SKL052-52-17

January 23,

2018

EPIP 5.7.1

Emergency Classification

EPIP 5.7.2

Emergency Director EPIP

SKL052-52-17

Licensed Operator Requalification Exam Scenario 17

January 3,

2018

71124.02 - Occupational ALARA Planning and Controls

ALARA Committee Meeting Minutes

Meeting

Title

Date

February

Meeting Minutes

February

2017

August

Meeting Minutes

August 2017

October

Meeting Minutes

October 2017

December

Meeting Minutes

December

2017

ALARA Planning, In-Progress Reviews, and Post-Job Reviews

Number

Title

Date

2016-01

RE29 CRDM Replacements

November 5,

2016

2016-03

RWCU Pump B Replace Power Frame

June 8, 2016

2016-05

RE-29 Refuel Floor Activities

November 5,

2016

2016-12

RE29, ISI and FAC Exams

December

14, 2016

ALARA Planning, In-Progress Reviews, and Post-Job Reviews

Number

Title

Date

2016-23

RR-A Motor, Impeller and Seal

November 6,

2016

2017-01

Spent Fuel Pool Clean-Up Project (Online)

December

11, 2017

Audits and Self-Assessments

Number

Title

Date

LO-2017-0204

Focused Self-Assessment:

Occupational ALARA Planning and Controls

December 1,

2017

Miscellaneous Documents

Title

5-Year CRE Reduction Plan (2018-2022)

RE29 Radiological Post Outage Report

2017 Cooper Nuclear Station ALARA Program

Procedures

Number

Title

Revision

9.ALARA.4

Radiation Work Permits

9.ALARA.8

ALARA Document Control

9.EN-RP-110

ALARA Program

9.EN-RP-110-03 Collective Radiation Exposure (CRE) Reduction Guidelines

9.EN-RP-110-04 Radiation Protection Risk Assessment Process

9.EN-RP-110-05 ALARA Planning and Controls

9.EN-RP-110-06 Outage Dose Estimating and Tracking

Radiation Work Permits

Number

Title

Revision

2016-014

Refuel Floor Activities

2016-055

RWCU-P-B Replacement and RWCU-CV11 Inspection

2016-060

Refuel Floor General SWP Work

2016-406

CRDMs Support - Support Work - RWP (NO ENTRY

ALLOWED INTO AN AREA POSTED SWP)

Radiation Work Permits

Number

Title

Revision

2016-506

Under vessel CRDMs Change outs Also Keyway Worker

and RP Under vessel Coverage

2016-523

RR-A Motor and Impeller Replacement in RE29 - SWP

2017-107

2017 SFP Cleanup

Condition Reports (CR-CNS-)

2016-06415

2016-06567

2016-07197

2016-08576

2017-02319

2017-04201

2017-04896

2017-04899

2017-05538

2017-06603

71124.04 - Occupational Dose Assessment

Audits and Self-Assessments

Number

Title

Date

Radiation Protection Program Annual Report

2016

16-05

QA Audit of Radiological Controls

August 10,

2016

LO-2017-0204

Focused Self-Assessment:

Occupational Dose Assessment

December 1,

2017

Miscellaneous Documents

Title

Date

2016 DAW Part 61 Analysis

March 29,

2017

100555-0 National Voluntary Laboratory Accreditation Program (NVLAP)

Certificate for Mirion Technologies

July 1, 2017

Internal Dose Assessment Prospectus

2017

Internal Dose Assessment Prospectus

2018

Multiplication Factor for the Merlin Gerin DMC 2000S (White Paper)

March 22,

2012

Procedures

Number

Title

Revision

9.ALARA.1

Personnel Dosimetry and Occupational Radiation Exposure 47

9.ALARA.13

Radiation Worker and Tour Group Dosimetry Management

Procedures

Number

Title

Revision

9.EN-RP-102

Radiological Control

9.EN-RP-104

Personnel Contamination

9.EN-RP-110-05 ALARA Planning and Controls

9.EN-RP-122

Alpha Monitoring

9.EN-RP-203

Dose Assessment

9.EN-RP-205

Prenatal Monitoring

9.EN-RP-206

Dosimeter of Legal Record Quality Assurance

9.EN-RP-208

Whole Body Counting and In-Vitro Bioassay

9.EN-RP-210

Area Monitoring Program

9.EN-RP-311

Self-Reading Dosimeters

9.RADOP.1

Radiation Protection at CNS

9.RADOP.5

Airborne Radioactivity Sampling

Condition Reports (CR-CNS-)

2016-01718

2016-04881

2016-07077

2017-04996

2017-05538

71151 - Performance Indicator Verification

Procedures

Number

Title

Revision

EN-LI-114

Performance Indicator Process

5C2

71152 - Problem Identification and Resolution

Miscellaneous Documents

Number

Title

Revision/Date

3059

EE-PNL-DG1 125VDC Load & Fuse Schedule, Sheet 11

3059

EE-PNL-DG2 125VDC Load & Fuse Schedule, Sheet 12

EE 2018-001

Characterization of Potential Risk of EDG Indicating Light

Failure

0, 1

G5-262-743

Emergency Diesel Generator #1 Electrical Schematic

Sheet 1

Miscellaneous Documents

Number

Title

Revision/Date

G5-262-743

Emergency Diesel Generator #2 Electrical Schematic

Sheet 1

NPP-61852

Failure Analysis of a Lamp Assembly

November

27, 2017

PAD 121981

Process Applicability Determination - Caution Order:

DG-1-DG-SW-DG2(43CM) Green Ind

PAD 121982

Process Applicability Determination - Caution Order:

DG-1-DG #1 Bulb Control

Condition Reports (CR-CNS-)

2017-01168

2017-05434

2017-05456

2017-06219

2017-07078

2017-07513

2018-00124

2018-00125

2018-00685

2018-00832

2018-01281

Work Orders

26885

71153 - Follow-up of Events and Notices of Enforcement Discretion

Procedures

Number

Title

Revision

2.0.5

Reports to NRC Operations Center

NRC Request for Information

System: Emergency Diesel Generators, Divisions 1 and 2

CD Date Requested by: January 2, 2018

Date Range of Document Request: December 31, 2015 - Current

Please provide the following documents:

1. Copies of all root and apparent cause evaluations performed on this system.

2. Summary list of all condition reports written on this system, sorted by CR classification

3. List of all surveillances performed on this system, sortable by component if possible.

4. Provide copies of the three most recently completed quarterly surveillances for both

divisions

5. List of all corrective maintenance work orders, with description of work, performed on this

system

6. Provide a list of control room deficiencies associated with this system

7. Copies of ODMIs, OWA/OWBs, prompt operability evaluations, and standing orders

associated with this system

8. Summarized list of all Maintenance Rule equipment issues evaluated for the system,

(including their conclusions), copies of each MRule evaluation for the system, and the

MRule Basis Document(s) for the system

9. List of all work orders, with description of work, planned for this system within the next year

10. Provide a list and description of overdue PMs, deferred PMs, and PM change requests for

this system

11. Provide copies of maintenance rule functional failure assessmentsregardless of the

resultperformed on these systems. Include CR number for each item on the list.

2. System design calculations for DG loading capabilities

13. Provide fire impairments associated with this system

14. Provide copies of any QA audits or self-assessments associated with this system

15. Copies of vendor manuals, drawings (P&IDs), and system training manuals

16. System health reports and system engineering logs for this system

17. List and description of temporary modifications; completed ECs (December 31, 2015 -

Current); and planned ECs (within the next year) associated with this system

18. Schedule of activities (Fragnets) for the planned AOT for the Division 1 and 2 DGs

scheduled for the work weeks of 1806 and 1812.

The following items are requested for the

Occupational Radiation Safety Inspection

at Cooper Nuclear Station

(February 12-16, 2018)

Integrated Report 2018001

Inspection areas are listed in the attachments below.

Please provide the requested information on or before January 25, 2018.

Please submit this information using the same lettering system as below. For example, all

contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled

1-A, applicable organization charts in file/folder 1-B, etc.

If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at

least 30 days later than the onsite inspection dates, so the inspectors will have access to the

information while writing the report.

In addition to the corrective action document lists provided for each inspection procedure listed

below, please provide updated lists of corrective action documents at the entrance meeting.

The dates for these lists should range from the end dates of the original lists to the day of the

entrance meeting.

If more than one inspection procedure is to be conducted and the information requests appear

to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which

file the information can be found.

If you have any questions or comments, please contact John ODonnell at (817) 200-1441 or

john.odonnell@nrc.gov. The other inspector will be Shawn Money.

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget,

control number 3150-0011.

2.

Occupational ALARA Planning and Controls (71124.02)

Date of Last Inspection:

October 3, 2016

A.

List of contacts and telephone numbers for ALARA program personnel

B.

Applicable organization charts

C.

Copies of audits, self-assessments, and LERs, written since date of last inspection,

focusing on ALARA

D.

Procedure index for ALARA Program

E.

Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures may be requested by number after the inspector reviews

the procedure indexes.

1. ALARA Program

2. ALARA Committee

3. Radiation Work Permit Preparation

F.

A summary list of corrective action documents (including corporate and sub-tiered

systems) written since date of last inspection, related to the ALARA program. In addition

to ALARA, the summary should also address Radiation Work Permit violations,

Electronic Dosimeter Alarms, and RWP Dose Estimates

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

G.

List of work activities greater than 1 rem, since date of last inspection,

Include original dose estimate and actual dose.

H.

Site dose totals and 3-year rolling averages for the past 3 years (based on dose of

record)

I.

Outline of source term reduction strategy

J.

If available, provide a copy of the ALARA outage report for the most recently completed

outages for each unit

K.

Please provide your most recent Annual ALARA Report.

4. Occupational Dose Assessment (Inspection Procedure 71124.04)

Date of Last Inspection:

March 23, 2016

A.

List of contacts and telephone numbers for the following areas:

1. Dose Assessment personnel

B.

Applicable organization charts

C.

Audits, self-assessments, vendor or NUPIC audits of contractor support, and LERs

written since date of last inspection, related to:

1. Occupational Dose Assessment

D.

Procedure indexes for the following areas:

1. Occupational Dose Assessment

E.

Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures will be requested by number after the inspector reviews

the procedure indexes.

1. Radiation Protection Program

2. Radiation Protection Conduct of Operations

3. Personnel Dosimetry Program

4. Radiological Posting and Warning Devices

5. Air Sample Analysis

6. Performance of High Exposure Work

7. Declared Pregnant Worker

8. Bioassay Program

F.

List of corrective action documents (including corporate and sub-tiered systems) written

since date of last inspection, associated with:

1. National Voluntary Laboratory Accreditation Program (NVLAP)

2. Dosimetry (TLD/OSL, etc.) problems

3. Electronic alarming dosimeters

4. Bioassays or internally deposited radionuclides or internal dose

5. Neutron dose

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

G.

List of positive whole body counts since date of last inspection, names redacted if

desired

H.

Part 61 analyses/scaling factors

I.

The most recent NVLAP accreditation report or, if dosimetry is provided by a vendor, the

vendors most recent results

ML18128A094

SUNSI Review

By: CHY/rdr

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

Keyword:

NRC-002

OFFICE

ASRI:DRP/C

RI:DRP/C

BC:DRS/EB1

BC:DRS/EB2

BC:DRS/OB

BC:DRS/PSB2

NAME

RKumana

MStafford

TFarnholtz

JDrake

VGaddy

HGepford

SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/

DATE

4/23/18

4/23/18

04/23/2018

4/23/2018

4/24/18

4/23/18

OFFICE

TL:DRS/IPAT

SPE:DRP/C

BC:DRP/C

NAME

GGeorge

CYoung

JKozal

SIGNATURE

/RA/

/RA/

/RA/

DATE

4/24/2018

4/27/2018

5/08/2018