Public Meeting Summary Duane Arnold End-of-Cycle Plant Performance Assessment
ML051370614
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 05/13/2005
From: Burgess B
NRC/RGN-III/DRP/RPB2
To:
References
Download: ML051370614 (4)


Text

May 13, 2005 LICENSEE: Nuclear Management Company FACILITY: Duane Arnold Energy Center

SUBJECT:

SUMMARY

OF THE MAY 9, 2005, MEETING WITH THE NUCLEAR MANAGEMENT COMPANY TO DISCUSS DUANE ARNOLD ENERGY CENTER PERFORMANCE On May 9, 2005, a public meeting was held at the Palo Community Center, Palo, Iowa, between the Nuclear Regulatory Commission (NRC) and Duane Arnold Energy Center staff. The purpose of the meeting was to discuss NRCs assessment of Duane Arnolds performance for the period of January 1, 2004, through December 31, 2004.

During the NRC presentation, an overall assessment of Duane Arnold performance was provided. As explained in the Annual Assessment letter from NRC to Mr. Mark Peifer, Site Vice President, Duane Arnold Energy Center, dated March 2, 2005, reference ADAMS accession number ML050620374, Duane Arnold operated in a manner that preserved public health and safety and fully met all cornerstone objectives. The slides presented that evening by the NRC are available in ADAMS (accession number ML051330332).

Before adjourning the meeting the NRC provided the opportunity for members of the public to ask questions. Questions from the public involved coordination of EOC meetings among the regions and the safety and risk values of a green significance determination program result.

An attached enclosure provides the NRC, licensee, and public attendees at the meeting.

/RA/

Bruce L. Burgess, Chief Branch 2 Division of Reactor Projects Docket No. 50-331 License No. DPR-49

Enclosure:

As stated See Attached Distribution

May 13, 2005 LICENSEE: Nuclear Management Company FACILITY: Duane Arnold Energy Center

SUBJECT:

SUMMARY

OF THE MAY 9, 2005, MEETING WITH THE NUCLEAR MANAGEMENT COMPANY TO DISCUSS DUANE ARNOLD ENERGY CENTER PERFORMANCE On May 9, 2005, a public meeting was held at the Palo Community Center, Palo, Iowa, between the Nuclear Regulatory Commission (NRC) and Duane Arnold Energy Center staff. The purpose of the meeting was to discuss NRCs assessment of Duane Arnolds performance for the period of January 1, 2004, through December 31, 2004.

During the NRC presentation, an overall assessment of Duane Arnold performance was provided. As explained in the Annual Assessment letter from NRC to Mr. Mark Peifer, Site Vice President, Duane Arnold Energy Center, dated March 2, 2005, reference ADAMS accession number ML050620374, Duane Arnold operated in a manner that preserved public health and safety and fully met all cornerstone objectives. The slides presented that evening by the NRC are available in ADAMS (accession number ML051330332).

Before adjourning the meeting the NRC provided the opportunity for members of the public to ask questions. Questions from the public involved coordination of EOC meetings among the regions and the safety and risk values of a green significance determination program result.

An attached enclosure provides the NRC, licensee, and public attendees at the meeting.

/RA/

Bruce L. Burgess, Chief Branch 2 Division of Reactor Projects Docket No. 50-331 License No. DPR-49

Enclosure:

As stated See Attached Distribution DOCUMENT NAME: G:\Branch TSS\EOC Mtg. Notices 2005\Mtg. Summaries\DAEC.wpd To receive a copy of this document, indicate in the box "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII NAME BBurgess:co DATE 05/13/05 OFFICIAL RECORD COPY Duane Arnold Energy Center cc w/encl: E. Protsch, Executive Vice President -

Energy Delivery, Alliant; President, IES Utilities, Inc.

C. Anderson, Senior Vice President, Group Operations J. Cowan, Executive Vice President and Chief Nuclear Officer J. Bjorseth, Site Director D. Curtland, Plant Manager S. Catron, Manager, Regulatory Affairs J. Rogoff, Vice President, Counsel, & Secretary B. Lacy, Nuclear Asset Manager Chairman, Linn County Board of Supervisors Chairperson, Iowa Utilities Board The Honorable Charles W. Larson, Jr.

Iowa State Senator D. McGhee - Department of Public Health

Duane Arnold Energy Center ADAMS Distribution:

WDR DWS RidsNrrDipmIipb GEG KGO GAW1 CAA1 DRPIII DRSIII PLB1 JRK1

Enclosure Meeting Participants NRC:

B. Burgess, Chief, Projects Branch 2 G. Wilson, Senior Resident Inspector, Duane Arnold Licensee:

Mark Peifer, Site Vice President Gary Van Middlesworth, Vice President, Fleet Optimization (Corporate)

John Bjorseth, Site Director Dean Curtland, Plant Manager Steven Catron, Regulatory Affairs Manager Public:

Don Flater R. L. Lam Bruce Bernier Bruce Lacy Dave Dewitte Parveen Baig